Questions Dump 2 Flashcards

1
Q

Project Management Office (PMO), which is a centralized organizational unit to oversee and coordinate the management of projects and programs under its domain throughout the organization, has all of the following functions EXCEPT:

A. Identify and develop the organization’s methodology, administrative practices, guidelines, policies, procedures, and rules.

B. Establish and maintain templates, policies, procedures, best practices, and standards for project management methodologies.

C. Monitor compliance with organizational project management processes, policies, procedures, and other items.

D. Be involved heavily during project initiation as a key decision maker and integral stakeholder to make recommendations, prioritize projects, terminate projects, or take other actions as required.

A

Answer: A

Explanation: The PMO identifies and develops the project management methodology, best practices, policies, procedures, and standards, but not the organizational methodology, administrative practices, guidelines, policies, procedures, and rules.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the name of PMI’s organization maturity model for project management that helps to determine the level of ability of an organization to deliver the desired strategic outcomes in a reliable, controllable, and predictable manner?

A. ISO 9000

B. OPM3

C. Project Management Maturity Model (PMMM)

D. Six Sigma

A

Answer: B

Explanation: OPM3 is the PMI’s organizational project management maturity model. This model helps to determine the level of ability of an organization to deliver the desired strategic outcomes in a reliable, controllable, and predictable manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which one of the following PMO structures mostly provides guidelines, policies, and templates and requires compliances and usually has a moderate level of control over projects and programs?

A. Supportive

B. Controlling

C. Directive

D. Constructive

A

Answer: B

Explanation: The controlling PMO provides guidelines, policies, and templates and requires compliances. This type of PMO usually has a moderate level of control over projects and programs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which one of the following is TRUE about power of the project managers in different organizational structures?

A. In a project-oriented organization, the project manager has no real authority and power.

B. A strong matrix maintains many characteristics of project-oriented organization, where much of the authority rests with the project manager.

C. In a weak matrix, the authority is shared between the functional manager and the project manager; the project manager does not have full authority over the project and its funding.

D. A balanced matrix maintains many characteristics of a functional matrix; the project manager role is like that of a coordinator or expeditor (communication coordinator or staff assistant) than that of a true project manager.

A

Answer: B

Explanation: The authority of the project manager varies greatly depending on the organizational structure. In a project-oriented organization, the project manager has almost total authority. A strong matrix maintains many characteristics of project-oriented organization where much of the authority rests with the project manager. In a balanced matrix, the authority is shared between the functional manager and the project manager; the project manager does not have full authority over the project and its funding. A weak matrix maintains many characteristics of a functional organization; the project manager role is like that of a coordinator or expeditor (communication coordinator or staff assistant) than that of a true project manager. In a functional organization, the project manager has no real authority and power.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Which one of the following PMO structures mostly serves as a project repository, plays a consultative role, and usually has a low level of control over projects and programs?

A. Supportive

B. Controlling

C. Directive

D. Constructive

A

Answer: A

Explanation: A Supportive PMO mostly serves as a project repository and plays a consultative role. This type of PMO usually has a low level of control over projects and programs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

You are overseeing the implementation of the internal website of your organization to view the company’s event calendar. Your role is to coordinate activities, resources, equipment, and information on the project, but you have limited authority in making project decisions and have to negotiate with the functional manager to get required resources for your project. Which kind of organization are you working in?

A. Balanced matrix

B. Composite structure

C. Weak matrix

D. Strong matrix

A

Answer: C

Explanation: You are working in a weak matrix organization. Your role is of a project expeditor or project coordinator where you mostly act as a staff assistant and communication coordinator with limited authority and have no control over the project’s budget. You have to negotiate with the functional manager to get needed resources for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Which one of the following is NOT true about functional organizational structure?

A. Project work is considered to be priority work in all functional groups.

B. Similar resources are grouped by specialists.

C. The project manager has little or no authority and could even be part time.

D. Multiple projects compete for limited resources and priority.

A

Answer: A

Explanation: In a functional structure, similar resources are grouped by technical expertise and are assigned to one supervisor. Team members give more importance to their functional responsibility to the detriment of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

All of the following are examples of Organizational Process Assets EXCEPT:

A. Organizational policies, procedures, and guidelines for any area such as safety, ethics, risk, financial, change control, reporting, and others.

B. Existing facilities and infrastructure.

C. Templates for common project documents such as WBS, network diagram, SOW, and contract.

D. Historical information and past lessons learned.

A

Answer: B

Explanation: Enterprise Environmental Factors are things that impact the project but are not part of the project itself. Existing facilities and infrastructure are Enterprise Environmental Factors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The level of power and authority of a project manager may fluctuate due to various factors. Typically, how much power and authority a project manager will have depends on which of the following?

A. The organizational structure

B. The negotiation skills of the project manager

C. Project management knowledge and technical competency of the project manager

D. The relationship of the project manager with senior management, especially with the sponsor

A

Answer: A

Explanation: The authority of the project manager varies greatly depending on the organizational structure. In a project-oriented organization, the project manager has almost total authority. A strong matrix maintains many characteristics of project-oriented organization where much of the authority rests with the project manager. In a balanced matrix, the authority is shared between the functional manager and the project manager, and the project manager does not have full authority over the project and its funding. A weak matrix maintains many characteristics of a functional organization; the project manager’s role is like that of a coordinator or expeditor (communication coordinator or staff assistant) than that of a true project manager. In a functional organization, the project manager has no real authority and power. Relationship, negotiation skills, and technical ability may affect the level of authority in some organizations, but managerial structure is generally the major factor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

You are managing a group of related or unrelated projects or programs and other works to achieve specific strategic business objectives and goals. You are a:

A. Program owner

B. Project manager

C. Program manager

D. Portfolio manager

A

Answer: D

Explanation: A portfolio can be generally described as a group of projects or programs and other works to achieve a specific strategic business goal. The programs may not be related other than the fact that they are helping to achieve the common strategic goal. A portfolio manager is usually assigned to manage these groups of projects, programs, and other works. Portfolio management encompasses identifying, prioritizing, authorizing, managing, and controlling the collection of projects, programs, other work, and sometimes other portfolios to achieve strategic business objectives. For example, a construction business has several business units such as retail, single and multifamily residential, and others. Collectively, all the programs, projects, and work within all of these business units make up the portfolio for this construction business.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

As a project manager in a balanced matrix organization, what type of authority you have?

A. Low to moderate

B. Little to none

C. High to almost total

D. Moderate to high

A

Answer: A

Explanation: A project manager has a low to moderate authority in a balanced matrix organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The management framework within which project decisions are made is called:

A. Project Management Information System (PMIS)

B. Configuration management system

C. Project management plan

D. Project governance

A

Answer: D

Explanation: Project governance is the management framework within which project decisions are made. The role of project governance is to provide a decision-making framework that is logical, robust, and repeatable to govern an organization’s capital investments. This framework provides the structure, processes, decision-making models, and tools to the project manager and team for managing the project. It also provides the team a comprehensive, coherent method of controlling the project and helps safeguarding project success by defining, documenting, and communicating reliable, repeatable project practices. The PMIS consists of the data sources and tools & techniques used to gather, integrate, analyze, and disseminate the results of the combined outputs of the project management processes. It is an automated system that can serve as a repository for information and a tool to assist with communication and with tracking documents and deliverables. The PMIS also supports the project from beginning to end by optimizing the schedule and helping collect and distribute information. The Configuration Management System is the subset of the Project Management Information System (PMIS) that describes the different versions and characteristics of the product, service, or result of the project and ensures accuracy and completeness of the description. The Project Management Plan is a single-approved document that defines how the project is executed, monitored and controlled, and closed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Which one of the following is NOT a planning process?

A. Create WBS

B. Perform Qualitative Risk Analysis

C. Estimate Costs

D. Develop Team

A

Answer: D

Explanation: Develop Team is a process in the Executing Process Group. All three remaining processes belong to the Planning Process Group.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Steve has been overseeing a project to implement a new wireless media streaming device for a local networking company. The team has completed all the technical work in the project. The senior management asked Steve to report on the remaining activities in the project. Which one of the following will Steve report as the remaining work?

A. Completion of the lessons learned

B. Validation of the Project Scope

C. Completion of the Quality Management Plan

D. Completion of Risk Response Planning

A

Answer: A

Explanation: The lessons learned are usually done once the work is completed in the project. The Quality Management Plan and the Risk Response Plan are created during the Planning Process Group. The Validate Scope process is done, not during closing, but in the Monitoring & Controlling Process Group.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You just finished creating your project charter. Which of the following will NOT be included in the charter?

A. Detailed work package descriptions

B. High-level roadmap and milestones

C. Assumptions and constraints

D. Authority level of the project manager

A

Answer: A

Explanation: High-level roadmap and milestones, assumptions and constraints, and authority level of the project manager should be included in the Project Charter. A Project Charter is created during Initiating Process Group, but a Project Scope Statement is created during Planning Process Group. The Scope Baseline will have the Project Scope Statement, WBS, and details on WBS work packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

While working in the Initiating Process Group, you are mainly focusing on creating a Project Charter and a Stakeholder Register. You will use all of the following as inputs EXCEPT:

A. Organizational values and work ethics

B. Project scope statement

C. Configuration management knowledgebase

D. Historical information and past lessons learned

A

Answer: B

Explanation: Organizational Process Assets such as configuration management knowledgebase, historical information, and past lessons learned as well as Enterprise Environmental Factors such as organizational values and work ethics are inputs in Initiating Process Group. Project Scope Statement is an output of the Planning Process Group

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which one of the following is NOT a component of a change request?

A. Corrective actions

B. Preventive actions

C. Defect repairs

D. Issue Log

A

Answer: D

Explanation: A change request consists of corrective actions, preventive actions, and defect repairs. Corrective actions are taken to bring expected future performance of the project work in line with the project management plan. Preventive actions are taken to reduce the probability of risk items in the project. Defect repairs are taken to repair defects or entirely replace components that are faulty or dysfunctional. An issue is an obstacle that threatens project progress and can block the team from achieving its goals. An issue log is a written log to record issues that require solutions. It helps monitor who is responsible for resolving specific issues by a target date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Last week you submitted 5 new change requests to the Change Control Board (CCB). After exploring different options, the board approved 3 of the change requests. Approved change requests will be inputs to which process group?

A. Initiating

B. Planning

C. Executing

D. Closing

A

Answer: C

Explanation: You will be coming up with change requests both in the Executing and Monitoring and Controlling Process Groups. These change requests will be an input to the Perform Integrated Change Control process in the Monitoring and Controlling Process Group. Approved change requests from the Perform Integrated Change Control process are fed back into the Direct and Manage Project Work process for implementation in the Executing Process Group.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Your team is very devoted to the project and can’t wait to move on to the next phase of the project. What is the most important factor to make sure prior to moving on to the next phase?

A. Making sure that you have sufficient fund for the next phase.

B. Verifying that the current phase satisfied its objective and stakeholders formally accepted its deliverables.

C. Making sure that you have all the resources you need for the next phase.

D. Confirming that there will be no negative stakeholders in the next phase.

A

Answer: B

Explanation: A project phase must be formally closed by meeting its objective and by receiving the formal acceptance on its deliverables prior to moving on to the next phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

While managing a complex project, you realize that the processes of a certain Process Group occur simultaneously as the processes of all remaining 4 process groups. You are referring to:

A. Monitoring and controlling

B. Closing

C. Executing

D. Planning

A

Answer: A

Explanation: Monitoring and controlling is something we are continuously doing in a project. Don’t get confused thinking that we monitor and control only after executing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A project is just initiated under a contract in your organization, and you were assigned as the project manager. You were expecting a Statement of Work (SOW), which will describe the business need, product scope, and other elements. In this case, from whom should you expect the SOW?

A. The project sponsor

B. The buyer

C. The contractor

D. The Project Management Office (PMO)

A

Answer: B

Explanation: Usually the buyers come up with the SOW in a project that is initiated by a contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

While managing a data center project, you used a Configuration Management System to describe the different versions and characteristics of the product, service, or result of the project and to ensure the accuracy and completeness of the description. All of the following are configuration management activities in the Integrated Change Control process EXCEPT:

A. Configuration verification and audit

B. Configuration identification

C. Forecasting and variance analysis

D. Configuration status accounting

A

Answer: C

Explanation: Configuration management activities in the Integrated Change Control process are configuration identification, configuration status accounting, and configuration verification and audit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

You are a project manager at a dairy farm that offers several dairy products to its clients in different states, especially on the West Coast. You have sent a few of your team members to China to get specialized training on a spectacular dairy food processing equipment recently introduced in the market. The team members just completed the training, and this is one of the work results you have collected and recorded. This output describes which of the following in the Direct and Manage Project Work process?

A. Deliverables

B. Work Performance Data

C. Change requests

D. Project Management Plan update

A

Answer: A

Explanation: This output describes a deliverable. Note that deliverables can be intangibles, such as the completion of a training program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

All of the following statements are true regarding assumptions EXCEPT:

A. Assumptions are factors used for planning purposes and may be communicated to a project team by several different stakeholders.

