Reactor Trip (RT) Flashcards

1
Q

Per RT Step 2, It is expected that the CRS will periodically review the event with the SM to update info pertaining to ___

A

Emergency Plan

  • May result in upgrade/downgrade classifications
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Per RT Step 5, Spray water delta T can either be logged using Appendix 6 or by ___

A

…printing ERFDADS point RCTDAUX

*RCTDAUX calculated difference in temperature, doesn’t track valve position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Per Step 9, The operator is responsible to prevent a SIAS/CIAS or MSIS due to overcooling. ___ in this step is allowed in order to restore level into the normal band.

A

Overriding AFAS

  • IF AFAS is used, ensure blowdown to DEMIN package is stopped due to no cooling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SG Blowdown may be secured to ___ and/or ___

A

Minimize RCS temperature reduction and/or SG level reduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Per RT Step 10, Prior to stopping HPSI, ensure that ___

A

…none of the SI throttle criteria is in danger of falling outside of the required value, would require restart of HPSI soon after it stopped

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Evaluation of LCO compliance should be completed ___

A

…in a timely manner.

The LCO entry time for any required actions will be considered the time of discovery of the condition.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly