Revenue recognition Flashcards

1
Q

four criteria

A

1 - Evidence of arrangement
2 - Delivery/Service performed
3 - Price is fixed and determinable
4 - Collectability reasonably assured

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When can rev. be recognized prior to sale?

A

Customer provides valid of payment AND conditions exist contractually guarantee sale.

Example - L-T contracts - gold production

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Normal - point of sale recognition

A

all criteria at this point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When will most rev. recognized be deferred?

A

No valid promise for payment. Significant effort left on contract.

Example - real estate deals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Installment method

A

Each dollar received is part return of cost and part profit.

B/S example
A/R Total
Deferred Gross Profit % of sale profit
Net A/R other half % - cost of uncollectible acct

Db DGP
Cr RGP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Deferred Gross Profit %

A

= DGP/AR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost Recovery Method

A

collectibility is uncertain, conservative, same j/e as installment, no gross profit recognized until cost recovered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

J/E Cost recover method

A

Db Sales
Cr COGS
Cr DGP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Sales with significant right of return

A

Profit not recognized until return privilege expired - unless six criteria met
First 5 similar to the realizable criteria. Sixth is if returns cannot be estimated at year end - then sales rev cannot be recognized until return privilege expired

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Percent of completion

A

= cost incurred to date/est total project cost

Profit recognized is the fraction above *(total revenue - total cost projected)

Rev for year 2 = (remaining % complete * total) - rev yr 1

Shows as a debit to CIP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

% of complete J/E

A
Db Const. in progress - costs from current yr
  Cr materials, cash... - same as CIP
Db Const. A/R - funds billed
  Cr Billings on CIP - funds billed
Db Cash - funds received
  Cr Const A/R  - funds received
Db Const Exp (given in problem)
  Cr CIP  (% of complete project)
Db Const Rev (sum of 2 above)

Db Const exp (given in problem)
Db CIP (fraction done * total) - last year CIP
Cr Const. rev (sum of 2 above)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Completed contracts

A

No profit recognized until project done

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Construction in progress

A

= costs incurred + profit

asset account

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Billings

A

contra construction account

When CIP (asset acct) exceeds billings, no current liabilities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contract losses

A

single period = total estimated profit decreases during period

overall loss = contract no longer profitable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

J/E Single Period loss - % of Completion

A
Db CIP
  Cr Materials, cash...
Db A/R
  Cr Billings
Db Cash
  Cr A/R
Cr Const. Exp
  Db CIP
  Db Rev
17
Q

Overall loss PC vs CC

A

PC = overall loss + previously recognized profit

CC = overall loss

18
Q

J/E Overall loss - % of Completion

A
Db CIP
  Cr materials, cash...
Db A/R
  Cr billings
Db Cash
  Cr A/R
Cr. Const Exp
  Db CIP
  Cb Const Rev
19
Q

J/E Overall Loss - Contract Completions

A
Db CIP
  Cr materials, cash...
Db A/R
  Cr billings
Db Cash
  Cr A/R
Cr. Loss on contract
  Db CIP
20
Q

Cost & profit in excess of billings

A

= CIP - billings