B. Assumptions are generally considered to be true, real or certain, and nonfactual

C. Assumptions are absolute and nonnegotiable.

D. A Failure to validate assumptions may result in significant risk events.

A

Answer: C

Explanation: Assumptions are not based on factual information, and failure to validate may result in significant risk events. Assumptions are documented mostly during the project initiating and planning processes. These assumptions are not absolute and can be negotiable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

You are one of the members of the project prioritization and selection committee in your organization. The selection team is debating between two projects, which are both considered to be very important. The organization has to make an initial investment of $250,000 with expected cash inflows of $75,000 in the first year and $25,000 per quarter thereafter for the first project. The second project has a payback period of thirty-five months. Based solely on this information, which project should the selection committee recommend?

A. First project as it has a smaller payback period

B. Second project as it has a smaller payback period

C. None of them since both of them have the same payback period

D. Either of the two projects since payback period is not important

A

Answer: A

Explanation: 1. The first project will have the cash inflows of $75,000 in the first twelve months, and for the rest of the investment ($250,000– $ 75,000 = $175,000) it will take seven quarters to recapture it; thus, for the first project, the total payback period is 12 + 21 (each quarter has three months; thus, seven quarters have 7 * 3 = 21 months) = 33 months. The first project has a smaller payback period than that of the second project; thus, we should select the first project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

You are the project manager for a cable service provider that is providing Internet, TV, and phone service throughout the United States. Your company recently introduced its service in Canada and made you the project manager for a critical project, which is two months in execution at this time. You are reporting on project elements such as deliverable status, schedule progress, resource utilization, costs incurred, and others. Which of the following outputs of the Direct and Manage Project Work does this describe?

A. Deliverables

B. Work Performance Data

C. Change requests

D. Project Management Plan update

A

Answer: B

Explanation: Work Performance Data describes how far along a deliverable is and how it is progressing against the plan. It can include several work performance data of interest, such as deliverable status, schedule progress, resource utilization, costs incurred, and quality standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

While managing a large construction project, you are ready to assign resources to the project using a work authorization system. All of the following statements are true about a work authorization system EXCEPT:

A. It is a formal, documented procedure to describe how to authorize and initiate work in the correct sequence at the appropriate time

B. It is a tool & technique of the Monitor and Control Project Work process.

C. It is a component of the enterprise environmental factors, which are inputs in the Monitor and Control Project Work process.

D. It is used throughout the project executing process.

A

Answer: B

Explanation: A Work Authorization System is not a tool & technique of the project monitoring & controlling process. It is a subset of the Project Management Information System (PMIS) and is considered a component of the Enterprise Environmental Factors, which are inputs in the Monitor and Control Project Work process. It is a formal, documented procedure to describe how to authorize and initiate work in the correct sequence at the appropriate time and is used throughout the executing process group.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

You are working as a project manager at a consulting firm and recently received a Statement of Work (SOW) from the client. As per your expectation, the SOW should contain or reference which of the following elements?

A. Business need, product scope description or what is to be done, and how the project supports the strategic plan

B. Measurable project objectives, business need, product scope description or what is to be done, and how the project supports the strategic plan

C. Project purpose, business need, product scope description or what is to be done, and how the project supports the strategic plan

D. Business need, product scope description or what is tobe done, and project purpose

A

Answer: A

Explanation: The project SOW should contain the business need, product scope, and strategic plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

You are the project manager for ITPro Consultancy. You have a project in mind that will be able to meet the strategic objective of your organization. While evaluating the project, your team found out that the project would cost $600,000. Since you are introducing a new potential product in the market, you are very hopeful that your expected inflows will be $30,000 per quarter for the first two years and then $90,000 per quarter thereafter. What is the payback period of this project?

A. Thirty-six months

B. Thirty-eight months

C. Forty-eight months

D. Fifty-two months

A

Answer: A

Explanation: The cash inflow is $30,000 per quarter, so in the first year the project will get back $120,000 in four quarters. In the first two years, the project will have a return of $240,000. The remaining investment will be $600,000 – $ 240,000 = $360,000. It will take four quarters or twelve months to have it back at a rate of $90,000 per quarter in the third year. The total amount of time it will take to get the entire investment back will be 24 months + 12 months = 36 months, or three years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

While managing a data recovery project, you are performing the following activities: comparing actual project performance against the project management plan, analyzing, tracking, monitoring project risks, assessing performance to determine whether any corrective or preventive actions are required, providing information to support status reporting, monitoring implementation of approved changes, providing forecasts to update current costs and schedule information, and other things. Which process are you in at this time?

A. Manage Stakeholder Expectations

B. Monitor and Control Risks

C. Direct and Manage Project Work

D. Monitor and Control Project Work

A

Answer: D

Explanation: All these activities are performed in the Monitor and Control Project Work process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Your company can accept one of three possible projects. Project A has a Net Present Value (NPV) of $30,000, it will take five years to complete, and the associated cost will be $10,000. Project B has a NPV of $60,000, it will take three years to complete, and the cost will be $15,000. Project C has a NPV of $80,000, it will take four years to complete, and it will cost $40,000. Based on the information, which project would you pick?

A. They all have the same value

B. Project A

C. Project B

D. Project C

A

Answer: D

Explanation: The number of years and cost are not relevant as they are accounted for in the calculation of Net Present Value (NPV). You simply select the project with the highest NPV; in this case, it is Project C that has a NPV of $80,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

A project manager for a pharmaceutical project is reviewing the project contract and going through the narrative description of products and services to be supplied under the contract. He is meeting with subject matter experts, key stakeholders, and business analysts to evaluate whether or not the project is worth the required investment of $1 million. He also asked the team members to carry out a feasibility study on the project and report to him the findings as soon as possible. Which of the following documents would be created as an output in the process?

A. Project Management Plan

B. Project Statement of Work

C. Project Charter

D. Requirements Documentation

A

Answer: C

Explanation: The project manager is in the Develop Project Charter process in Project Integration Management. The output of this process is a Project Charter, which is used to formally initiate a project. In this case, the project manager is using a Statement of Work (SOW) to understand the product requirements and descriptions. The project will be initiated under the contract, and the SOW was given to the project manager by the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

All of the following statements regarding Integration Management are true EXCEPT:

A. The need for Integration Management is one of the major driving forces for communication in a project.

B. Project integration is a key responsibility of the project team.

C. The project manager’s role as an integrator is to put all the pieces of a project into a cohesive whole.

D. Project Integration Management is the set of combined processes implemented by the project manager to ensure all the elements of the project are effectively coordinated.

A

Answer: B

Explanation: Project integration is a key responsibility of the project manager.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

The Scope Management Plan, Schedule Management Plan, Schedule Baseline, Process Improvement Plan, Change Management Plan, and others are which one of the following to the project plan?

A. Subsidiaries

B. Appendixes

C. Constraints

D. Glossary

A

Answer: A

Explanation: The subsidiary plans are usually included to support the overall project management plan and are developed for the purpose of providing more detailed information, guidelines, and control processes for specifically defined project elements or planning components. These are the outputs of some of the other planning processes associated with scope, time, cost, quality, human resources, communications, risk, procurement, and stakeholder management. Additional plans such as change management, process improvement, and configuration management plans, can also be added to the project management plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

You are working on a construction project and successfully completed all the work. Your stakeholders were very pleased and recently communicated their final acceptance of the project. You are now meeting with your team to update the organizational process assets with a record of knowledge gained about the project to help future project managers with their projects. Once the lessons learned is completed, what should you do next?

A. Release the team.

B. Close the contract.

C. Get formal acceptance.

D. Write lessons learned.

A

Answer: A

Explanation: You should release the team once the lessons learned are documented and added to the organizational process assets. Most contracts have payment terms that allow for some period of time before full payment is required; thus, the last thing you do on the project is close the contract. When closing the project, the order should be get formal acceptance, write lessons learned, release the team, and close the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

Your cyber security implementation project has a Schedule Performance Index (SPI) of 1.2 and Cost Performance Index (CPI) of 1.3. Now that you are ahead of schedule and under budget, you can add work without delaying your project or exceeding the budget. You realized that throughout the project, your team made several mistakes and ignored few best methods for securing the network and preventing various types of attack. Your sponsor was very disappointed that a Denial of Service (DOS) attack was carried out against your organization recently. You tried to identify information on similar mistakes from previous projects but failed to identify any relevant Lessons Learned Register. You decided to develop a Lesson Learned Register that you need to update:

A. At the completion of the entire project

B. At the completion of each phase

C. Bi weekly

D. Throughout the project

A

Answer: D

Explanation: A live document such as Lesson Learned Register should be regularly updated throughout the project for the benefit of the entire organization. It should be an excellent source of information on mistakes and areas for improvements for current and future similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

You are in the Close Project or Phase process of your construction project. All of the following occur during this process EXCEPT:

A. Confirm work completion to requirements

B. Determine the Net Present Value of the project

C. Gain formal acceptance of the product

D. Hand off completed product

A

Answer: B

Explanation: Determining the Net Present Value (NPV) is done during the Develop Project Charter process in the initiating phase, not during the Closing Project or Phase process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Product scope describes the features, functions, and physical characteristics that characterize a product, service, or result. Completion of the product scope is measured against which one of the following?

A. Scope statement

B. Project requirements

C. Project objectives

D. Product requirements

A

Answer: D

Explanation: Completion of the product scope is measured against the product requirements to determine successful fulfillment. The project requirements, project objectives, and the Project Scope Statement are associated with project scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

As per the project manager’s instruction, the team has decomposed project deliverables and project work into smaller, more manageable components to develop a WBS and WBS dictionary. The team finalized the WBS by establishing control or cost accounts and unique identifiers for the lower-level components of the WBS called work packages. Normally presented in the chart form, this WBS provides a structure for hierarchical summation of:

A. Cost and schedule information

B. Cost and requirements information

C. Cost, resource, and schedule information

D. Schedule and requirements information

A

Answer: C

Explanation: A Work Breakdown Structure (WBS) is the foundational block to the initiating, planning, executing, monitoring & controlling, and closing phases. Normally presented in chart form, it is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It provides a structure for hierarchal summation of cost, schedule, and resource information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

A project manager managing a data center project had the opportunity to attend several meetings about the project prior to the creation of the project charter. In one of the meetings, the sponsor specifically denied funding for two very specific items. Two months into the project, a couple of stakeholders requested the project manager add work for one of the items that was strongly denied by the sponsor. What will be the best thing the project manager can do in this situation?

A. Add the work if it does not have much impact on the schedule.

B. Inform the stakeholders that the work cannot be added.

C. Evaluate the impact of adding the work on time, cost, quality, risk, human resource, and other elements.

D. Immediately inform the sponsor about the request that was denied by him.

A

Answer: B

Explanation: The most appropriate thing to do in this kind of situation is to find out the root cause of the problem, but the option is not presented here. Based on the information provided, there is no reason to find out the details and try to convince the sponsor to add the work (C & D). The project manager should inform the sponsor, but the best course of action will be to inform the stakeholders that the work could not be added. Even though there is no impact on the schedule, there may be impact on other areas. A project manager should not implement a change request without performing an impact analysis and must get the approval for the change from the Change Control Board.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Verified deliverables are inputs in which of the following scope management processes?

A. Define Scope

B. Create WBS

C. Validate Scope

D. Control Scope

A

Answer: C

Explanation: Verified deliverables are the deliverables that have been completed as per the documented scope and checked for defects by the project team members in the Control Quality process. These deliverables are inputs in the Validate Scope process and are given to the customers and stakeholders for their acceptance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

All of the following are true regarding the Control Scope process EXCEPT:

A. It assures that underlying causes of all requested changes and recommended corrective actions are understood and processed through the Integrated Change Control process.

B. One of the key focuses in the process may be dispute resolution related to project scope.

C. It monitors the status of the project and product scope, maintains control over the project by preventing overwhelming scope change requests, and manages changes to the scope baseline.

D. It verifies the correctness of work results.

A

Answer: D

Explanation: Verifying the correctness of work is associated with the Control Quality process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Your project is approaching completion, and you were able to release some of the team members from the team to be assigned to other projects. Your team has successfully resolved all the issues in the issue log except for one, which will be fixed in the next version of the application as per the agreement with the client. You are ahead of schedule but $3,500 over budget due to an unexpected price increase for one of the major pieces of equipment. Your team also successfully performed quality control inspections and met quality requirements for all of the items except one. You called a meeting and requested the client for product verification, and surprisingly the client mentioned that they wanted to make a major change to the scope. In this situation, the project manager should:

A. Immediately inform management about this surprising new change.

B. Have an urgent meeting with the team members to explore the feasibility of making the change.

C. Inform that it is too late now to make a major change.

D. Request the client for a description of the change.

A

Answer: D

Explanation: Note that in this kind of situation you should always try to gather as much information as possible if the time allows. You simply should not say no without knowing the details of the change and its possible impact on the project (C). The client only mentioned that they wanted a change but did not provide you with any description of it. You may inform management (A) and also have a meeting with the team if their inputs are needed (B) but not before understanding what the change is all about.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Your company, ITPro Consultancy, has assigned you as the project manager to upgrade the call center in your organization. The number of calls the customer support agents have to answer each month has increased drastically in the last five months, and the phone system is approaching the maximum load limit. Your team has worked on the requirements document and the Project Scope Statement, and you are now ready to create the WBS with the help of your team members. All of the following are true regarding the WBS EXCEPT:

A. The WBS represents all the work required to be completed in the project.

B. Each level of the WBS represents a verifiable product or results.

C. Activities in the WBS should be arranged in the proper sequence they will be performed.

D. The WBS should be decomposed to a level called the work package level where cost and schedule can easily be calculated.

