Remedies: Damages Flashcards
Most commonly sought form of relief in Contract Law
The common law remedy of damages is the most frequently sought relief in cases of breach of contract.
How are damages calculated?
While in tort, damages are calculated to restore a plaintiff to the position in which she would have been in had the tort not occurred, in contract, damages are assessed with the aim of putting the
plaintiff in the position in which she would have been had the contract been performed
Hickey v HSE [2008]
“The rule of the common law is that where a party
sustains a loss by reason of a breach of contract,
he is, so far as money can do it, to be placed in the
same situation, with respect to damages, as if the
contract had been performed.”
Doran v. Delaney [1999], Geoghegan J
“If a party to a contract breaks that contract the
other party is entitled to be compensated on the
basis of what he has lost by reason of the contract
not being performed.”
Remoteness of Damage
Where there has been a breach of contrat, all sorts of dreadful consequences could flow from that. But, that does not mean all those losses will be compensated.
If you book a taxi to bring you to the airport, tomorrow morning at 7am. The taxi driver doesn’t turn up, at all. Because they don’t turn up as agreed, you aren’t at the airport in time for your flight, miss your flight, and miss your job interview with a law firm. Because it is missed, you don’t get offered a job by them. And you miss out on your highly lucrative commercial law career in London. Had a breach of contract with the Taxi driver, can you recover indefinitely? No. Taxi driver is not liable for everything. Remoteness
British Columbia Saw-Mill Co Ltd v Nettleship [1868]
Man going on horseback to marry an heiress. Horse had a problem with this shoe.
Goes to a Blacksmith to remedy the issue, but, did his job so badly, that it was rendered lame.
Arrived so late, heiress married somebody else.
Sues Blacksmith for loss of marriage, and he recovered. Since then, things have tightened up
LEADING CASE: Hadley v Baxendale [1854]
Where the defendants had breached their contract with the plaintiffs by making late delivery of an engine shaft for a mill in Gloucester.
Delivery was required by the contract to be performed within one day, but it actually took a week.
This meant that the mill was out of operation for a full week, resulting in a loss of profits. Could these be recovered as against the defendant?
The Court held that damages were available either if the damages were (a) such as would flow naturally from a particular breach of contract; or (b) such as may reasonably have been supposed to be in the contemplation of both parties, at the time of making the contract, to be a probable result of a particular breach
This damage did not flow naturally from the breach: could have had a spare part, reasonable clause. The fact that they did not have such a contingency plan in operation was a special circumstance of which the defendant did not have actual knowledge. However, it was also not communicated to the defendant
that the mill would have to shut down, were the shaft to be delivered late.
If plaintiff had have made urgency known, e.g. that it was required to allow the mill to function, then it may have been recoverable as it would have been within the contemplation of both parties at the time the contract was entered.
Balfour Beatty Construction v Scottish Power PLC [1995]
Plaintiffs were the main construction company on the Edinburgh bypass, aqueduct. Defendants agree to supply electricity. Power-cut.
Difficulty. Breach of contract. Temporary power-cut, all of the work done on the aqueduct was rendered worthless as it required a constant supply of electricity, and it had to be demolished.
Massive loss but, the damage was too remote! HOL would not reward damages. Applying Hadley,
1. Not the sort of damage that usually arises from a power-cut to a construction site
2. Defendant did not know about the need for a constant supply of electricity, nor was there any reason why they should be presumed to know about it.
3. Special circumstances of the aqueduct had not been communicated by the plaintiff.
If this had been communicated, the plaintiff may have not recovered, by not entering the contract due to the risk, or by charging at a much higher price to reflect the risk they carried at the plaintiff’s request.
Parsons Ltd v Utley Ingham [1978]
Plaintiff pig farmers ordered a storage hopper for storing pig nuts. Filled and released periodically to automatically feed the pigs
Storage hopper was negligently installed by the defendants, so when the nuts are fed in, they rotted.
Rotted nuts fed to the pigs, causing intestinal disease of such severity, so that 254 pigs perished.
Breach of contract. Defendants attempted to argue that the death of the pigs was too remote of a consequence, and they should not be liable. Severity was unforeseen.
Court rejected the defendants’ argument. It
was enough for the plaintiff to establish that illness was the natural consequences of the defective feed being given to the animals.
Fact that the illness caused the deaths of a
significant number of pigs did not make the loss too remote (which makes sense as remoteness does not relate to the size of the loss, but rather its proximity in causation terms to the breach of contract).
Kemp v. Intasun [1987]
Element of formality to the communication of the Hadley test.
