Revision Flashcards

1
Q

What are the four sources of conflict?

A

Kindlers four sources of conflict

1) Incomplete/Inaccurate information
- Cause team members to take different course of actions
- Most likely to happen in definition phase
- Particularly impactful in Iterative project deployment phase
- Frustration – loss of commitment
- Have they interpreted same information differently? PM to understand why

2) Inappropriate/Incompatible goals
- Clash over different opinions on what is important
- Stakeholder disagreement in scope – concept phase
- Risk of wasting resource or time

3) Ineffective Methods
- Was the task formulated well?
- Was the criteria clear?
- Were ethical standards followed?
Leader does not practice what they preach
Emphasise team shared values

4) Antagonistic or Negative feelings
- Resentment from poorly managed conflict previously
- People who have been undermined or - feel betrayed
- Loss of commitment
- Loss of belief in PM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a model of addressing conflict?

A

Thomas-Killmann Conflict Mode Instrument
Persons response to conflict along two behaviour traits
- Assertiveness: Individual attempts to satisfy his/her own concerns
- Cooperativeness: Individual attempts to satisfy the other persons concerns

1) Collaborating
Two heads are better than one
Find a mutually beneficial solution
Two or more parties of the same power (Stakeholders)
Definition phase – defining scope
Collaboration builds commitment/interest in objective being successful

2) Accommodating
Kill your enemies with kindness
One person sacrifice their own goals to accommodate the other
Bank credit to use later
PM to PM, one may need the other PM support in future

3) Compromising
Split the difference
Lies somewhere between competing and compromising
Give and take approach
Not ideal for either party

4) Avoiding
Leave well alone
Individual does not pursue their concerns
When one party is of higher power (Sponsor and Team Member)
Little chance of successfully resolving their concern
Raising may cause ill feeling and greater negative impact that leaving alone

5) Competing
Might makes right
If one has enough power may pursue their own goal with no consideration
Scenario health and safety issue – Safety never be compromised (business case)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the seven project elements?

A
  • Time
  • Cost
  • Scope
  • Quality
  • Risk
  • Benefits
  • Safety
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Project VS BAU

A

PROJECTS
Dynamic multi-disciplined teams
Deliver outputs
Respond to change
Managing project, time, cost, quality, scope
Risk Aware

BAU
Fixed specialised skills
Deliver outcomes and benefits
Continuous improvement
Operates within time, cost, quality, and safety constraints
Risk Averse

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Benefits of project management

A

Compliance with governance - Controlled & sustainable

Staff capability - Extends experience of staff, helps equip them for more responsibility

Improved decision making - Adopting standardised approach helps equip stakeholders with information in a timely manner, better understanding of risks and improved decision making

Chance of project failure reduced - Using standardised organisational approach will increase likelihood of project meeting its objectives, increased likelihood benefits are realised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Barriers to using project management

A

Perception functional departments are being scrutinised - Department heads impacted by a project concerned their authority and control of resource is being undermined when a new PM is working in their environment (matrix organisation)

Lack of project management expertise - PM/Steering groups require certain skills. Need to have appropriate hard and soft skills to successfully deliver the project

Communication interfaces - Detailed, structured communication and interaction will be required to avoid confusion and conflict with different parties who have different and competing priorities

Perceived Bureaucracy - Extra work required to formally document the justification and project plan sometimes seen as a waste of time and resource

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Circumstances that may prompt the use of a programme

A

1) When scope of the business change is not fully defined
First project within programme could be a ‘fact find’
Results used to add clarity to the scope of the programme
Paves the way for later projects within programme
Project has defined cost, time , quality so not ideal when change not defined

2) High amount of uncertainty
Splitting overall requirements into several phases uncertainty spread across project
Each project follows same risk management process (PMP)
Earlier projects hopefully mitigate threats and reduce risk level across programme

3) Complex set of dependencies and outputs
Programme manager can divide requirements into projects, defined for each project
If problems arise the PM can escalate to programme manager
Programme manager can decide to solve now or push to next project
Project would require change request, programme doesn’t

4) Programme does not have defined start and end date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Visionary programme?

A

Senior leaders have a specific idea of what they want the organisation to look like when the work is complete

Tend to be transformative programmes (such as restructure)

Strong commitment to the vision and what it will do for the organisation

Most people get behind it as they see no other choice

Senior leader support is very common, top down approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is an Emerging programme?

A

Perhaps the hardest type of programme to get involved with as they do not actually start as programmes but grow into one as default

Happens because business starts a number of projects loosley connected

people realise they are struggling to secure similiar resource and there is an overlap in some outputs or deliverables

Concern benefits are double counted, as a result programme framework emerges so it can be bought into a single leadership structure, better coordination and communication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a mandatory programme?