A

Answer: C

Explanation: Note that we do not usually include the activities in the WBS, especially for the large projects, even though we decompose the WBS work packages to get our activities during the Define Activities process in time management. Once the activities are defined, sequencing is done in the Sequence Activities process. Note that WBS has no particular sequence to it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

The sponsor has recently assigned you as a project manager to design and develop a custom video conferencing tool. As per the sponsor, the project must be completed in four months and should integrate with the existing infrastructure and applications in the organization. This is an example of which of the following?

A. Constraints

B. Assumptions

C. Expert judgment

D. High-level planning

A

Answer: A

Explanation: Constraints specify the limitations and restrictions, such as constraints on time, budget, scope, quality, schedule, resources, and technology that a project faces. By specifying a time limit and technology compliance, the sponsor is limiting the options for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

All of the following are TRUE about the Validate Scope process EXCEPT:

A. Customer acceptance of the project deliverables is a key output of this process.

B. It is an input to the Develop Project Management Plan process and an outputof the Control Quality process

C. It should be performed at the end of each phase of the project.

D. This process is closely related to the Control Quality process.

A

Answer: B

Explanation: The output of the Validate Scope process is the customer acceptance of the project deliverables. This process is performed during the monitoring & controlling process group. To get approval of the phase deliverables, it is done at the end of each project phase in addition to other points to get approval for the interim deliverables. Both the Control Quality and Validate Scope processes can be performed simultaneously, but Control Quality is usually performed prior to Validate Scope. Control Quality verifies correctness of the work, whereas Validate Scope confirms completeness. Control Quality is focused on measuring specific project results against quality specifications and standards, whereas Validate Scope is mainly focused on obtaining acceptance of the product from the sponsor, customers, and other stakeholders. It is not an input to the Develop Project Management Plan or an output of the Control Quality process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

A project manager is in the Control Scope process of monitoring the status of the project and product scope, maintaining control over the project by preventing overwhelming scope change requests, and managing changes to the scope baseline. Which one of the following is NOT true about this process?

A. The Control Scope process must be integrated with other control processes.

B. It should be performed prior to scope planning.

C. Variance analysis is used as a tool & technique in this process.

D. Work Performance Information and Change Requests are the key deliverables in this process.

A

Answer: B

Explanation: Scope planning should be performed prior to the Control Scope process. A change in one control process impacts the others; thus, the Control Scope process is integrated with other control processes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Your project to build a new substation to supply power to a newly developed industrial park is not going too well. You are overwhelmed with numerous issues in the project and got really frustrated when the city conducted an inspection and reported a building code violation. You were asked by management to ensure full compliance to the mandatory city and construction industry standards. At this time, you are also approaching the final deadline of the project in two weeks. You have identified a couple of changes that will drastically enhance performance and make your clients very happy. While trying to sort all these messes out, you received a call from the senior engineer informing you that he would be leaving the company soon. Which is the MOST critical issue you should address first?

A. Notify the customers about the possible delay in the project.

B. Initiate the change control process to implement new changes.

C. Find a replacement for the senior engineer.

D. Ensure compliance with the city and construction industry standards.

A

Answer: D

Explanation: A project manager is responsible for prioritizing the most critical issue to concentrate on. The situation here does not really specify whether the senior engineer is playing a vital role in the project or not. “Gold Plating,” or giving customers extra, is not actually required in the project. The project manager should evaluate the current situation and then determine if the project will require additional time or not to complete. The most critical item for the project manager is to ensure full compliance with the city and construction industry standards.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Sarah, a project manager, is in the Define Scope process of developing a comprehensive, detailed description of the project and product. Which of the following is NOT a tool & technique used in this Define Scope process?

A. Interpersonal and Team Skills

B. Product Analysis

C. Decision Making

D. Inspection

A

Answer: D

Explanation: Inspection is used as a tool & technique in the Validate Scope process, not in the Define Scope process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

You have been selected as the project manager for a major data center upgrade at your company headquarters. The sponsor has handed you a Project Charter and wished you best of luck. What should you do next as the first step?

A. Instruct the team to work on a Project Scope Statement.

B. Instruct the team to work on the WBS.

C. Review the charter and make sure that all key stakeholders have inputs into the scope.

D. Start working on planning the project.

A

Answer: C

Explanation: You should review the Project Charter and make sure that you have inputs from all key stakeholders in order to avoid confusion and unnecessary change requests in the future. You should then concentrate on creating the Project Scope Statement, the WBS, and the project plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Walkthroughs, reviews, product reviews, and audits are examples of which one of the following methods of examining work or a product to determine whether it conforms to documented standards or not?

A. Observation

B. Verification

C. Inspection

D. Decision Making Techniques

A

Answer: C

Explanation: Inspection includes activities such as measuring, examining, and verifying to determine whether work and deliverables meet requirements and product acceptance criteria. Inspections are sometimes called walkthroughs, reviews, product reviews, and audits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

You are overseeing a project to implement a web-based traffic monitoring system. You have requested three programmers, three database developers, and two testers; senior management only approved five team members for your project. Which one of the following may you use to produce a resource-limited schedule by letting the schedule slip and cost increase in order to deal with a limited amount of resources, resource availability, and other resource constraints?

A. Resource Leveling

B. Fast-Tracking

C. Crashing

D. Critical Path Method

A

Answer: A

Explanation: Resource leveling is used to produce a resource-limited schedule by letting the schedule slip and cost increase in order to deal with a limited amount of resources, resource availability, and other resource constraints. It can be used when shared or critically required resources are only available at certain times, are in limited quantities, or when resources have been over allocated. Fast- tracking is the technique of doing critical path activities in parallel when they were originally planned in series. Crashing is the technique of adding additional resources to a project activity to complete it more quickly. The critical path is the longest path through a network diagram and determines the shortest time to complete the project as well as any scheduling flexibility. It is not the project schedule, but it indicates the time period within which an activity could be scheduled considering activity duration, logical relationships, dependencies, leads, lags, assumptions, and constraints.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Steve is the project manager for a construction project to convert an old nursing home into a new multistory office complex. The architectural design and site surveys are completed, and Steve is now waiting for the clearance and permit from the city to start the construction. This is an example of which kind of dependency?

A. Mandatory dependency

B. Internal dependency

C. External dependency

D. Discretionary dependency

A

Answer: C

Explanation: External dependencies are driven by circumstances or authority outside the project and must be considered during the process of sequencing the activities. Internal dependencies are based on the needs of the project and are mostly under the control of the project team. Mandatory dependencies are mandatory and unavoidable dependencies that are inherent in the nature of the work or are contractually required. They are like laws of nature and are also called “hard logic.” Discretionary dependencies are also called “preferred logic” or “soft logic” as they are the preference of the project planner and the team members. These dependencies may be determined by best practices or by local methodology and may vary from project to project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Your team has been working with the WBS for a while and has completed the decomposition of the work packages. After a week, the team finalized the estimates of all activities and completed the network diagram. Which of the following activities will be the next to concentrate on for the project manager?

A. Develop a preliminary schedule and get the approval from the team members

B. Finalize the Project Scope Statement

C. Use the precedence diagramming method for sequencing the activities

D. Develop the risk management plan and add it to the total Project Management Plan document

A

Answer: A

Explanation: The project manager should now focus on developing the preliminary schedule and get the approval from the team members. Finalizing the Project Scope Statement should have been completed prior to completing the WBS. The team members have completed the network diagram, which suggests that the activities sequencing is also completed. Since the project schedule is an input to risk management, developing the risk management plan should be done once the schedule is completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Which of the following is FALSE about analogous estimating?

A. It measures the project parameters such as budget, duration, size, complexity, and duration based on the parameters of a previous similar project and historical information.

B. It is usually done during the early phase of the project when not much information is available.

C. It uses a bottom-up approach.

D. It usually is the overall project estimate given to the project manager from management or the sponsor.

A

Answer: C

Explanation: Analogous estimates take a top-down approach, and the overall project estimate is usually given to the project manager from the management or the sponsor. It is usually done during the early phase of the project when not much information is available. It is less accurate even though it is less costly and less time consuming. In a bottom-up approach, one estimate per activity is received from the team members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

You recently took over a project from another project manager. While reviewing the network diagram, you find that there are four critical paths and three near-critical paths. What can you conclude about the project?

A. The project will likely be completed on time and within budget.

B. The project is at high risk.

C. The project will require more people and additional budget.

D. The project should be terminated.

A

Answer: B

Explanation: The project is definitely at high risk because activities on critical path and near critical path can be delayed anytime causing the entire project to be delayed. Having more than one critical path and several near-critical paths does not necessarily mean that more resources and additional budget will be required to complete the project. There is no valid reason to terminate the project just because it is at high risk of schedule delay.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

You are overseeing a data center project for one of your clients. The team members have finished creating the Work Breakdown Structure (WBS) and Work Breakdown Structure Dictionary. The team members also submitted their activity duration estimates to you. Recently, you came up with the project estimate by adding estimates for all activities from the team members. What did you do wrong in this case?

A. The estimates should be coming from senior management

B. The project estimate should be the same as the required completion date from the customer

C. You didn’t use a Network Diagram

D. You should come up with the estimates for all activities by yourself

A

Answer: C

Explanation: As a project manager, you should not be coming up with individual activity estimate. The team members will be working on the activities and should come up with the estimates for their activities. Estimates should also not be coming from senior management or customers but they may let you know their expected completion date for the project. You will be able to identify that some activities may take place concurrently by refrying to your Network Diagram. If you just add up all the activity estimates without considering the sequence and concurrent activities, your estimate will not be correct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

Your project sponsor is extremely disappointed with the project as it is over budget by $20,000 and also behind schedule by several weeks. The sponsor has asked you to take care of the situation immediately. While desperately exploring different options to shorten the project duration, you realize that you have no access to additional resources. Your team took care almost all of the risk items and currently you have only discretionary dependencies. As a project manager, what will be your best course of action?

A. Remove a big activity from the project

B. Remove resources from an activity

C. Add additional resources to complete remaining activities faster

D. Fast track the project

A

Answer: D

Explanation: Removing an activity may save you time but your customer will be very unhappy if you do so. Removing resources will not really save you any time. You can’t add additional resources as you have no access to it. Since most of the risk items are closed and you have discretionary or preferential dependencies, you should be fast-tracking or working on some of the activities concurrently.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

The project manager and the team members have just finished working on the WBS and have almost finalized the project schedule. The project manager is also planning to start working on the project budget. Which document will be used for planning, estimating, budgeting, and controlling costs so that the project can be completed within the approved budget?

A. Earned value management

B. Cost baseline

C. Cost Management Plan

D. Funding limit reconciliation

A

Answer: C

Explanation: The project Cost Management Plan is a component of the overall project management plan, and it defines how the project cost will be planned, managed, expended, and controlled throughout the project life cycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

The Earned Value Management (EVM) will NOT be very beneficial in which situation?

A. To measure a project’s progress against the project scope, cost, and schedule baselines.

B. To forecast future performance and the project’s completion date and final cost.

C. To provide schedule and budget variances during the project.

D. To develop the project cost baseline.

A

Answer: D

Explanation: Earned value analysis provides a means to determine cost and schedule variances, not to develop the project cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

You are preparing a Cost Management Plan for the data center project you are managing for ITPro Consultancy, LLC. All of the following is true regarding this plan EXCEPT:

A. Activity cost estimates will be rounded to a prescribed precision; for example, $100, $1,000, and so on.

B. Units of measurement such as hours, days, weeks, or a lump sum amount will be used to estimate resources.

C. The primary concern is determining the amount of resources needed to complete the project activities.

D. The WBS provides a framework for the Cost Management Plan, and a control account (CA) in the WBS is used to monitor and control the project cost.

A

Answer: C

Explanation: The primary concern for Project Cost Management is to determine the cost of resources, not the amount to complete the project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

You estimated your project cost to be $80,000 with a timeline of eight months. After four months in the project, you found out that 40 percent of the project is completed; the actual cost is $25,000. What does the SPI tell you in this case?

A. There is not enough information to calculate the SPI.

B. The project is behind schedule.

C. The project is ahead of schedule.

D. The project is progressing as per the plan.

A

Answer: B

Explanation: Here we have BAC = $80,000 We know that EV = BAC * Actual % Complete So EV = BAC * 40 percent completion = $80,000 x 40 percent = $32,000 Also PV = BAC * (Time Passed/Total Scheduled Time) And PV = $80,000 * (4 months/8 months) = $40,000 So SPI = EV/PV = 32,000/40,000 = 0.8 SPI is less than one, which suggests that the project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

You estimated your project cost to be $80,000 with a timeline of eight months. As of today, you found out that 40 percent of the project is completed; the actual cost is $30,000. What does the CPI tell you in this case?

A. There is not enough information to calculate the CPI.

B. The project is over budget.

C. The project is under budget.

D. The project is costing as per the plan.

A

Answer: C

Explanation: Here we have BAC= $80,000 and AC = $30,000 We know that EV = BAC * Actual % Complete So, EV = BAC * 40 percent completion = $80,000 * 40 percent = $32,000 So, CPI = EV/AC = 32,000/30,000 = 1.066 CPI is more than one, which suggests that the project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

You just completed your Cost Management Plan and defined how the project cost will be planned, managed, expended, and controlled throughout the project life cycle. You also looked into your variance threshold, which is usually expressed as percentage deviations from the cost baseline that the sponsor or stakeholders are willing to allow before any action is required. This threshold is called:

A. Approved threshold

B. Variance limit

C. Control threshold

D. Control limit

A

Answer: C

Explanation: Control thresholds are usually expressed as percentage deviations from the cost baseline that the sponsor or stakeholders are willing to allow before any action is required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

Which one of the following is FALSE about TCPI?

