Reports Flashcards
defined as all costs specific to a project incurred through the startup of a facility but prior to the operation of a facility. It is comprised of TEC and OPC.
Total Project Cost
Selection of Civil Engineer
- Envelope System
2. Bidding
Charging of Civil Engineer
- Salary Cost times Multiplier plus direct salary Expense
- Hourly Billing rate
- Per diem
- Cost plus fixed fee
- Fixed Price
- Percentage of construction
- Schedule of min. Basic fee
Defined as Direct salary plus employee’s benefits
Salary Cost
Factor that compensate the engineer for overhead cost
Multiplier
defined as all engineering design costs (after conceptual design), facility construction costs, and other costs specifically related to those construction efforts. These are typically capitalized.
Total Estimated Cost
are defined as all other costs related to a project that are not included in the TEC, such as supporting research and development, pre-authorization costs prior to start of Title I design, plant support costs during construction, activation, and startup.
Other Project Cost
TEC is divided into cost associated wiht
Project Management (PM) Construction Contractor (CM) Construction Management (CM) ED&I
activities include the engineering and design activities in Titles I & II, the inspection activities associated with Title III, and activities defined in the Brooks Bill (e.g., the 6 percent allowed for design, drawings, and specifications).
Ed&I
covers those services provided to the DOE on a specific project, beginning at the start of design and continuing through the completion of construction, for planning, organizing, directing, controlling, and reporting on the status of the project.
Project Management
covers those services provided by the organization responsible for management of the construction effort during Title I and Title II design, and continuing through the completion of construction.
Construction Management
cover salaries, travel, and other expenses of engineers, engineering assistants, and their secretarial support responsible for engineering and design performed by the construction contractor
Construction Contractors
COST ALLOCATIONS
Plant and Capital Equipment (PACE) Fund
Operating Expense Fund
Usage
provides funding for the plant and
its basic equipment/furnishings. This fund is for conventional construction projects
only.
The Plant and Capital Equipment (PACE) Fund
provides funding for ongoing activities, such as laundry, cleaning, etc. These items are typically captured in site overhead accounts and then allocated to projects as site overhead.
Operating Expense Fund
REPUBLIC ACT NO. 9184
AN ACT PROVIDING FOR THE MODERNIZATION, STANDARDIZATION, AND REGULATION OF THE PROCUREMENT ACTIVITIES OF THE GOVERNMENT AND FOR OTHER PURPOSES
Also known as the Government Procurement Reform Act