When installing a switched receptacle in a residential bedroom, what must be done so the receptacle can also be counted as a wall outlet
A) constant power to top socket
B) switched power to top socket
C) switched power on bottom socket
D) cannot be done
A) constant power on top
26-720(k)
To satisfy 26-724(a)
When installing exit signs, what classification must be marked on the equipment
A) national building code of Canada
B) Canadian standards association
C) national electrical manufacturers association
D) national fire safety code of Canada
B) Canadian standards association
When installing exit signs and related devices such as remote lamps, how shall the equipment be controlled
A) over current device accessible only to authorized persons
B) two-pole lockable switch accessed by fire department
C) overcurrent device accessible to the public
D) automatic transfer equipment accessible only to authorized persons
D) automatic transfer equipment accessible only to authorized persons
46-206(1)
What is the maximum permissible operating current on the secondary of a CT
A) 4A
B) 5A
C) 6A
D) 10A
B) 5A
How many control conductors are required in a ridged PVC conduit run from the magnetic controller of a HOA selector switch
A) 2
B) 3
C) 4
D) 5
B) 3
A solar photovoltaic systems disconnecting means shall be within how many meters
A) 3m
B) 5m
C) 9m
D) 15m
C) 9m
64-060(2a)
What does “cardiac contact” mean
A) contact by a voluntary action with device that has no part applied to a patient
B) an electrode applied to the skin to
Monitor electrical pulses
C) intentional contact internally but not directly to the hear
D) intentional contact directly to the heart by means of an invasive procedure
D) intentional contact directly to the heart by means of an invasive procedure
24-002
An electrical blueprint has a scar of 1:100. A certain wall on the drawing is 20mm in length, what is the true length of the wall in meters
A) 0.02m
B) 0.2m
C) 2m
D) 20m
C) 2m
What is one of the problems that can result when aluminum cable is installed in concrete with chlorine additives
A) surface penetration of water into cable
B) potential chemical reaction with concrete
C) differential expansion and contraction rates
D) potential for unbalanced magnetic fields
B) potential chemical reaction with concrete
12-602(3)
A 347/600 V, 3-phase rated transformer delivers a secondary f
Full load current of 2000 amps with an impedance of 5%. What is the maximum fault current available at the secondary terminals
A) 40KAIC
B) 20KAIC
C) 15kAIC
D) 12kAIC
A) 40kAIC
When installing cable tray in an office building, what is the minimum horizontal clearance required between the cable tray and adjacent walls
A) 150mm
B) 300mm
C) 450mm
D) 600mm
D) 600mm
12-2200(6c)
When the liquid level is down in a battery, what type of liquid do you add
A) ionized water
B) sulphuric acid
C) distilled water
D) sodium sulphate
C) distilled water
What is the maximum distance the disconnecting means can be located from a 600V, 3-phase, 25 kVAR dry-type capacitor bank
A) 15m
B) 9m
C) 5m
D) 3m
B) 9m
26-212(2)
What is the maximum overcurrent device permitted for a branch circuit supplying an automobile heater receptacle
A) 15A
B) 20A
C) 30A
D) depends on automobile heater
B) 20A
8-400(2)
On a single-phase split-phase induction motor, the centrifugal switch disconnects the start winding from the circuit at what percentage of the full speed of the motor
A) 50%
B) 65%
C) 75%
D) 95%
C) 75%