A. TCPI calculates the performance that must be achieved in order to meet financial or schedule goals.

B. TCPI usually determines the status on the remaining work with respect to the funds remaining.

C. If the cumulative CPI falls below the baseline plan, all future work must be performed at the TCPI to achieve the planned BAC

D. If the cumulative CPI falls below the baseline plan, all future work must be performed below the TCPI to achieve the planned BAC.

A

Answer: D

Explanation: TCPI calculates the performance that must be achieved in order to meet financial or schedule goals and determines the status on the remaining work with respect to the funds remaining. If the cumulative CPI falls below the baseline plan, all future work must be performed at the TCPI to achieve the planned BAC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

All of the following statements are true about cost baseline EXCEPT:

A. It is a time-phased budget used to monitor, measure, and control cost performance during the project.

B. It is usually displayed in the form of an S-curve.

C. It assigns cost estimates for expected future period operating costs.

D. It aggregates the estimated costs of project activities to work packages, then to control accounts, and finally to the project.

A

Answer: C

Explanation: Expected future period operation costs are considered to be ongoing costs and should not be part of the project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

While working on your project budget, you also calculated the contingency reserve. This contingency reserve is the estimated cost to be determined, managed, and controlled at your discretion to deal with which of the following?

A. To compensate inadequacies in your original cost planning.

B. To address the cost impact of the risks remaining during the Plan Risk Responses process.

C. To handle anticipated and certain events in your project.

D. To handle unanticipated events or surprises in your project.

A

Answer: B

Explanation: The project manager determines, manages, and controls the contingency reserves, which will address the cost impact of the risks remaining (residual risks or known unknown risks).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Lori is the project manager for a software development firm and has been assigned to create an accounting automation application for a dentist’s office. While reviewing the cost estimate with Lori, the sponsor expressed her frustration with the higher cost and asked to reduce the estimate by at least ten percent. The sponsor is not too worried about the project duration estimate and suggested that Lori seek her help with the schedule if needed. What is the best course of action for Lori in this kind of situation?

A. Replace a couple of expensive resources with lower-cost resources.

B. Continue with the project and constantly find an opportunity to save money for a total savings of 10 percent.

C. Have an urgent meeting with the team members and ask them to be innovative and squeeze their estimate.

D. Inform the sponsor of the activities to be cut.

A

Answer: D

Explanation: The project manager is expected to come up with a realistic estimate that does not include padding. The project manager also should not simply reduce the estimate whenever asked by the sponsor or clients. If the project manager must reduce the estimate, she needs to explore other options such as cutting scope, reducing quality, or replacing expensive resources with lower-cost resources. In this case, Lori should inform the sponsor the activities to be cut in order to reduce the estimate by ten percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Selina is a project manager involved in the Estimate Costs process in the early phase of her project when a limited amount of detail was available to her. The range of her estimate was $75,000 to $200,000, and the actual cost came to be around $150,000. What would you call such an estimate?

A. A variable estimate

B. A definitive estimate

C. A rough order of magnitude estimate

D. A budget estimate

A

Answer: C

Explanation: A rough order of magnitude (–25 percent to 75 percent) is an approximate estimate made without detailed data. This type of estimate is used during the formative stages for initial evaluation of a project’s feasibility. In this example, $75,000 and $200,000 are –25 percent to +75 percent of $150,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

You have fifteen components to work on in a software development project. As per your estimation, the first six components would cost $1,500 each, and the remaining nine would cost $1,400 each. Your schedule projected that you would be done with 40 percent of the components today. While collecting the status updates from the team members, you found out that the first five components were completed at a cost of $8,000. What is the SPI?

A. 1.2

B. 0.132

C. 0.833

D. Cannot be determined

A

Answer: C

Explanation: The budget for the first six components is 6 * $1,500 = $9,000, and the budget for the remaining nine components is 9 * $1,400 = $12,600. So, BAC = $9,000 + $ 12,600 = $21,600 We know PV = BAC * Planned % Complete So, PV = 21,600 * 40 percent = $8,640 We have a total of fifteen components and so far, completed five components. EV = BAC * (Work Completed/Total Work Required) So, EV = $21,600 * 5/15 = $7,200 So, SPI = EV/PV = 7200/8640 = 0.833

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

You are working on a project to convert an old nursing home to a new office complex. While reviewing the progress of your project, you found out that your EV = $26,000 and AC = $27,000. One of your site supervisors calls to inform you that there are several damages in the foundation that were not discovered earlier, and it will result in a significant cost overrun. What will you do FIRST?

A. Make sure that the contingency reserves you have will be sufficient enough to cover the cost overrun.

B. Call the sponsor immediately and inform her that additional funds will be needed.

C. Ask the supervisor to figure out why these damages were not discovered earlier.

D. Evaluate the cause and size of this cost overrun.

A

Answer: D

Explanation: The first step should be to get as much information as possible about the damages in the foundation by evaluating the cause and size of the damage and the amount needed for the fix. You can take other actions as appropriate once you have all the details.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

You are managing a software application project budgeted for $90,000 to develop an online PMP exam simulator. The team has completed design work, received approval from technical review team, and initiated coding work. You think that the current variances are atypical, and that similar variances will not occur in the future. You found that AC = $30,000 and EV = $35,000. What is your Estimate at Completion (EAC)?

A. $85,000

B. $77,586

C. $90,000

D. $60,000

A

Answer: A

Explanation: If current variances are considered as atypical and you anticipate that similar variances will not occur in the future, the correct EAC formula is EAC = AC + (BAC – EV). In this case, BAC = $90,000 EAC = $30,000 + ($90,000 – $35,000) = $85,000 c

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of inadequate results is:

A. Quality assurance

B. Quality planning

C. Quality control

D. Quality management

A

Answer: C

Explanation: Quality control is utilized to monitor and record results during execution of quality activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Conformance to specifications—or making sure a project produces what it was created to produce—prevention over inspection, and zero defects are key items emphasized by:

A. W. Edwards Deming

B. Phil Crosby

C. Joseph Juran

D. None of the above

A

Answer: B

Explanation: Phil Crosby popularized the concept of the cost of poor quality, advocated prevention over inspection and “zero defects,” and defined quality as conformance to specification (project produces what it was created to produce).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

You are planning to hire a third-party auditor to perform a scheduled or random structured review to determine whether your quality management activities comply with organizational and project processes, policies, and procedures. All of the following will be done in this quality audit EXCEPT:

A. Identify ineffective and inefficient activities or processes used on the project.

B. Identify required improvements, gaps, and shortcomings in the processes.

C. Create quality metrics.

D. Recommend changes and corrective actions to Integrated Change Control.

A

Answer: C

Explanation: A quality audit is done in the Manage Quality process, and quality metrics, which are the outputs in the Plan Quality Management process, are used as inputs in the Manage Quality process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

You are overseeing a software application project to implement a custom accounting and financial system for medium to large- sized corporations. The quality assurance team submitted a defect report that has relevant information on the description, severity, root causes, possible resolutions, owner, due date, and reporter of the defects. You intend to know which causes of defects are most serious so that you can prioritize the potential causes of the problems. Which of the following tools should you use to isolate the critical few causes of defects from the uncritical many?

A. Control chart

B. Pareto chart

C. Scatter diagram

D. Fishbone diagram

A

Answer: B

Explanation: A Pareto chart illustrates which causes of error are most serious. It is displayed as a histogram and shows frequency of error according to cause. The concept is based on the 80/20 rule: “80 percent of the problems come from 20 percent of the causes;” thus, it is important to pay close attention to the 20 percent of critical causes in order to resolve 80 percent of the problems. A Pareto chart: – Helps focus attention on the most critical issues – Prioritizes potential causes of the problems – Is used to determine priorities for quality improvement activities – Separates the critical few from the uncritical many.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

A project manager was recently recognized for delivering a high-quality product with no noticeable defects. Some of the stakeholders were skeptical about limited features offered by the product. This kind of product that has a high- level of quality but does not include many of the features of comparable products is referred to as:

A. Low quality

B. Low grade

C. Inaccurate

D. Sketchy

A

Answer: C

Explanation: Products that are produced at an acceptable level of quality and meet the desired requirements of the customer but have limited functionality and features compared to similar products are referred to as low grade.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Plan Quality Management is the process of identifying all the relevant quality requirements, specifications, and standards for the project and product and detailing how the specifications will be met and should be performed:

A. During the initial phase of the project.

B. Prior to the approval of the Project Charter.

C. After the work breakdown structure has been developed.

D. In parallel with the other planning processes.

A

Answer: D

Explanation: Quality management is integrated with many other project planning processes, especially cost and time management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

A project manager working on implementing WIMAX connectivity in a rural area has to deploy several network devices and set up POPs to house those devices. She performed a cost-benefit analysis and was apprehensive about the high cost of nonconformance, or cost that will incur if proper quality is not implemented in her project. In quality management, which one of the following is NOT an attribute of the cost of nonconformance?

A. Processing customer complaints

B. Machinery maintenance and calibration

C. Bad word-of-mouth advertising

D. Field repair work

A

Answer: B

Explanation: Machinery maintenance and calibration is an appraisal function that is included in the cost of conformance. All other costs listed are costs of nonconformance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

As a project manager, you are trying to decide the trade-offs between quality and grade in your project. Which one of the following is correct with respect to a product developed or a service performed?

A. There is no difference between quality and grade.

B. Neither low grade nor low quality is acceptable.

C. Low quality is acceptable, but low grade is not.

D. Low quality is not acceptable, but low grade is.

A

Answer: D

Explanation: A product that is produced at a high-level of quality but does not include many of the features of comparable products is referred to as low grade. A low grade product with limited features may be acceptable, but a low quality product or service is unacceptable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

A project manager is in the Plan Quality Management process of identifying all the applicable quality requirements, specifications, and standards for the project and product and detailing how the specifications will be met. All of the following are true about the Plan Quality Management process EXCEPT:

A. It should begin in the early planning phase in parallel with other planning processes.

B. It should balance the needs of quality with scope, cost, time, risk, and customer satisfaction.

C. It ensures that processes and procedures are giving us the intended results and we are meeting quality objectives.

D. Inputs of this process are Scope Baseline, Stakeholder Register, Risk Register, Enterprise Environmental Factors, and Organizational Process Assets.

A

Answer: C

Explanation: Manage Quality, not Plan Quality Management process ensures that processes and procedures are giving us the intended results and we are meeting quality objectives.

82
Q

A project manager for a business automation project is working with the quality assurance department to improve stakeholders’ confidence that quality management activities will comply with organizational and project processes, policies, and procedures. Which of the following MUST the project manager and quality department have prior to initiating this Manage Quality process?

A. Quality control measurements

B. Change requests

C. Verified deliverables

D. Quality Reports

A

Answer: A

Explanation: Quality control measurements are relevant quality level and compliance measurements. These measurements are inputs to the Manage Quality process. Change requests are outputs for both the Manage Quality and Control Quality processes, and verified deliverables are outputs for the Control Quality process. Quality Reports are the result of the Manage Quality process.

83
Q

Proprietary quality management methodologies are used as tools & techniques in which of the following quality processes?

A. Plan Quality Management

B. Manage Quality

C. Control Quality

D. Perform Quality Management

A

Answer: A

Explanation: Proprietary quality management methodologies such as Six Sigma, Lean Six Sigma, Quality Function Deployment, and CMMI® are used as tools & techniques in the Plan Quality Management process.

84
Q

You are using standard deviation to set the level of quality that your company has decided to achieve and also to set upper and lower control limits to determine if a process is in control. Standard deviation is a measure of how:

A. Accurate the sample data is.

B. Close the estimate is from the lowest estimate.

C. Far the measurement is from the mean.

D. Far apart the upper and lower control limits are.

A

Answer: C

Explanation: Standard deviation is a measurement of range around the mean.

85
Q

While developing the quality metrics, you have defined the product attributes and ascertained how quality will be measured in your project. You have spent a substantial amount of time defining key attributes that are crucial to you and your stakeholders. Which of the following is NOT an example of a product attribute?

A. Number of defects

B. Desirability

C. Availability

D. Defect frequency

A

Answer: B

Explanation: Attributes are those items associated with the actual physical product or deliverable. Failure rate, defect frequency, reliability, cost control, number of defects, availability, test coverage, and on-time performance are product attributes, but desirability is not.

86
Q

A project manager supervising a project to develop an auto crash video simulator for a local auto maker recently created a project budget, formalized a communications management plan after identifying all major stakeholders and their information needs, and was about to contemplate on completing the work packages. As per the instruction of senior management, the project manager has to move to a higher-priority project, leaving the simulator project to another project manager. What should the new project manager do NEXT?

A. Enter in the executing process group.

B. Initiate the Identify Risks process.

C. Facilitate completion of work packages.

D. Identify quality standards.

A

Answer: D

Explanation: The previous project manager did not complete the planning; thus, planning should be completed first followed by executing. Identifying risks and quality standards are both done in the planning process group, but quality standards are identified prior to risk identification in the project.

