Requirements of Bidding and Construction - General Requirements Flashcards

1
Q

One of the most complex industries in human society; the process where in a design is tranlated into the real world in an intangible manner.

A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • The art, science, or business of building.
  • The process of building from site preparation through erection, assembly and finishing operations.
  • The manner in which material are orderes, assembled and united into a whole as frame construction.
A

Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Two parallel line, supported by a frame, filled with insulation, covered with wallboard and then finished with paint.

A

Wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

A temporary endevour undetaken to create a unique product, service or result.

A

Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Four major standpoint to study construction.

A

As an Industry
As a Business
As a Science
Building System

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The three key player in construction.

A

Client
Contractor
Consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Tradition procurement:

A

Design
Bidding/Tender
Build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Four major project considerations:

A

Site
Program
Schedule
Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The geographical venue of a project; location of a structure or group of structure.

A

Site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • The determine need of the users that will guide for the design process.
  • Desired list of spaces, rooms and elements as well as their sizes for used in designing a building.
A

Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The sequence, duration of works to be done in order to complete the project.

A

Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The financial allocation for the project.

A

Budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Budget Composition (Hard Cost)

A

Construction
Fixtures
Furniture
Equipment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Budget Composition (Soft Cost)

A

Design/Consultancy Fees
Project Management Fees
Permit Fees
Insurance
Contigencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Allocoted budget for unforseen or other possible changes in the design or construction of a project.

A

Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Types of Contigencies

A

Design Contigencies
Construction Contingencies
Owner Contingencies
Escalation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Money for design changes that may be needed in the design in order to accomodate new project requirements.

A

Design Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Money that may be needed to pay for unforseen work or materials necessary to complete construction work.

A

Construction Contigencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Money allocated by owner to possible fund additional work or materials during course of the project.

A

Owner Contingencies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Money that may be needed to pay for significant increase in construction cost particularly cost of materials.

A

Escalation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Written information that clarifies or modifies the bidding documents, often issued during the bidding process.

A

Addendum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Additional design or material option added to the construction documents and or specification to obtain multiple cost estimates for the project.

A

Alternate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Imply added material and cost.

A

Add-Alternate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Imply of rsoval of certain element to lower the project costs as necessary.

A

Deduct-Alternate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is ANSI?

A

American National Standard Institute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Also known as “record drawing”, contract drawing that have been marked up to reflected any changes to a project during construction.

A

As-Built Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

A proposal or a price, contractors are asked to sumbit their estinates as to the time and the costs of the project.

A

Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Written documents issued by the appropriate government authority permitting the construction of a specific project in accordance with the drawings and specifications that the authority has approved.

A

Building Permit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Documents issued by local government agency, stating that the buidling or property meets local standard of occupancy and is in compliance with the public health and building codes.

A

Certificate of Occupancy

30
Q

Written document between and signed by owner and contractor authorizing a change in the work or adjustment in the contract sum or length of time.

A

Change of order

31
Q

Intensive design process for solving architectural problem qucikly, often undertaken by student of architecture but also employed by professionals in various stages of the design process.

A

Charrette

32
Q

Direct construction costs for labor, material, equipments and services as well as overhead and profit.

A

Construction Cost

33
Q

Organization and direction of the labor force, materials and equipment to build the project as designed by the architect.

A

Construction Management

34
Q

Written agreement giving responsibility for project planning and accomplishment and overall planning, design and construction to a construction management firm or individual, called the CM “Construction Manager”

A

Construction Management Contract

35
Q

Hired by the owner or the architect to provide information and to advice the project in the area of his or her expertise.

A

Consultant

36
Q

Contractual duties and responsibilities of the architect and engineer during a project construction.

A

Contract Administration

37
Q

Difference between the orginal contract price and the final completed cost, including all change order adjustment.

A

Contract Over or Under Run

38
Q

Licensed individual or company that agrees and perform the work as specified with the appropriate labor, equipment and materials.

