Quiz 1 Flashcards

1
Q

Eligibility documents should have the following:

A
  • Eligibility Criteria
  • Eligibility Requirements
  • Format and Signing Eligibility Documents
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Use equations that express the statistical relationship between building parameters and cost of the building

A

Parametric Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

These provisions detail more than just the deadline to complete your work.

A

TIme

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The construction contract should provide how these disagreements should be dealt with.

A

Claims and Disputes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost required to perform all the work

A

Contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A set of precise and clear specifications is a prerequisite for Bidders to respond realistically and competitively to the requirements of the Procuring Entity without qualifying or conditioning their Bids.

A

Specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

the 3rd type of changes that may be allowable under contract.

A

Minor Changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

such as crushed stone, crushed gravel or natural gravel with particles retained on a 5mm sieve.

A

Coarse Aggregates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

This document shall include but not limited to the Invitation to Bidders:

A
  • Scope of Bid
  • Source of Funds
  • Procedure for clarifications
  • Bid preparation – form
  • Language
  • Pricing and currencies
  • Bid evaluation criteria and procedures
  • Closing Date
  • Bid submission procedure
  • Corrections
  • Bid Validity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When a Contract has been entered into, to provide a priced Bill of Quantities for use in the periodic valuation of Works executed.

A

Bill of Quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

where the designing engineer specify the mixture proportion.

A

Prescribed Mix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

This document is intended to assist the Procuring Entity in providing the specific information and requirements in relation to corresponding clauses in the Eligibility Documents and has to be prepared for each specific procurement.

A

Eligibility Data Sheet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

This will outline the circumstances in the contract

A

Suspension & Termination

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Approximate cost of the Project

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contents of Philippine Bidding Documents (PBDs)

A
  • Invitation to Apply for Eligibility and to Bid (IAEB)
  • Eligibility Documents
  • Eligibility Data Sheet
  • Instructions to Bidders (ITB)
  • Bid Data Sheet (BDS)
  • General Conditions of Contract (GCC)
  • Special Conditions of Contract (SCC)
  • Specifications
  • Drawings
  • Bill of Quantities
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

must be strong enough to carry the designed load.

A

Hardened Concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

an artificial stone as a result of mixing cement, fine aggregates, coarse aggregates and water.

A

Plain Concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

select an optimum proportion of cement, water and aggregates to produce a concrete that will satisfy the requirements of strength, workability, durability and economy.

A

Concrete Mixing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Issued by the Procuring Entity to provide the prospective bidders all the necessary information that they need to prepare their bids.

A

Bidding Documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Who issued the Documents that provides the prospective bidders all the necessary information the they need to prepare their bids?

A

Procuring Entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

should be economically produced.

A

Concrete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

When will be the final proportion which will be adopted in concrete mixing must be established

A

Actual Trial and Adjustment on the site (to attain desired strength of concrete)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

To provide sufficient information on the quantities of works to be performed to enable Bids to be prepared efficiently and accurately

A

Bill of Quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What includes the Document Review?

A
  • Bid Documents
  • Contract Documents
  • Plans and Drawings
  • Technical Specifications
  • Methodology
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Factors Affecting Decision to Bid

A

Investment of time and money
Risk during construction
Labor and equipment
Ongoing projects
Geographic location
Complexity of project
Owner and designer’s reputation
Profit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

To perform this type of estimates, the contractor must have a complete of contract documents

A

Detailed Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

a simplified map showing the location of the site in relation to the local geography, indicating major roads, posts, airports, and railroads, is helpful.

A

Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Encompass every aspect of the project so it can be hard to boil everything down into a single article. Still, the following are some of the more important provisions that everyone should take note of before signing a contract.

A

General conditions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

there’s always the chance that one side might consider something to be minor while the other side sees it as a material change to the job.

A

Minor Changes

30
Q

What are the factors that is included in Quantity Take-off?

A
  • Construction method
  • Plan reading and review
  • Calculate the quantity of material
  • Unit of measure
  • Cost of material
  • Cost of labor
  • Cost of equipment
  • Cost of subcontracted works
  • Common error
  • Direct cost and Indirect cost
  • Risk
  • Profit
31
Q

What are the purposes of Estimates?

A
  • Determining the feasibility of a project
  • Calculating an approximate price of a project
  • Providing value analysis or engineering
  • Calculating and establishing bid prices
  • Determining project budget in cost control
32
Q

Invitation should indicate the following:

A
  • Date of Availability of the Bidding Documents
  • Place where the Bidding Documents may be purchased
  • Deadline for the submission and receipts of bids
  • any important bid evaluation criteria
33
Q

a concrete with reinforcement embedded in such a manner that the two materials act together in resisting forces.

