Resource Management Flashcards

1
Q

What are four criteria typically considered when assembling a project team?

A
  • experience
  • availability
  • billing rate
  • personality
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the primary criterion for consultant selection? Secondary?

A
Primary = past working relationship. 
Secondary = fee proposal and firm expertise.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Allocation of project resources within an office is dependent on…

A

… Owner preferences for staff selection and the firm’s organizational structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the primary role of the project manager?

A

Coordinate all design and construction administration activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EPA

A

Environmental Protection Agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

FEMA

A

Federal Emergency Management Agency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

OSHA

A

Occupational Safety and Health Administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

AHJ

A

Authority having jurisdiction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

ANSI

A

American National Standards Institute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ASHRAE

A

American Society of Heating, Refrigeration and Air Conditioning Engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

ASTM

A

American Society for Testing and Materials.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

ICC

A

International Code Council

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

IEBC

A

International Existing Building Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

IECC

A

International Energy Conservation Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

IFC

A

International Fire Code

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

IMC

A

International Mechanical Code

17
Q

IPC

A

International Plumbing Code

18
Q

NEC

A

National Electrical Code

19
Q

NFPA

A

National Fire Protection Association

20
Q

SMACNA

A

Sheet Metal & Air Conditioning Contractors’ National Association

21
Q

ASHRAE 90.1

A

A standard that provides minimum requirements for the energy-efficient design of buildings, except for low-rise residential buildings.

22
Q

AGC

A

Associated General Contractors of America

23
Q

EJCDC

A

Engineers Joint Contract Documents Committee

24
Q

Authority having jurisdiction

A

The governing body carrying the requirements and codes by which the project must adhere.

25
Q

NIOSH

A

National Institute for Occupational Safety and Health

26
Q

Who are the three participants, at minimum, that are involved in a project team?

A

owner, architect, and consultant

27
Q

What team member is added to the project team if minimizing sound transmission is included in the scope of the work?

A

Acoustical engineer