A

Contractor

39
Q

Date certified by the architect when the work is to be completed.

A

Date of Substantial Completion

40
Q

Arrangement wherein a contractor bids or negotiates to provide design and construction services for the entire project.

A

Design-Build Construction

41
Q

Calculation of the amount of materials, labor and equipment needed to complete a given project.

A

Estimating

42
Q

Method of construction management in which construction works begins before completion of the construction documents, resulting in a continuous design-construction situation.

A

Fast-Track Construction

43
Q

Movable furniture, fixtures or equipment that do not require permanent connection to the structure or utilities of a building.

A

FF&E

44
Q

Written order calling for clarification or minor change in the construction and not involving any adjustment to the terms of contract.

A

Field Order

45
Q

Licensed individual or company with prime responsibility for the work.

A

General Contractor

46
Q

Expenses that are not changeable to a specific project or task such as overhead.

A

Indirect Cost

47
Q

What is NIBS?

A

National Institiue of Building Sciences

48
Q

Written contract between the architect and client for professional architectural services.

A

Owner-Architect Agreement

49
Q

Cetral idea governing and organizing a work of architecture, from the French “Partir” to depart with the intention of going somewhere.

A

Parti

50
Q

Line diagram showing proposed and actual starting completion timeline in a project.

A

Progress Schedule

51
Q

All cost for a specific project including those for land, professionals, construction finishing, fixtures, equipment, financing and any other project related expenses.

A

Project Cost

52
Q

Written list of names and addresses of all parties involve in a project, including the owner, architect, engineer and contractor.

A

Project Directory

53
Q

Qualified individual or firm authorized by the owner to be responsible for coordinating time, equipment, money, task and people for all portions of a project.

A

Project Manager

54
Q

Detailed written specifications describing construction materials and methods.

A

Project Manual

55
Q

Written request from a contractor to the owner or architect fo clarification of the contract documents.

A

Request for Information “RFI”

56
Q

Written request to a contractor, architect or subcontractor for an estimate or cost proposal.

A

Request for Proposal “RFP”

57
Q

Plan for performing work also a chart or table within the drawing set.

A

Schedule

58
Q

Chart, diagram or outlime of a system being proposed.

A

Scheme

59
Q

Written range of view or action for a specific project.

A

Scope of Work

60
Q
  • Drawings, diagrams, schedules and other data specifially prepared by the contractor or subcontractor, suncontractor manufacturer, supplier or distributor.
  • These drawings show the specific way in which the particular contractor or shop intends to furnish, fabricate, assemble or install it’s product.
A

Shop Drawings

61
Q

Expenses in addition to the direct construction cost, including architectural and engineering fees, permit, legal and financing fees, construction interest and operating expenses, leasing and real estate commissions, advertising and promotion and supervision.

A

Soft Costs

62
Q

Listing of minimum acceptable ethical. Principals and practices adopt by qualified and recognized professional oragnizations to guide their members in the conduct of specific professional practice.

A

Standard of Prosessional Practice

63
Q

Load bearing assembly of beams and columns on a foundation.

A

Structural System

64
Q

Specialized contractor who is subordinate to the prime or main contractor.

A

Subcontractor

65
Q

Proposed replacement or alternate for a material or process of equivalent costs and quality.

A

Substitution

66
Q

Interior improvements of the project after the building envelope os complete.

A

Tenant Improvements “TIS”

67
Q

Written agreement wherein payment is based on actual cost for labor equipment, materials and services rendered in addition to overhead.

A

Time and Materials “T&M”

68
Q

Process of analyzing the costs versus the value of alternative materials, equipments and systems; usually in the interest of achieving the lowest total costs for a project.

A

Value Engineering

69
Q

Restrictions of areas or regions of lands within specific areas based on permitted building size, character and uses as established by governing urban authorities.

A

Zoning

70
Q

Document issued by a governing urban authority that permits land to be used for specific purposes.

A

Zoning permit