A

Reinforced Concrete

34
Q

This document shall include but not limited to the General Conditions of Contract:

A
  • Scope of Contract
  • Contractor’s Obligations
  • Warranty
  • Liability of the Contractor
  • Advance Payments
35
Q

such as crushed stone sand, crushed gravel sand or natural sand with particles passing on a 5 mm sieve.

A

Fine Aggregates

36
Q

This section of the Bidding Documents provides the information necessary for Bidders to prepare responsive bids, in accordance with the requirements of the Procuring Entity.

A

Instruction to Bidders

37
Q

If this is in the prime contract, subcontractors will often be bound by similar terms. Regardless – it’s important to understand whether change directives can be made and how they’ll be managed.

A

Changes in Directive

38
Q

Cost of various design alternatives

A

Designer

39
Q

When they’re validly executed (pursuant to the contract), change orders become a part of the original contract.

A

Change Orders

40
Q

could withstand the conditions to which it is exposed to serve.

A

Hardened Concrete

41
Q

What are the factors that is included in Site Visit?

A
  • Available space for storage of materials
  • Control of traffic
  • Security
  • Existing under and above ground facilities
  • Zonal description of site
  • Local laws governing the site
42
Q

have the potential for creating chaos – so make sure the general conditions discuss how change orders must be agreed upon, executed, and billed.

A

Change Orders

43
Q

This document is intended to assist the Procuring Entity in providing the specific information and requirements in relation to corresponding clauses in the Eligibility Documents and has to be prepared for each specific procurement.

A

Eligibility Data Sheet

44
Q

This document provides information necessary for prospective bidders.

A

Eligibility Documents

45
Q

can get risky if they aren’t limited by the general conditions of the contract.

A

Changes in Directive

46
Q

must be drafted to permit the widest possible competition and, at the same time, present a clear statement of the required standards of materials, Plant, other supplies, and workmanship to be provided.

A

Specifications

47
Q

This section is intended to assist the Procuring Entity in providing the specific information in relation to corresponding clauses in the ITB included in Section II, and has to be prepared for each specific procurement.

A

Bid Data Sheet

48
Q

For clarity, it might be a good idea to set parameters for what’s considered a “minor” change under the agreement.

A

Minor Changes

49
Q

must show sufficient details to enable bidders to understand the type and complexity of the work involved and the price the Bill of Quantities.

A

Drawings

50
Q

where the contractor is responsible in selecting the mixture proportion to achieve the required strength and workability

A

Designed Mix

51
Q

Amendments to the contract

A

Change Orders

52
Q

should also be touched on in time section

A

Delays and extensions

53
Q

These are simple adjustments to the project that don’t affect either the price of the time to complete performance.

A

Minor Changes

54
Q

Used in the equation which includes gross square footage, number of floors, length of perimeter, percentage of building that is common space and so forth

A

Building Parameters

55
Q

Determination of the quantities and cost of everything that is required to complete the project.

A

Detailed Estimates

56
Q

Provides information that enables potential bidders to decide whether to participate in the procurement at hand.

A

Invitation to Bid

57
Q

What includes for the Preparation for Detailed Estimates?

A
  • Document Review
  • Site Visit
  • Quantity Take off
  • Direct and Indirect Cost
  • Risk of Uncertainties
  • Profit
58
Q

These provisions authorize the owner to unilaterally make changes to the work, with the price and schedule changes will be agreed upon later.

A

Changes in Directive

59
Q

Disagreements arise all the time on construction projects.

A

Claim and Disputes

60
Q

Seems fairly obvious

A

Time

61
Q

read in conjunction with the Special Conditions of Contract and other documents listed therein, should be a complete document expressing all the rights and obligations of the parties.

A

General Conditions of Contract

62
Q

Types of Cement

A
  • Ordinary Portland Cement
  • Rapid Hardening Portland Cement
  • Portland Blast furnace or Sulphate
  • Low Heat Portland Cement
  • Portland Pozzolan Cement
  • High Alumina Cement
63
Q

must be workable which means that it could freely flow to fill all voids inside the form

A

Fresh Concrete

64
Q

Prepared by comparing the cost of the proposed project to a completed project

A

Project Comparison Estimates

65
Q

the clauses in this section are intended to assist the Procuring Entity in providing contract-specific information in relation to corresponding clauses in the General Conditions of Contract.

A

Special Conditions of Contract

66
Q

These can include anything from the owner having funding issues to any delays the project might encounter.

A

Suspension & Termination

67
Q

will determine the full contract price and how payments are structured.

A

Price & Payments

68
Q

What is the formula of Forecast Unit Cost?

A

UC=(A+4B+C)/6

69
Q

Prepared by multiplying square footage of a building by a cost per square foot and then adjusting the prose to compensate for differences in the building heights, length of the building parameter and other building components.

A

Square-foot Estimates

70
Q

Essentially a mini-agreements to adjust the work, price, and schedule of the initial contract.

A

Change Orders