87
Q

Which one of the following statements is TRUE about verified deliverables? Verified deliverables are:

A. Outputs of the Control Quality process and inputs to the Validate Scope process.

B. Inputs to the Control Quality process and outputs of the Validate Scope process.

C. Tools and techniques of the Control Quality and Validate Scope processes.

D. Outputs of the Control Quality and Validate Scope processes.

A

Answer: A

Explanation: Verified deliverables are Outputs of the Control Quality process and inputs to the Validate Scope process.

88
Q

There are 33 work packages in your cyber security implementation project. The project is supposed to safeguard all your clients critical and sensitive information using different cryptographic and hashing techniques. While reviewing the packages, you realized that 2 of the packages have not met the quality metrics. After further research, your team concludes that it is not possible to meet the metric at this time. You met with the team and other relevant stakeholders to analyze the situation and determine the impact. Which of the following process are you involved in?

A. Plan Quality Management

B. Manage Quality

C. Control Quality

D. Perform Integrated Change Control

A

Answer: C

Explanation: Measuring specific project results against quality standards and required metrics is part of the Control Quality process. In this situation, there is a high probability that a change request will be submitted to Perform Integrated Change Control process.

89
Q

Your team has just completed implementing a Data Loss Prevention Application to stop internal employees from stealing valuable top secret information for one of your valuable customers. You realized that the developers added some features that were not asked for to add value and impress the customer. The customer sent out a note to your manager expressing satisfaction with the project. Which one of the following is the most accurate statement about this project?

A. It is a successful project for meeting and exceeding the customers’ expectation

B. There is a good possibility that the customer will give you more business in future

C. The project is a success as it gave the team the opportunity to learned new features

D. The project is unsuccessful as it was gold plated

A

Answer: D

Explanation: Gold plating is the practice of making changes to a project that are beyond the original agreed-upon scope. Gold plating is time consuming and expensive in most cases. Gold plating is generally seen as a poor practice. Despite best intentions, the added work is often risky. Gold plating may take longer than anticipated, pushing a project past its due date. The additional changes can even have a negative effect on the existing functionality. Advanced quality thinking doesn’t recommend gold plating as a best practice. The project manager should make sure that team members are not providing extra features, extra functionalities, or higher quality than expected in the project.

90
Q

As an experienced construction project manager, you realize that almost all construction projects vary from the original design, scope and definition due to technological advancement, statutory changes or enforcement, change in conditions, geological anomalies, non-availability of specified materials, or simply because of the continued development of the design after the contract has been awarded. In your project, the design requires thickness tolerances of +3/8 to -1/4 inch for slabs less than 12 inches and +1/2 to -3/8 inch for slabs more than 12 inches thick. In which document will the project manager document this if needed?

A. Quality Report

B. Quality Policy

C. Quality Management Plan

D. Risk Register

A

Answer: C

Explanation: The Quality Management Plan documents quality objectives, expected quality level, quality standards, metrics, and other quality related items. The defined level of required thickness tolerances would be documented in the Quality Management plan.

91
Q

A project manager is in the Collect Requirements process of collecting and documenting quantifiable needs and expectations of the sponsor, customer, and other stakeholders. Which of the following is NOT true regarding this process?

A. It describes project deliverables and the work required to create them in detail as well as deliverables description, product acceptance criteria, requirements assumptions and constraints, and exclusions from requirements.

B. Requirements Documentation and Requirements Traceability Matrix are the key outputs in this process.

C. Various Data Gathering Techniques and Decision Making techniques are used as tools & techniques in this process.

D. The Scope Management Plan and Requirements Management Plan are inputs in this process.

A

Answer: A

Explanation: The Project Scope Statement, not the Requirements Documentation, describes project deliverables and the work required to create them in detail as well as the deliverables description, product acceptance criteria, requirements assumptions and constraints, and exclusions from requirements.

92
Q

The team members are analyzing the objectives and description of the product stated by the customer or sponsor and turning them into tangible deliverables and finally creating the Project Scope Statement. Which of the following BEST describes what the team members are doing?

A. Performing the product analysis

B. Performing the plan quality management

C. Conducting a multi-criteria decision analysis

D. Determining the product description

A

Answer: A

Explanation: The team members are gaining a better understanding of the product of the project to create the Project Scope Statement by performing the product analysis. The team must have a product description before they can perform product analysis. The level of quality desired is analyzed in the plan quality management, not in product analysis. The multi-criteria decision analysis is a technique to evaluate and rank ideas. This technique uses a decision matrix based on factors such as uncertainty, expected risk levels, cost and benefit estimates, and time estimates to quantify requirements.

93
Q

Your project to build a new substation to supply power to a newly developed industrial park is not going too well. The Net Present Value (NPV) of the project is $560,000 and the payback period is 3 years. After six-and-a-half months of work, the project is on schedule and budget, but requirements have been changing throughout the project. You became extremely worried to find out that a substantial amount of new change requests are coming from your key stakeholders, customers, and even from your manager. You are anxious that these changes will drastically increase the cost and time of the project. Which of the following will MOST likely happen in your project?

A. You may need to add additional resources.

B. You may need to cut cost.

C. You may need to terminate the project.

D. You may not be able to measure completion of the product of the project. .

A

Answer: D

Explanation: Nothing in this is suggesting that you may need to cut cost, add resources, or terminate the project. Not having complete requirements will make it difficult to measure as requirements are used to measure the completion of the product of the project.

94
Q

Your project sponsor is extremely disappointed with the project as it is over budget by $20,000 and also behind schedule by several weeks. The sponsor has asked you to take care of the situation immediately. While exploring different options to shorten the project duration, you decide, with management’s approval, to perform several activities in parallel rather than in sequential order as originally planned. You know your option will possibly result in rework, increase risks, and require more communication, but you decide to go for it any way. This is an example of which of the following?

A. Critical chain method

B. Crashing

C. Resource leveling

D. Fast-tracking

A

Answer: D

Explanation: Fast-tracking is the technique of doing critical path activities in parallel when they were originally planned in series.

95
Q

You have recently been assigned as a program manager to implement an ERP solution in your organization. Initially, the team will only work on five key modules in the first phase of the project. The second phase of the project has not been approved yet. You have estimated that three of the modules will take ten days each, and the remaining two will be completed in fifteen days each. It is not possible to work on these modules in parallel. What would be the approximate duration for the first phase of your project?

A. Fifty-five to sixty-five days

B. Fifty days

C. Ten days

D. Ninety days

A

Answer: A

Explanation: The duration of three modules is 10 * 3 = 30 days, and the remaining two modules is 2 * 15 = 30 days. The first phase of the project will take 30 + 30 = 60 days, or approximately between fifty-five and sixty-five days.

96
Q

You are in the Control Schedule process of monitoring the status of the project by comparing the result to the plan, updating project progress, and managing changes to the project schedule baseline. You are mainly focused on the current status and changes to the project schedule, influential factors that create schedule changes, and management of actual changes as they occur. Which of the following is NOT a tool or technique in this Schedule Management process?

A. Schedule compression

B. Critical Path Method

C. Resource optimization

D. Schedule forecasts

A

Answer: D

Explanation: The schedule forecasts are outputs of the Control Schedule process, not tools & techniques.

97
Q

Steve has just been assigned as a project manager for a newly approved software development project. The sponsor is interested in knowing a high-level estimation on the total duration of the project and asks Steve to send him the information by the end of the day. What kind of estimate should Steve use in this kind of situation?

A. An analogous estimate

B. A heuristic estimate

C. A three-point estimate

D. A bottom-up estimate

A

Answer: A

Explanation: An analogous estimate is usually done during the early phase of the project when not much information is available about the project. It is less accurate even though it is less costly and less time consuming. In a bottom-up approach, one estimate per activity is received from the team members; it requires significant time to develop. A heuristic estimate is based on rule of thumb. A PERT estimate, also known as a weighted average estimate, is usually associated with specific project activities and requires significant time to develop as well.

98
Q

You are in the Estimate Activity Durations process to estimate durations for the activities of the project. These estimates usually originated from project team members most familiar with the activity and then progressively elaborated. Which one of the following is TRUE about this process?

A. This process must be performed after the Develop Schedule process.

B. Padding is a common practice and the project manager should not be too worried about it.

C. The duration estimates are outputs in this process.

D. It is not important that all estimates in this process should use a common workunit/ period.

A

Answer: C

Explanation: The duration estimates are outputs in the Estimate Activity Durations process. This process should be performed before the Develop Schedule process. Adding additional time or padding the estimate is a common practice in this process, so the project manager should make sure that the estimates from the team members are realistic. It is important that all estimates in this process should use a common work unit/period.

99
Q

You just completed developing the schedule for your project and got the approval from stakeholders and the sponsor. One of the team members assigned to work on a critical component informs you that she needs additional time to complete her activities as several relevant pieces were missed during planning. Her updated estimate would have no impact on the critical path; thus, the project duration would be the same. The best approach the project manager may take in this situation will be:

A. Find a replacement for the resource who can complete the task within the allocated time.

B. Inform the resource that it is too late for any kind of change in the project schedule.

C. Inform her that it is OK as you have sufficient schedule reserve to handle this kind of situation.

D. Update the project schedule and other relevant plans to reflect the new estimate.

A

Answer: D

Explanation: The best course of action will be to update the project schedule and other relevant plans to reflect the new estimate.

100
Q

You are overseeing a data center project for one of your clients. The team members have finished creating the Work Breakdown Structure (WBS) and Work Breakdown Structure Dictionary. The team members also submitted their activity duration estimates to you. What should you focus on NEXT?

A. Sequence the activities using the precedence diagramming method.

B. Create the activity list.

C. Determine high-level project assumptions and constraints.

D. Develop the project schedule.

A

Answer: A

Explanation: Your team has created the WBS, WBS Dictionary, and activity list and has submitted the activity durations. The next step should be to sequence the activities by creating a network diagram using the precedence diagramming method. Determining high- level project assumptions and constraints is done as part of project initiation and is completed much earlier. The Develop Schedule process follows the Sequence Activities process. Note that sequencing activities can be done before or after the activity duration estimation is done.

101
Q

You are overseeing a data center project for one of your clients. The team members have finished creating the Work Breakdown Structure (WBS) and Work Breakdown Structure Dictionary. The team members also completed activity sequencing and submitted their activity duration estimates to you. Recently, you developed the project schedule. What should you focus on NEXT?

A. Finalize the schedule

B. Control the schedule

C. Compress the schedule

D. Gain approval

A

Answer: C

Explanation: The Control Schedule process is the next process after the Develop Schedule process, but all the activities of the Develop Schedule process are not completed yet. Once the schedule is developed, it should be compressed, finalized, and approved by the stakeholders. Then you should start controlling the schedule.

102
Q

Your IT project is progressing well and is on schedule when a vendor sends you an e-mail stating that the equipment delivery will be delayed by a week due to severe snow storm on the East Coast. Which of the documents would best capture the impact of the delay on the project schedule?

A. Risk Register

B. Issue Log

C. Network Diagram

D. Work Breakdown Structure

A

Answer: C

Explanation: The project network diagram represents activities and their logical relationships, dependencies, and sequence; thus, the network diagram will best capture the impact of the delay on the project schedule. The work breakdown structure is a deliverable- oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables, but it does not focus on the duration of the project activities. The risk register would show an increase in project risk but would not help to determine the impact of a delay on the project schedule. An issue log will also capture the root cause, person assigned, due date, and other factors but will not give out much information about the impact of the delay on the project schedule.

103
Q

Your IT project has ten team members, and recently you have hired three more database developers. You are using a time- phased graphical display of activity start dates, end dates, and durations for tracking progress and reporting to the team. Which chart are you using?

A. Milestone Chart

B. Work breakdown Structure

C. Network Diagram

D. Gantt Chart

A

Answer: D

Explanation: A Gantt chart or bar chart is a time-phased graphical display of activity start dates, end dates, and durations. It is useful for tracking progress and reporting to the team and can be easily modified to show the percentage of completed work. As the project progresses, bars are shaded to show which activities are now completed. The work breakdown structure is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables, but it does not focus on the duration of the project activities. A milestone chart is similar to a bar chart but only shows major events. It is a good tool for reporting to management and customers. This type of chart is reserved for brief, high- level presentations as too much detail may be undesirable and distracting to senior management. A network diagram is a schematic display of the sequential and logical relationships of the project activities. It shows dependencies and the order in which activities in a project must be performed.

104
Q

Your company just initiated a project to install a Wi-Fi network in one of the Asian countries. One of the clients offers gifts to all your team members and requests you to give his office a dedicated connection with the max bandwidth possible. What should you do in this situation?

A. Reject the gifts and never communicate with that client again

B. Accept the gifts but refuse to give the dedicated connection.

C. Reject the gifts as accepting gifts is a violation of the code of ethics and professional conduct.

D. Accept the gifts and agree to give the dedicated connection as it will not cost any extra to the project.

A

Answer: C

Explanation: The client is making a request by offering gifts; thus, you should reject the gifts as it is a violation of the PMI code of ethics and professional conduct. A project manager is expected to be honest and should not engage in dishonest behavior with the intention of personal gain or at the expense of others. If it is customary in that country to offer gifts, you may accept the gift without agreeing to the client’s request of dedicated connection. Not communicating with the specific client may impact the project.