Mrs Kemp and her daughter called to Thomas Cook to book a summer holiday. Referred specifically in chatting to the sales assistant, to the fact that her husband suffered from asthma, and that special health insurance was required due to her husband’s condition.
Booked a room in a particular hotel – “The America 1”- in Mallorca. The booking form had a space for “special requests” but nothing entered. The hotel was full and the Kemps were taken to an inferior hotel, where their room was in staff quarters and was filthy and dusty. Breach of contract -> holiday promised was vastly different from the holiday delivered.
Mr Kemp ended up suffering an asthma attack which caused him and his family considerable distress. An award of £400 for inconvenience and disappointment was not appealed by Intasun but an extra award of £800 for the consequences of the asthma attack was appealed by Intasun as being too
remote.
Intasun should have reasonably contemplated that
the conditions in a room provided by way of alternative accommodation might foreseeably be injurious to Mr Kemp’s health. Mrs Kemp’s evidence
established that the conversation in Thomas Cook’s had been casual and not part of the booking arrangements.
Kerr LJ found that the trial judge had erred in attributing any contractual consequences to that casual conversation, at the time of the conversation (whatever about later in the transaction), Thomas Cook was not Intasun’s agent. Too remote!
Heads of Loss
When there has been a breach of contract, your losses can be quantified under different headings. Can recover under any heading you like, but cannot double-count or recover the same loss twice when they overlap under headings. There are three generally recognised primary types or heads of losses:
1. Expectation loss: compensates the plaintiff for the expected profit had the contract been carried out
2. Reliance loss: compensates the plaintiff for wasted expenditure incurred in reliance on a person to carry out a contract e.g. hiring of staff, getting materials, etc.
3. Restitutionary loss: arises where the plaintiff has conferred some benefit on the defendant under the contract, e.g. a deposit. If the defendant then fails to perform the contract it is open to the court to order that the benefit be returned to the plaintiff.
But, presumption that the performance of the contract will make a profit - not always true! Have to prove that the contract would have been profitable. May be better off recovering wasted expenditure rather than expectation, etc.
Anglia Television v Reed [1972]
US actor Robert Reed pulled out of a contract in order to be free to make a TV movie at the last minute. Could not be replaced so the original film
– a film of the play “The Man in the Wood” - had to be
abandoned.
Plaintiff has incurred considerable expenditure in preparing for the movie, both before and after the contract was entered - hiring actors, engaging script writers, etc.
Defendant contended that only the expenditure incurred after the contract was entered into could be recovered. Not liable for any prior expenditure, but, casting is one of the last things to be done.
Case heard by Lord Denning, very little enthusiasm for film or films. The plaintiff could recover all that loss which flowed from breach of contract notwithstanding that the particular expenditure was incurred before the contract was concluded. The plaintiff could not claim both for loss of profits and
wasted expenditure Plaintiff had a choice as to which head of loss they would claim.
Hard to prove a shitty sounding film would have made profit. Tactically, better off recouping wasted expenditure rather than for lost profits that may not satisfy the judge.,=
If a plaintiff would have lost money but for the breach of contract by the defendant, then…
…it cannot recover damages to compensate in respect of expenditure incurred in reliance on the contract.
Bowlay Logging v Domtar [1978]
The defendant contracted to provide trucks to transport logs to the plaintiff’s sawmill.
They failed to provide a sufficient number of trucks, in breach of contract.
However, the plaintiff would not have made a profit had sufficient trucks been available: the sawmill was an economically unviable operation which was losing money on each consignment of logs.
It would have made an even greater loss had the defendant actually performed its obligations under the contract.
The plaintiff claimed, not for expected profits (which were obviously non-existent) but for the recovery of expenditure incurred in the expectation that sufficient trucks would be available.
It was held that damages were not recoverable. The plaintiff’s losses on full performance would have exceeded its losses on expenses thrown away.
It was contrary to the principle of reliance loss to put the plaintiff in a better position than it would have been in had the contract not been performed. Reliance here had not led to any loss. Concept of how damages are awarded does not make sense here.
Intangible Loss -> Lost Chances
The quantification of damages in situations where loss is intangible is particularly difficult. However, the courts have taken a pragmatic approach to the assessment of loss in these circumstances. One question which arises is whether a party can claim for “loss of a chance”, i.e. claim that but for the defendant’s breach of contract, a certain event might have happened.
Lost chances used to be dismissed as too conjectural to ground a claim for damages. This changed with the case of Chaplin v Hicks [1911]