The Perform Integrated Change Control process occurs in which Process Group?
Monitoring and Controlling
Which item is an example of personnel assessment?
Focus group
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
Project documents
The number of potential communication channels for a project with 5 stakeholders is
10
A project charter is an output of which Process Group?
Initiating
Which process involves subdividing project deliverables and project work into smaller, more manageable portions?
Create WBS
Which tool or technique is effective in a project in which the deliverable is not a service or result?
Product analysis
Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:
Work performance information.
Which process in Project Time Management includes reserve analysis as a tool or technique?
Estimate Activity Durations
Which type of project management office (PMO) supplies templates, best practices, and training to project teams?
Supportive
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
Project charter
An input to the Manage Project Team process is:
Work performance reports.
Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:
Cost management plan.
Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?
Perform Integrated Change Control
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
Estimate Activity Resources.