Random Info Flashcards

1
Q

4kv room breaker numbers on 4KV1-4

A
  • 4KV1-2 are 52/1 through 52/14
  • 4KV3-4 are 52/15 through 52/28

-52/29 and up are not in the 4KV room

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

4KV room layout

A
  • Starting from 4KV1 to the right
  • 4KV1-4KV2-4KV3-4KV4-SST2B-480V2B-480V3-SST2C-SST2A-480V1-480V2A-DS bus

SST-2D and 480V4 are on the NE corner

480V5 and SST-2E are in the nook

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

MCC-5 normal power and alternate power?

A
  • Normal power from E-1

- Alternate power from DS bus through kirk key breaker across from WGDP.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

IB alternate power

A
  • All IB panels (1-4) can be alternately powered from 480V Bus 3 via MCC4-MCC8
  • Only 1 IB can be alternately powered at one time
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Energizing Dead Bus operation

A

-when a breaker is operated to energize a dead-bus, the breaker switch should be held 4 to 8 seconds to allow time for the UV coil to be energized.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

125VDC DP-A provides control power to?

MCC-A

A
  • 480V Busses 1, 2A, and E-1

- 4KV Busses 1 and 2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

125VDC DP-B provides control power to?

MCC-B

A
  • 480V Busses 2B,3 and E-2

- 4KV Busses 3 and 4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Control Power for 480Bus 4?

A

-125VDC MCC-B-A (powered from MCC-B0

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Control power for 480Bus 5?

A

-It provides its own control power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Switchyard Disconnects

A
  • Are manually operated unlike breakers.
  • All 3 phases disconnect at the same time.
  • Only operated after OCB’s are open
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

OCB in switch yard indication?

A
  • To revieve open indication on the RTGB all 3 phases of the OCB must be open.
  • Only 1 Phases has to be close to get a Close indication on the RTGB
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Main Transformer fans and oil pumps power supplies?

A
  • Normal power 480V Bus 1 via PP-63

- Alternate power MCC-17 via PP-64

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

UAT fans and oil pump power supplies?

A
  • Normal Power 480Bus 1 via PP-63

- Alternate power from MCC-4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

115KV SUT fans and controls

A
  • Normal PP-90
  • Alternate PP-91

-LTC powered by PP-92

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

230KV SUT fans and controls

A

-Normal PP-91
Alternate PP-90

-LTC powered by PP-93

How well did you know this?
1
Not at all
2
3
4
5
Perfectly