Right of Way Utility Relocation Activities (Stages) Flashcards
1
Q
Order of Stages
A
- Need Identified
- Project Initiation
- Permits and Studies
- Right of way
and - PS & E
- Construction
2
Q
In Project Initiation…
A
- Early potholing
- Prepare Data sheet
- impact assessment/avoidance
3
Q
In Need Identified…
A
- CCE
4
Q
In PA & ED ( Permits and studies)…
A
- update data sheet
- verification
- potholing
- identified conflicts
5
Q
PS&E (with ROW)
A
- RCL
- Relocation plans
- NTO
- UA
- ROI
- Issue utility clearance
6
Q
Construction (with ROW)
A
- discovered work
- process bills
- transfer land rights
- close files