105
Q

You are participating in a bid in a foreign country for a company that wants to procure several expensive pieces of hospital equipment. You have meticulously followed the bidding procedure and are expecting to be the most qualified and lowest bidder. One of the representatives of the procuring company contacted you and asked for 10 percent commission on the total price or they would award the deal to some other vendor. What will be your BEST course of action?

A. Contact PMI immediately and report the situation.

B. Negotiate the commission and try to bring it down as much as possible.

C. Deny the offer and notify your management.

D. Agree to give 10 percent to secure the deal.

A

Answer: C

Explanation: You should never bribe even though it may help you win a project. Your best course of action will be to deny the offer and disclose the incident to higher management.

106
Q

The project manager has just spoken to one of the software developers, Bill on the project and has asked for an estimate of how long it will take to code a specific function. Bill said the maximum amount of time it will take will be 10 days. He also stated that the most likely amount of time will be 6 days. The project manager has calculated the PERT estimated duration of this activity to be six days. What is the least amount of days it will take to complete this activity?

A. 1

B. 2

C. 3

D. 4

A

Answer: B

Explanation: in this you have to use the PERT formula which is (O+4R+P)/6 and find the optimistic number. The gives you the answer to the formula which is 6 days and you will need to figure out the other components. In the the pessimistic is given which is 10, the realistic is 6 and you have to find out the optimistic number. Plug the numbers into the formula which looks like this: (O+46+10)/6=6. Based on this equation the optimistic is equal to 2.

107
Q

The risk management plan generally outlines the steps the project will take to conduct the processes to manage risks on the project. Which of the following with the risk management plan not include?

A. A way to categorize the risks

B. Roles and responsibilities for the project team concerning risks processes

C. Positive risk that could affect the project

D. The methodology used to manage risks

A

Answer: C

Explanation: The risk register will list both positive and negative risks not the risk management plan. Risk management plan will include the risk breakdown structure that will categorize risks, roles and responsibilities for the team members, and the methodology they would use to perform the risk processes on the project.

108
Q

Mary was just rewarded by senior management of her company to manage the new datacenter renovation project. She is very excited about this new project since it is something she has been trying to get done for a long time. What process will Mary perform right after she has been assigned to this new project?

A. Develop Project Management Plan

B. Collect Requirements

C. Define Scope

D. Identify Stakeholders

A

Answer: D

Explanation: Since Mary has just been assigned the project, we can assume that the project charter is done. Once the charter is complete the next process would be to identify your stakeholders before completing any of the planning processes which are the other 3 choices.

109
Q

The project was executed about three weeks ago and the project team seems to be having a lot of difficulties getting along with each other. They are always having a conflict about how to proceed on certain activities and the project manager has to step in in order to solve this conflict. What process is the project manager performing?

A. Acquire Team

B. Control Resources

C. Control Scope

D. Manage Team

A

Answer: D

Explanation: in the process of managed team the project manager has to resolve issues and conflicts amounts project team. This is done using the tool interpersonal and team skills, particularly conflict management. Acquire team is not a process in the PMBOK. Control resources is a process that involves physical resources not human resources. Control scope is about preventing scope creep and ensuring the project meets the scope.

110
Q

The project manager and team are currently working to create a list of activities that will be needed to complete the project. They have come to one particular work package that they cannot decompose currently because they do not know enough about the work yet. They have decided that midway through the project they will decompose this particular work package. What tool or technique are they using?

A. Decomposition

B. Forward Planning

C. Rolling Wave Planning

D. Requirements Future Planning

A

Answer: C

Explanation: Rolling wave planning is a tool used in the process of define activities to breakdown work in the near future in details and work farther into future more high-level. Forward Planning and requirements future planning are not real tools used in the process of define activities. Decomposition is a tool that’s used to breakdown the activities currently.

111
Q

The project manager is having a very difficult time collecting the requirements from the customers. The customers are having a difficult time putting the requirements into a logical grouping. What tool can help group the requirements?

A. Prototype

B. Affinity Diagram

C. Decomposition

D. Requirements Documentation

A

Answer: B

Explanation: An affinity diagram is used to group large number of ideas to be analyzed. A prototype is a functional model of a product, given to customers for their feedback. Decomposition is a tool used to breakdown work into more detail activities. The requirements documentation would be the output of this process of collect requirements not a tool.

112
Q

You are in the Plan Resource Management process of identifying and documenting project roles, responsibilities, required skills, competencies, reporting structure, and other items. Which of the following Hierarchical-Type chart can help you track project cost as it ties to the organization’s accounting system?

A. Resource Breakdown Structure (RBS)

B. Organizational Breakdown Structure (OBS)

C. Responsibility Assignment Matrix (RAM)

D. Position descriptions

A

Answer: A

Explanation: A Resource Breakdown Structure (RBS) looks like a typical organizational chart, but it is organized by types of resources. An RBS can help track project cost as it ties to the organization’s accounting system. An Organizational Breakdown Structure (OBS) is similar to a company’s standard organizational chart that looks like a WBS but only includes the positions and relationships in a top- down, graphic format. It is arranged according to an organization’s existing departments, units, or teams with their respective work packages. Any operations department such as manufacturing or engineering, can identify all of its project responsibilities by looking at its portion of the OBS. A Responsibility Assignment Matrix (RAM) cross-references team members with the activities or work packages they are to accomplish. One example of a RAM is a Responsible, Accountable, Consult, and Inform (RACI) chart, which can be used to ensure clear divisions of roles and responsibilities. A text-oriented position description, or role-responsibility-authority form, is particularly important in recruiting. It is used to describe a team member’s position title, responsibilities, authority, competencies, and qualifications in detail.

113
Q

A project manager is in the Develop Team process, focusing on enhancing project performance by building a sense of team and improving the competencies, team interaction, and overall team environment. While referring to Tuckman’s model, she notices that the team members begin to start trusting and working together as they adjust work habits and behaviors to work as a team. What stage of team development is the project manager referring to?

A. Forming

B. Adjourning

C. Storming

D. Norming

A

Answer: D

Explanation: The team members are in the Norming stage as they are adjusting work habits and behaviors to work as a team. They begin to start trusting and working together.

114
Q

You are considering the idea of putting all team members in the same physical location for the first time. All of the following is true about colocation EXCEPT:

A. The goal is to enhance team members’ ability to perform as a team.

B. It is also called a war room.

C. It is meant to identify concerns and issues and to come up with mutually agreed-upon solutions.

D. The goal is to identify the individual(s) or team responsible for project issues and inform them about it.

A

Answer: D

Explanation: The objective of collocation, or the war room, is to build a better relationship among the team members, enhance their ability to perform as a team, identify concerns and issues in the project, and figure out solutions for those issues. The idea is not to point fingers at other team members or get involved in any kind of argument.

115
Q

You are in the Plan Resource Management process of identifying and documenting project roles, responsibilities, required skills, competencies, reporting structure, and other items. Which one of the following will you NOT use as a tool & technique in this process?

A. Hierarchical-type Charts

B. Recognition and Rewards

C. A responsibility Assignment Matrix

D. Organizational Theory

A

Answer: B

Explanation: Recognition and Rewards are used as a tool & technique in the Develop Team process, not in the Plan Resource Management process. Hierarchical-type charts, a Responsibility Assignment Matrix (which is a matrix-type organizational chart), and Organizational Theory all are used as tools & techniques in the Plan Resource Management process.

116
Q

You were informed by management that an external audit team will be auditing your project to make sure that the project complies with standard organizational project management policies and procedures. During the audit, the key auditor wants to review the training plan for the team members as well as their certification requirements. You should refer the auditor to which of the following?

A. Resource Management Plan

B. RACI Chart

C. Training and Certification Management Plan

D. Resource Breakdown Structure

A

Answer: A

Explanation: The Resource Management Plan identifies the training needs and certification requirements of the team members. One example of a responsibility assignment matrix is a RACI (Responsible, Accountable, Consult, and Inform) chart, which can be used to ensure clear divisions of roles and responsibilities. Training and Certification Management Plan is a fake term. A Resource Breakdown Structure (RBS) looks like a typical organizational chart, but this one is organized by types of resources. An RBS can help track project cost as it ties to the organization’s accounting system.

117
Q

While overseeing a data center project, you notice that one of the team members is extremely dedicated to the project and a consistent overachiever. In order to appreciate her spectacular work and great contribution, you made her the ‘team member of the month’ three times in a row. What kind of impact will this have on the project team?

A. This will initiate a healthy competition among the team members.

B. This will drastically improve team cohesiveness.

C. This will negatively impact team morale.

D. Team members hardly care about recognition and rewards; thus, there will be no impact.

A

Answer: C

Explanation: A project manager can kill the team morale by consistently rewarding the same individual repeatedly as it can be perceived that the project manager is playing favorites. If the team members believe that the rewards are win-lose and that only certain team members will be rewarded, it may demoralize them. In this kind of situation, the project manager can consider team awards, which is a win-win as all the team members are recognized for their contributions.

118
Q

You are a project manager who believes steady employment leads to high employee satisfaction and morale, increased loyalty to the organization, and increased productivity. Which theory do you subscribe to?

A. McGregor Theory X and Theory Y

B. Fred E. Fiedler’s Contingency theory

C. Dr. Willam Ouchi’s Theory Z

D. Victor Vroom’s Expectancy theory

A

Answer: C

Explanation: Theory Z was introduced by Dr. Willam Ouchi. This theory is concerned with increasing employee loyalty to his/her organization. This theory emphasizes the well-being of employees both at work and outside of work, it encourages steady employment, it leads to high employee satisfaction and morale, and overall it results in increased productivity.

119
Q

Mary, a project manager, is in the Develop Team process, focusing on enhancing project performance by building a sense of team and improving the competencies, team interaction, and overall team environment. While referring to Tuckman’s model, she notices that the team is in a stage where her role is mostly overseeing and delegating. The team is in which stage of team development?

A. Forming

B. Adjourning

C. Storming

D. Performing

A

Answer: D

Explanation: As per Tuckman’s model, in the Performing stage, the team functions as a well-organized unit. They are interdependent and work through issues smoothly and effectively. The role of the project manager is mainly overseeing and delegating.

120
Q

A project manager overseeing a construction project notices that her team members are having constant conflicts over issues. The situation was causing her a lot of concern, and she decides to identify the key causes of the conflicts. While exploring the causes, she finds that the most common causes of conflicts among team members are project priorities, resources, and:

A. Personality

B. Schedule

C. Technical options

D. Administration procedures

A

Answer: B

Explanation: There are several sources of conflict, including schedule priorities, scarce resources, personal work style, cost, and other elements, but it’s important to note that personality differences are not the root cause of conflict; in fact, it’s rarely the case. The three main causes of project conflicts are schedule, project priorities, and resources, as approximately 50 percent of all conflicts come from these three sources.

121
Q

You are overseeing a video conferencing application project and just completed negotiation for three additional resources from different functional areas and extra reserve money for your project. During the negotiation, two of the functional managers were very skeptical about the request for additional resources and were reluctant to assign their resources to your project. At last, a solution was reached in which you were allowed to obtain the resources you requested, but you had to agree to give up some other resources at an earlier date than you had originally planned. What type of conflict resolution technique was used in this situation?

A. Smoothing

B. Compromising

C. Forcing

D. Collaborating

A

Answer: B

Explanation: Compromising is bargaining to some level of mutual (dis)satisfaction to both parties. Parties are asked to lose something to gain something. Smoothing is emphasizing areas of agreement and downplaying differences of opinion. Forcing is exerting one opinion over another. Collaborating focuses on working to combine multiple differing perspectives into one shared perspective and results in a win-win situation for all parties.

122
Q

Your data center project is in a mess, and the entire team is under enormous pressure from management to complete the project on time. At team meetings, team members are continuously pointing fingers at each other and blaming others for the delay in their deliverables. You had an urgent meeting with the sponsor to discuss the situation, and he expressed his interest to attend the meeting to evaluate the situation himself. What will be the BEST course of action for you in this type of situation?

A. Request the sponsor to provide help if possible but not to attend the meeting.

B. Inform the team members that the sponsor will be attending the meeting.

C. Remove the team member from the team who is most vocal and who is causing the most issues.

D. Create new ground rules for the meetings and introduce them to the team members.

A

Answer: D

Explanation: The most effective solution in this type of situation will be to create ground rules and introduce them to the team members. Ground rules identify acceptable and not acceptable behaviors on the project and try to minimize the negative impacts of bad behaviors. Some of the ground rules that will be applicable in this situation include the following: – Methods of how conflict should be resolved – Ways to treat sensitive data in the project – Methods of notifying the project manager about difficulties, issues, and concerns – Acceptable ways to interrupt someone talking at a meeting – Methods to stop talking over a team member inappropriately – Rules for joining meetings and consequences of being late.

123
Q

Your project has 13 team members, 6 stakeholders, and 2 sponsors. You used a Responsibility Assignment Matrix (RAM) to maps specific resources to the work packages from the Work Breakdown Structure (WBS). Your Project Management Office (PMO) asked you to use a Resource Histogram as well. You don’t really understand the benefit of using a Resource Histogram and asked PMO to explain the reason of using it. The PMO explained that one of the following items would be shown in the Resource Histogram but not in the Responsibility Assignment Matrix.

A. Who reports to whom

B. Who will do the work

C. Number of resources used in each time period

D. Interrelationships

A

Answer: C

Explanation: The Responsibility Assignment Matrix (RAM) shows who will do the work and a Resource Histogram shows the number of resources used in each time period that a RAM doesn’t show.