A

Can happen at any given time (E.G new legislation) that generates multiple projects

resources and budget held centrally so easier to manage as a programme to monitor overall complience

Outcomes likley to be new polocies/procedures

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Benefits of programme management

A

share resource - resources can be used more efficiently throuh integration (E.G software purchased for one project used for anouther)

Consistency

Risk management

complex change management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Barriers of programme management

A

Maintaining focus on life cycle of programme - Programme will very rarley have a defined path

Maintaining alignment of projects - external enviroment may impact stratgic change plans and business cases, programmes may need to realign

conflict of project priority

opposing objectives of stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When is portfolio management required

A

When resources are shared/limited - more pulled from BAU greater negative impact. limited resource due to investment/skills

Focus on moving into a new market

Ensuring business meets new legislation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

VUCA

A

Volatility, uncertainty, complexity, ambiguity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the typical contents of a PMP

A

1) Why - reasons work is required
2) What - objectives, scope, deliverables, acceptance criteria
3) how - may be multiple methods of acheiving stakeholder requirments, chosen method should be documented and reasons for its choice
4) who - key roles and responsabilities and plan defining resource requirments and how will be aquired
5) when - project schedule including key milestones, phasing and detailed timings for activities
6) How much - budgets and cash flows for expenditure
7) Where - geographical location

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who owns the PMP

A

Owned by the project manager
input by stakeholders
approved by project sponsor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

what forms the deployment baseline

A

when the PMP has been reveiwed and approved by stakeholders and sponsor

it is the starting point for progress monitoring

baseline should only be changed with sponsor approval

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How does scope differ between Project, Programme and Portfolios

A

Project - Has defined criteria for time & cost, scope is agreed at the start of the project (linear)

Programme - Broad scope, benefits support strategic objectives

Portfolio - Scope will change as the context of the business change enviroment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

How does sucsess differ between Project, Programme and Portfolios

A

Project - Sucsess measured by stakeholder satisfaction in meeting time, cost quality constraints

programme - degree of benefits delivered

Portfolio - sucsess measured by the ongoing performance of the portfolio

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

How does management differ for project, programmes and portfolios

A

Project - Project managers manage time, cost, scope, quality, risk and benefits

proframme - Programme managers manage the project managers whilst adapting to changing priorities

Portfolio - Portfolio executive teams manage portfolio management staff

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

How does change differ for project, programmes and portfolios

A

Project - Project managers manage any changes via agreed change control

Programme - Programme manager must anticipate any change triggered from external enviroment that may impact strategic chnage

Portfolio - monitor change in all areas of the business to manage relevant inferfaces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How does planning differ for Projects, programmes and portfolios

A

Projects - Plans produced at high level and then refined throughout the lifecycle

Programme - programme plan produced when he programme is being defined, then decomposed into high level project plans

Portfolio - Portfolio managers create and maintain necessary processes and communications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

4 benefits of an Iterative lifecycle

A

1) embracing change - requirments not defined from the outset, possible to add changes to timeboxs
2) Being on time - time is fixed, customer gains confidence and allows for early realisation or confirmation of benefits
3) level of quality protected - customer will set minimum standards for quality, these must be maintained to meet acceptance criteria
4) customer doesnt need everything - not all elements are critical, focus on the must haves within timebox

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

4 types of project reveiws

A

decision gate
autit
post project reveiw
benefits reveiw

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

3 reasons why a project may close early

A

1) failure of business case due to increased costs
2) poorley forecasted benefits
3) realisation risk is too large

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

4 ways outputs of knoweledge mnagemet informs decision making

A

1) help aid the understanding of stsus reports
2) engagement of subject matter experts
3) gathering lessons learned
4) risk identification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

3 Strengths of a functional matrix

A

1) staff are skilled in expertise of their area
2) staff familiar with reporting lines and esculation routes, avoids confusion
3) staff not distracted by line management responsibilities and are focused on targets and objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

3 weeknesses of a functional matrix

A

1) staff are less flexible and would find it hard to adapt
2) demotivated by lack of variety
3) career progression & job security can be limited. Project team dispanded after project close

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

3 Strengths of a project matrix

A

1) project manager will document roles and responsabilities and develop team around these
2) reasource skills and availability easily understood, PM will know where they can find required resource
3) staff see PM as aurthority and can rely on when decisions need to be made

30
Q

3 weeknesses of a project matrix

A

1) team will be dispanded once project over. Skills aquired will be lost
2) required strong resource management
3) If a team memeber is not fully utilised no garentee they will be utilised on anouther

31
Q

2 strengths of a matrix structrue

A

1) PM given authority over staff seconded to the project. Common understanding the PM will build and direct the team to deliver objectives
2) specilist skills maintained in function once project ends

32
Q

2 weeknesses of matrix structure

A

1) staff may be conflicted as to who their lotalty lies - dual authority
2) PM must have strong communication, motivation and negotiation skills to gain commitment from staff

33
Q

Sponsors responsabilities in the concept phase

A

Establish context in which the project will operate

agree team structure and provide resource

sign the business case

34
Q

sponsors responsabilites in definition

A

Agree the contents of the PMP including stated baseline scope, timescale and budget

