Rear Mono Flashcards
Homeless shelter
2.Unload, as fast as possible, it is the only place to save time.
Store
3.Hang governer, minifor, sheave, and pit template.
Graffiti wall
4.First round of brackets and rails, use laser on pit template.
Art house
5.Counterweight sling, cw rollers Top. gov in pit, set rail blocks.
Liquor store
6.Hoist sheave in pit, safety plank, balance beam, ISO profiles, rods, platform
Steel wall
7.Load weights into counterweight frame, and take cover off sheave.
Tin Vietnamese
8.Top safety plank,cab walls,
Wig store
9.Canopy, top rollers , plumb car , put in cab steadyiers. take out jack bolts, and nail down canopy with tek screws.
Parking lot
10.Hand rails , and unload And install tyrak, also did car top skirt and made and install front diagonals .
Natoma entrance
1.Meet and greet , safety nets, and safety lines, survey
Burlington coat factory
11.Ran power for tyrak into machine room and verified power, then ran tyrak rope down hoistway into tyrak.
Bucca
- Adjusted asgt and checked safeties. Then installed underslung and sheeve in pit
Marijuana store
- Dropped plumb lines and set up car top
Tile picture
14.Main rails
2cnd tile picture
15.
Cwt rails, Top bracket on king needs to be sucked in to make room for lollipop