124
Q

You received numerous complaints about an individual from several other team members. This specific team member was not attending meetings or responding to her emails. You tried to smooth the situation and cooled down the other team members as much as you could and even took some her responsibilities. At last, she called you and explained that she was going through a bad divorce which impacted her work. You were really concerned about her and rescheduled some of the activities to allow her more time to cope with the disastrous personal situation. This is a good example of:

A. Contingency theory

B. Theory Z

C. Problem-solving

D. Emotional Intelligence

A

Answer: D

Explanation: Emotional Intelligence is the capacity to be aware of, control, and express one’s emotions, and to handle interpersonal relationships judiciously and empathetically utilizing observation, interpersonal skills, and communication. By making team members feel important and valued, you tried to bring out the best in the team members. In this case, you showed empathy and also worked out a plan for the team member to fulfill her job responsibilities.

125
Q

You team is getting ready to start the testing phase of your Enterprise Resource Planning (ERP) project. The duration of the project is 2 years and a total of six modules will be implemented to automate most of the business processes in your organization. The IT support team just set up a testing environment with a high-end server and spent a big budget on the DBMS licenses. Another project manager also requested to use the testing environment for her project around the same time your team wants to use it. Your organization can only afford to have one such high cost testing environment and leasing is not at all feasible at this time. What should be your last course of action in this situation?

A. Make changes to your project plan to make best use of this situation

B. Ask the sponsor to get involve

C. Have a discussion with the other project manager on a win-win situation

D. Negotiate with the procurement department to lease a testing environment

A

Answer: B

Explanation: As a project manager, you should always deal with a situation and try out different options prior to asking help from the sponsor. You should also be considerate to the needs of the entire organization, not only your ones.

126
Q

Your project is on track and has all the support from sponsors and senior management. You like to motivate and encourage your employees so that they will contribute more to the project. You spent a considerable amount of money from your project budget on shifting the team to an expensive office space with a nice view and also added the term “senior” to their job titles. What is true about this situation?

A. You are paying a lot of attention to motivating agents

B. You have a good understanding of the Herzberg’s theory

C. You took the correct step by giving more attention to the hygiene factors

D. You don’t really understand Herzberg’s theory

A

Answer: D

Explanation: You are trying to make a great working condition better by renting a new office space and upgrading the team members’ titles. Herzberg classified needs under two much larger categories of motivators (opportunity for advancements and achievement, variety of work, sense of responsibility, recognition, and professional growth) and hygiene (compensation, personal life, working conditions, supervisors, security, status, and relationships with peers, subordinates, and supervisors). Destroying hygiene factors can destroy motivation but improving them under most circumstances will not improve motivation. Hygiene factors are not sufficient to motivate people, and motivating agents provide the best positive reinforcement. Motivating people is best done by rewarding people and letting them grow.

127
Q

A Project Manager is in the Manage Communications process of collecting and distributing performance information and is especially focused on reporting against the performance baseline. Which one of the following is an output in this process?

A. Performance reporting

B. Information Management System

C. Communication methods

D. Project communications

A

Answer: D

Explanation: Project reporting, Information Management System, and Communications Methods are tools & techniques in the Manage Communications process; only project communications are the outputs.

128
Q

Your project currently has ten more people assigned to the team besides you. As your project is getting delayed, management wants you to add four additional team members to your project at the end of the month. How many more communication channels will you have once the additional team members are added?

A. 55

B. 50

C. 105

D. 160

A

Answer: B

Explanation: Your team currently has eleven team members including you; thus, the number of communication channels is calculated by using the formula: # of Channels = n* (n – 1)/2 = 11 (11 – 1)/2 = 55 If you add four more resources, then you will have 11 + 4 = 15 team members. So the number of channels will be 15 (15 – 1)/2 = 105 So you will have 105 – 55 = 50 more channels after adding the new resources.

129
Q

You have been asked to provide information about your project’s current performance in terms of the relationships between scope, schedule, and budget. The most appropriate type of report that will accomplish this is:

A. Progress report

B. Earned Value Management report

C. Trend report

D. Status report

A

Answer: D

Explanation: Earned Value Management provides an integrated view of project performance and compares work performed with work planned to be performed and the planned cost of work with the actual cost of work. Progress reports provide information about what has been accomplished so far; a trend report examines project results over time to see if performance is improving or deteriorating. A status report describes where the project now stands regarding performance measurement baselines in cost, schedule, scope, and quality.

130
Q

Which one of the following is not a noteworthy factor in the determination of the method that may be used to transfer information to, from, and among project stakeholders?

A. Availability of technology: Appropriate systems may already be in place, or you may need to procure a new system or technology.

B. Urgency of the need for information: There may be a need to have frequently updated information available at a moment’s notice, or regularly issued written reports may be sufficient.

C. Stakeholder identification: It will provide a list of stakeholders affected by the project and who have interest in the project.

D. Duration of the project: Technology will not likely change prior to the project’s completion or it may need to be upgraded at some point.

A

Answer: C

Explanation: The methods used to transfer information to, from, and among project stakeholders can vary significantly. Factors such as availability of technology, expected project staffing, urgency of the need for information, project environment, duration of the project, and other things may play a significant role in determining the method that may be used to transfer information among project stakeholders. Stakeholder identification will provide a list of stakeholders affected by the project and does not play much of a role in this situation.

131
Q

You are leading a project status meeting with key stakeholders and customers, but it is not going too well. Participants are discussing various topics at random, talking at the same time and interrupting each other, a few of the attendees are not participating in the discussion at all, and two of the customers are busy over the phone. To avoid this kind of situation and have an effective meeting, what meeting rules shouldyou apply?

A. You should have a real purpose of the meeting and invite the right people.

B. You should always schedule your meeting in advance so that people have plenty of time to be prepared for the meeting.

C. You should create and publish an agenda with specific topics to discuss and establish ground rules.

D. You should control who is allowed to speak and who is not and ask everyone to demonstrate courtesy and consideration to each other.

A

Answer: C

Explanation: ‘A’ and ‘B’ will not help too much in this kind of situation as there is no indication here that the right people were not invited to the meeting or the meeting was not scheduled in advance. ‘D’ is not a rule for a meeting. People discussing topics at random suggests that there was no set agenda for the attendees to follow. Establishing and Imposing ground rules will restrict people from talking at the same time and interrupting each other or remaining busy over the phone.

132
Q

You have several internal and external stakeholders involved in your construction project. As a project manager, you need to identify the information type, format, value, and needs for all these stakeholders. Which of the following tools & techniques is used to identify this type of information?

A. Stakeholder Engagement Plan

B. Communications Requirements Analysis

C. Trend Analysis

D. Value Analysis

A

Answer: B

Explanation: Stakeholder communications requirements are determined during communications requirements analysis. The intention is to identify information that is most valuable to stakeholders. The Stakeholder Engagement Plan is an output to Plan Stakeholder Engagement process, and it defines an approach to manage stakeholders and to increase support for and minimize negative impacts on stakeholders throughout the entire project life cycle. A trend analysis examines project results over time to see if performance is improving or deteriorating. Value analysis or value engineering is associated with product analysis, and it helps to find a less costly way to do the same work without loss of performance.

133
Q

You have been managing a multi-year construction project for one of your most important clients. You requested your lead business analyst to develop a report that will capture project results for the last four years and illustrate whether project performance is improving or deteriorating. You are interested in which of the following reports?

A. Trend report

B. Variance report

C. Forecasting report

D. Progress report

A

Answer: A

Explanation: The trend report examines project results over time to see if performance is improving or deteriorating.

134
Q

You have fifteen identified internal and external stakeholders in the network infrastructure project you are supervising. You are sending out progress and status reports to all your stakeholders on a regular basis as per your communications management plan. One of the stakeholders needs a very specific progress report on her team’s deliverables and sends you an urgent e-mail requesting you to send the report as soon as possible. Your bandwidth is almost fully occupied in various project-related activities, but you have to find some spare time to fulfill this unexpected request from the stakeholder. What will be your BEST course of action?

A. Consider it as part of the Manage Communications process and send out the requested report.

B. Consider it as gold plating and ignore the request from the customer.

C. Inform the stakeholder that you are unable to send out ad hoc reports as it is not included in the project Communications Management Plan.

D. Complain to the sponsor about this unreasonable request from the stakeholder.

A

Answer: A

Explanation: Accommodating to planned and ad hoc information requests is part of the Manage Communications process.

135
Q

You are the project manager of a very important software development project in your organization. As you are closely monitoring and managing your project, you are happy that the project is progressing as per your plan. You reviewed the status of all the deliverables with your team members prior to having a project status update meeting with the stakeholders. Your team has developed a prototype, or a working model of the proposed end product, and it will be presented to the stakeholders for interaction and feedback. This will be an iterative process, and the prototype may be modified numerous times to incorporate the feedback until the requirements have been finalized for the product. Which one of the following will you do in your status meeting?

A. Do not mention anything about the prototype.

B. Demo the prototype to the stakeholders and obtain their formal approval.

C. Report on the progress of the prototype and point out that it’s a completed task.

D. Review the technical documentation of the prototype and obtain the formal approval.

A

Answer: C

Explanation: Usually the project manager reports on the progress of the project in a status meeting rather than demoing any prototype or reviewing any technical documentation.

136
Q

While planning communication for the network infrastructure project to which you have been assigned as project manager, you know you have to pay particular attention to your body’s mannerisms, facial expressions, and the tone and pitch of your voice to communicate effectively. All of the following are FALSE about communication EXCEPT:

A. Acknowledge means the receiver has received and agreed with the message.

B. Encode means to translate ideas or thoughts so that others can understand them.

C. Noise has nothing to do with sending and receiving messages.

D. Verbal communication is more important than nonverbal communication.

A

Answer: B

Explanation: Acknowledge means the receiver has received the message, but it does not mean that the receiver necessarily agrees with the message. Noise or communication blockers play a vital role in effective communication. 55 percent of all communication is nonverbal, and verbal communication is not more important than nonverbal communication. Encoding is translating ideas and thoughts.

137
Q

While working on your communications plan, you have considered several communication technologies to transfer information among project stakeholders. Communication technology will take into account the following factors that can affect the project EXCEPT which one?

A. Urgency of the need for information: Are regularly issued written reports enough for the project, or is frequently updated information needed at a moment’s notice?

B. Expected project staffing: Are the proposed communication systems compatible with the experience and expertise of the project participants, or is extensive training and learning required?

C. Duration of the project: Is the available technology likely to change before the project is over?

D. Reason for the distribution of information: What are the reasons for distributing information?

A

Answer D:

Explanation: Communication technology will take into account urgency of the need for information, expected project staffing, and duration of the project, but not reason for the distribution of information.

138
Q

A project manager overseeing a construction project has several stakeholders involved in the project. During project implementation, the project manager is required to submit several reports that will communicate information about the project. The report that describes where the project now stands regarding performance measurement baselines in cost, schedule, scope, and quality is called:

A. Status report

B. Quality report

C. Progress report

D. Forecast report

A

Answer: A

Explanation: Status reports address the current condition of a project, including risks and issues. Progress reports refer to work that has been completed during a reporting period, and forecasts refer to future scheduled work. The quality report is a made-up term.

139
Q

You are managing a software development project and have worked on a Stakeholder Register and a Communications Management Plan. Now you are about to execute your Communications Management Plan. Which one of the following is TRUE regarding Manage Communications?

A. Manage Communications will end when the product has been accepted.

B. Communication methods such as individual and group meetings, video and audio conferences, computer chats, and other remote communication methods are used to manage communications.

C. Manage Communications is a monitoring & controlling process.

D. Manage Communications only carries out predetermined communication and does not respond to unplanned requests from stakeholders.

A

Answer: B

Explanation: Some stakeholders will need information distributed even after the product has been accepted as they want to get information about the closure of the project and the contract. The Manage Communications is an executing process. Manage Communications carries out not only predetermined communication but also handles responses to unplanned requests from stakeholders. The listed communication methods are used in Manage Communications; thus, letter ‘B’ is the correct answer.

140
Q

The project manager who has been managing a large, multi-year network infrastructure project recently left the company, and you were assigned as a project manager to continue with the project. There are more than five different vendors, fifteen team members, and several key stakeholders involved in this very important project. While trying to identify stakeholder communication requirements, format, method, time frame, and frequency for the distribution of required information, which of the following will you be referring to?

A. Communications Management Plan

B. The information Distribution Plan

C. Project Management Plan

D. Stakeholder Management Strategy

A

Answer: A

Explanation: Even though the Communications Management Plan is a part of the Project Management Plan, the best option here will be the Communications Management Plan, where the purpose for communication, communication requirements, method, time frame and frequency for distribution, person responsible for communication, methods for updating the communications management plan, and other communication related items can be found.

141
Q

A Project Management Information System (PMIS) is used as a tool & technique in many of the forty-nine processes. Which statement describes a PMIS BEST?

A. A PMI certification for project management focused on information systems.

B. A necessary log for timekeeping.

C. A repository for project information used for future reference.

D. An automated system to support the project by optimizing the schedule and helping collect and distribute information.

A

Answer: D

Explanation: PMIS is an automated tool used to gather, integrate, and disseminate project information.