35
Q

sponsors responsabilities in deployment phase

A

approval at project stage gates

receive reports from PM and take necessary actions

make decisions when outside of PM authority

engage with key stakeholders

36
Q

Sponsors responsability in transition phase

A

accept deliverables

ensure plans for benefit realisation are in place

37
Q

sponsors responsability in adoption phase

A

ensuring formal reveiw of the benefits documented in the business case is undertaken at benefit reveiw dates specified in benefits realisation plan

38
Q

responsibilities of the Project Manager

A

Ensures objectives and responsabilities of the team are properly documented on RACI

facilitates the identification of project resource

facilitates team meetings to reveiw issues, risks and project progress

creates regular status reports

39
Q

Roles and responsabilities of Governance board/steering group

A
  • represent key stakeholders from user and supplier groups
  • assists the sponsor with championing the project
  • input into the business case
40
Q

Roles and responsabilities of Users

A
  • specify the needs of those who will use the projects products
  • helps the sponsor to identifty benefits
  • helps with checking benefits
41
Q

Roles and responsabilities of Product Owner

A

a representative of user/customer who is embedded within agile development team

priratises backlog

42
Q

Benefits of a PMO

A

1) provides a centre of excellence
2) experts in planning tools and risk software
3) maintain corporate consistancy
4) single source of information

43
Q

4 communication methods

A

1) Face to face
2) email
3) video confrencing
4) reports

44
Q

4 barriers to effective communication

A

1) culture and language
2) geography and time zones
3) the enviroment (noise)
4) misinterpratation

45
Q

what is included in a comms plan

A

what
why
who
when
medium

46
Q

Benefits of a communication plan

A

1) sense of ownership
2) less liklihood of conflict
3) reporting of project progress
4) relaying of information - PM responsability

47
Q

Tuckmans stages of team development

A

forming, storming, norming, performing, adjourning

48
Q

challanges of building and leading a virtual team

A

1) building trust
2) culture
3) communication
4) ensuring contribution

49
Q

4 factors that contribute to sucsessful teams

A

1) clearly defined goals
2) clearly defined roles
3) open and clear communication
4) management of conflict

50
Q

Common Estimating methods

A

1) Analogous - History. assumming records have been kept up to date, historical project data and learnings can be used to produce a reasonable estimate - concept phase

2) quantatative or parametric - analysis of data relating to cost, effort or matirial - definition phase

3) Analytical - using a detailed work breakdown structure, Uses the expertise of the team. Reffered to bottom up estimating - definition phase

4) Delphi - generates estimates throguh team or expert concensus. Group all estimate and these are then compared.

51
Q

what is resource smoothing

A

used when time constraints take priroty

objective is to complete work by set date whilst avoiding peaks and troughs in resource demand

may be achvied by delaying work (total float), cannot impact critical path

disadvantage that it reduces flexibility and increases risk of schedule delay

itertaive

52
Q

what is resource leveling

A

linear lifecycle

used when limits on resource availability take priority, no more resource available

impact to critical path, will need to be re-calculated and a new deployment baseline

allowed to delvier late

53
Q

Benefits of complying with project governance

A

1) maintaining stakeholder confidence
2) accountability and responsability
3) stakeholder engagement
4) better decision making

54
Q

what are the stages of benefit management

A

identification
definition
planning
tracking
realisation

55
Q

DOAM

A

Description, observation, attribution, measurment

56
Q

what is requirments management

A

process of capturing, assesing and justifying stakeholder wants and needs

57
Q

what is quality management

A

ensuring outputs, benefits and processes by which they are delivered meet stakeholder requirments and are fit for purpose

58
Q

Steps of the requirments management process

A

gather
analyse
justify
baseline

59
Q

quality management elements

A

quality planning
quality assurance
quality control
continuous improvement

60
Q

elements of the change control process

A

request
initial evaluation
detailed evaluation
recommendation
update plans
implement the change

61
Q

Advantages of change control

A

1) a formal process will ensure accurate record keeping so that stakeholders are all clear on the current baselin
2) helps avoid any uneccsary changes, ensuring effieicnt use of resource
3) project scope is managed and control is maintained via the provision of a clear baseline, describing time, cost and quality paramaters

62
Q

disadvantages of a change control process

A

1) could cause delay in schedule due to various levels of management that may be involved with approving, deffering or rejecting the change
2) may seem like unneccesary beauracracy, some senior managers will just want to get it done
3) could cause conflict between PM and user if users beleive pM to be hiding behind process

63
Q

configuration management process

A

Planning
identification
control
status accounting
verification and audit

64
Q

Risk Management Process

A

Initiate
identify
assess
plan responses
implement responses

65
Q

How to describe a risk effectivley

A

cause, event, effect

66
Q

Benefits of risk management

A

1) increase return of investment
2) increased chance of project sucsess
3) leassons learned for future projects
4) aids decision making

67
Q

What is an issue

A

something that threatens projects objectives

68
Q

Issue Management Process

A

create an issue register
log the issue
evaluate the issue
esculate the issue
asign actions
monitor progress
Assess the resolution
approve resolution
close the issue

69
Q

BATNA

A

Best alternative to negotiated agreement

70
Q
A