142
Q

A stakeholder is complaining that she has no clue what is going with the project as she is not receiving any kind of communications from you. You are sure that you identified this specific stakeholder and analyzed her communication need and preferred communication method in the initiation phase of the project. You went through a specific document and realized that the stakeholder asked for a monthly status report that should be posted in your partners’ portal. Where did you find this information?

A. Communication Management Plan

B. Resource Management Plan

C. Stakeholder Engagement Assessment Matrix

D. Responsibility Assignment Matrix (RAM)

A

Answer: A

Explanation: A Communication Management Plan includes purpose of communication, information needs of each stakeholder or stakeholder group, stakeholder communication requirements, and format, method, time frame, and frequency of the distribution of required information.

143
Q

Project risk is an uncertain event or condition in the future; if it occurs, it will have a positive or negative impact on one or more project objectives including scope, schedule, cost, and quality. Project risk is typically characterized by three elements:

A. Risk event, probability, and amount at stake

B. Severity, duration, and cost of impact

C. Source, probability, and frequency of risk

D. Timing, frequency, and cost of risk

A

Answer: A

Explanation: A risk event is the actual occurrence of the risk, such as an equipment failure. Risk probability is the likelihood that a risk event may occur. The amount at stake refers to the impact or consequence of the risk on one or more project objectives including scope, schedule, cost, and quality.

144
Q

Designing redundancy in the system, taking early action, adopting less complex processes, conducting more tests, and developing prototypes are all examples of:

A. Risk avoidance

B. Risk transfer

C. Risk mitigation

D. Risk acceptance

A

Answer: C

Explanation: These are all examples of risk mitigation. Risk mitigation simply means a reduction in the probability and/or impact of an adverse risk event to an acceptable threshold. Transferring is shifting the negative impact of a threat, along with the ownership of the response, to a third party to make it their responsibility. An example of this would be insurance bonds, warranties, guarantees, and contracts. Avoidance is eliminating the threat by eliminating the cause or changing the project management plan. An example of this would be using a slower but reliable technology instead of a cutting-edge one to avoid associated risk. Since it is seldom possible to eliminate all risks and also since the cost or impact of avoid, transfer, and mitigate is too high, acceptance can be the preferred strategy. It indicates that the project team is simply accepting the risk and will continue with the project.

145
Q

You are the project manager assigned to a critical project that requires you to handle project risk intentionally and methodically, so you have assembled only the project team. The team has identified thirty-two potential project risks, determined what would trigger the risks, and have rated and ranked each risk using a risk rating matrix. You have also reviewed and verified all documented assumptions from the project team and verified the sources of data used in the process of identifying and rating the risks. You are continuing to move through the risk management process. Which one of the following important steps have you missed?

A. Engage other stakeholders.

B. Conduct a Monte Carlo simulation.

C. Determine which risks are transferable.

D. Determine the overall riskiness of the project

A

Answer: A

Explanation: Stakeholders may be great contributors for identifying potential risks in the project. You should have involved other stakeholders instead of only working with the team members on risk management activities.

146
Q

You are managing the construction of a disaster center for a financial institute. After the preliminary survey, you found out that the location that was selected for the disaster center was highly prone to earthquakes. You raised your concern to management, but due to a specific strategic reason you were told that changing the location would not be an option. In order to deal with this situation, you have selected a specific architectural design that is technologically advanced and earthquake resistant. This is an example of which of the following?

A. Accept risk

B. Transfer risk

C. Avoid risk

D. Mitigate risk

A

Answer: D

Explanation: Since you are taking action to lower the probability and impact of the risk, you are mitigating the risk.

147
Q

During the initial stage of project planning, you made a guess that all the construction materials such as sand, cement, concrete, rods, and other items would be available within a reasonable price during building construction. While identifying the risk in your project, you found out that the price for cement significantly increased due to heavy demand and less supply. You decided to add this as a new risk in your project. This is an example of:

A. Assumptions analysis

B. Diagramming techniques

C. SWOT analysis

D. Expert judgment

A

Answer: A

Explanation: This is an example of assumptions analysis. This is an analysis of the validity of assumptions, hypotheses, and scenarios developed in project initiation to identify risks from inaccuracies, incompleteness, and inconsistencies of assumptions. The assumptions that turn out to be invalid should be evaluated, qualitatively and quantitatively analyzed, and planned for just like other risks.

148
Q

Steve, an IT project manager, is overseeing a project to develop a new wireless media streaming device. He is using various techniques such as Root Cause Analysis, SWOT Analysis, and Assumption and Constraint Analysis to determine what could cause potential risks to his project. Which one of the following Risk Management Processes is he in now?

A. Plan Risk Management

B. Identify Risks

C. Perform Qualitative Risk Analysis

D. Monitor Risks

A

Answer: B

Explanation: The Data Analysis Technique, such as Root Cause Analysis, Assumption and Constraint Analysis, and SWOT analysis, are used as tools & techniques in the Identify Risks process.

149
Q

You have been working on the Plan Risk Management process of establishing the basis to approach, plan, and execute risk management activities and have developed a risk management plan. Which one of the following will NOT be included in your risk management plan?

A. Methodology: Defines approaches, tools, and data sources for risk management.

B. Roles and Responsibilities: Defines the roles and responsibilities and sometimes includes non-team members who may have certain roles in risk management.

C. Identified Risks: A list of identified risks in the project.

D. Risk Categories: A group of potential causes for risk that can be grouped into categories, such as technical, political, external, project, environmental, and others.

A

Answer: C

Explanation: A list of identified risks will be included in the risk register, not in your Risk Management Plan.

150
Q

Which one of the following will NOT be considered a valid way of reducing risks in your project?

A. Plan to mitigate the risk.

B. Develop a workaround.

C. Select a specific contract type to distribute risk between the buyer and the seller.

D. Purchase insurance against the risk.

A

Answer: B

Explanation: Workarounds, unplanned responses developed to deal with the occurrence of unanticipated risk events, are not valid ways of reducing risks in a project.

151
Q

You are in the Plan Risk Responses process of developing options and actions to reduce threats and enhance opportunities to your project objectives. The tools & techniques of the Plan Risk Responses process include:

A. Audits

B. Escalate, avoid, transfer, mitigate, and accept

C. Data Analysis

D. Meetings

A

Answer: A

Explanation: Audits and Data Analysis Techniques such as Technical Performance Analysis and Reserve Analysis are tools & techniques used in the Monitor Risks process. Strategies for negative risks or threats such as escalate, avoid, transfer, mitigate, and avoid are used as tools & techniques in the Plan Risk Responses process.

152
Q

You planned a trip to a destination four hundred miles away from home. You found out that there is a long stretch of construction on one of the major highways that you are planning to use. You decide to use another highway for that stretch of driving so that you do not have to wait too long in traffic. This is an example of:

A. Avoiding risk

B. Creating contingency reserves

C. Creating a workaround

D. Creating a fallback plan

A

Answer: A

Explanation: Risk avoidance is the elimination of the threat by eliminating the cause or changing the project management plan. This is an example of avoidance since you are changing your travel plan to eliminate the threat of traffic delay.

153
Q

You will be overseeing a project to develop a smartphone application. While analyzing your project, you identify that there is a 55 percent probability of making $120,000 a 45 percent probability of losing $55,000. What does $41,250 represent in this case?

A. Net Present Value (NPV)

B. Return on Investment (ROI)

C. Economic Value Added (EVA)

D. Expected Monetary Value (EMV)

A

Answer: D

Explanation: The expected monetary value is calculated by multiplying the probability with the impact. The EMV for the opportunity is 55 percent * $120,000 = $66,000 and for the threat is 45 percent * $55,000 = $24,750. The total EMV in this case is $66,000 – $24,750 = $41,250 profit.

154
Q

Your team has identified several risks in the project as well as their probability, impact, and priorities. The team is now exploring the response strategies to risks if they occur. The team identified that a couple of the programmers on the team might leave, which would significantly impact the project, but they decided to deal with it if and when it occurs. Which one of the following statements is true?

A. This is passive acceptance.

B. This is active acceptance.

C. This is risk avoidance.

D. This is risk mitigation.

A

Answer: A

Explanation: Since it is seldom possible to eliminate all risks and also since the cost or impact of avoid, transfer, and mitigate is too high, acceptance can be the preferred strategy. It indicates that the project team is simply accepting the risk and will continue with the project. The team has decided to go for passive acceptance, which requires no action.

155
Q

You are overseeing a project to implement a smartphone application and are currently in the Identify Risks process of identifying and documenting the project risks. While exploring the elements of the enterprise environmental factors as inputs to the Identify Risks process, your team will be exploring all of the following elements EXCEPT:

A. Organizational risk attitudes

B. Commercial databases

C. Assumption and Constraint Analysis

D. Published checklist

A

Answer: C

Explanation: Assumption and Constraint Analysis is a Data Analysis Technique that is not used as an input but as a tool & technique in the Identify Risks process.

156
Q

You have been working on the Plan Risk Management process of establishing the basis to approach, plan, and execute risk management activities and have developed a risk management plan. Each of the following statements is true regarding the Plan Risk Management process EXCEPT:

A. The risk management plan, which is a part of the overall project management plan, is an input to all other risk processes.

B. The risk management plan includes a description of the responses to risks and triggers.

C. The risk management plan is an output of the Plan Risk Management process.

D. The risk management plan includes methodology, roles and responsibilities, budget, risk categories, definition of risk probability and impact, revised stakeholder tolerances, reporting formats, and other items.

A

Answer: B

Explanation: The Plan Risk Management process establishes the basis to approach, plan, and execute risk management activities throughout the life of the project and develops the risk management plan. The risk management plan does not include a description of the responses to risks or triggers. Responses to risks are documented in the risk register as part of the Plan Risk Responses process.

157
Q

Your company, ITPro Consultancy, has assigned you as the project manager to upgrade the call center in your organization. The number of calls the customer support agents have to answer each month has increased drastically in the last five months, and the phone system is approaching the maximum load limit. You worked with the team and identified several risk items in your project in the Identify Risk process. In which of the following process will you be identifying more risk items?

A. Plan Risk Responses

B. Implement Risk Responses

C. Monitor Risks

D. Perform Qualitative Risk Analysis

A

Answer: C

Explanation: Risk items will be identified throughout the project life cycle. The team will identify most of the project risk items in the Identify Risk process and newly emerging risks will be identified in the Monitor Risk process.

158
Q

After reviewing your project schedule and resource calendars, you realize that your resources are 100 percent occupied and will have no time to work on a new component. So, you decide to outsource the component and start negotiating with a couple of potential vendors. While outsourcing, which of the following should you be MOST concerned about?

A. The technical background of the vendor

B. The financial capability of the vendor

C. The relevant experience of the vendor

D. Proprietary data of your organization

A

Answer: D

Explanation: The technical background, financial capability, and relevant experience of the vendor are all very important factors while outsourcing, but we should be very concerned about the sensitive and confidential proprietary data of our organization that we may need to turn over to the vendor.

159
Q

Sabrina, a project manager for ITPro Consultancy, LLC, is overseeing the design and development of an indoor room temperature and humidity controlling device. While working on the procurement plan, she compared the cost of an off-the-shelf product to the cost of her programmers’ design to develop the custom device. Sabrina is engaged in which of the following?

A. Using expert judgment

B. Coming up with source selection criteria

C. Performing a Make-or-buy analysis

D. Working on the procurement statement of work

A

Answer: C

Explanation: Make-or-buy analysis is concerned with determining whether a product can be cost effectively produced in- house or whether it should be purchased, leased, or rented. While performing this analysis, we must consider indirect as well as direct costs, availability in addition to related risk, schedule, etc. Source selection criteria is developed and used to provide sellers with an understanding of the buyer’s need and also to help them in deciding whether to bid or make a proposal on the project. Later on, it also helps to evaluate sellers by rating or scoring them. The procurement Statement of Work (SOW) describes the subject item in sufficient detail to allow prospective sellers to determine offerings (bids, proposals, etc.). It documents details of the work to be performed by the seller under a contract.

160
Q

While working on a data mining project, you realize that you need a data validation tool that was never thought of earlier. After reviewing your project schedule and resource calendars, you realize that your resources are 100 percent occupied and will have no time to work on this new component. So, you decide to outsource the component and start negotiating with a couple of potential vendors. You quickly realize that you do not have a clear definition of the scope, but the vendor agrees with you that the project will be relatively small and you have an urgent need. Which contract type is MOST appropriate in this kind of situation?

A. Cost Plus Fixed Fee (CPFF)

B. Cost Plus Award Fee (CPAF)

C. Fixed Price Economic Price Adjustment (FPEPA)

D. Time and Materials (T & M)

A

Answer: D

Explanation: This time-based fee plus cost of materials contract is used for smaller amounts and shorter times and requires little or no defined scope of work. In a T & M contract, the seller pays a rate for each of the people working on the team plus their material costs. The “time” part means that the buyer pays a fixed rate for labor, usually a certain number of dollars per hour. And the “materials” part means that the buyer also pays for materials, equipment, office space, administrative overhead costs, and anything else that has to be paid for.

161
Q

You are in the Control Procurements process and are ensuring that the seller’s performance meets contractual requirements by monitoring contract performance and making appropriate changes and corrections. Which of the following will you most likely NOT use as an input in this process?

A. Procurement documents

B. Work performance information

C. Contract

D. Seller proposals

A

Answer: D

Explanation: Seller proposals are inputs to the Conduct Procurements process for obtaining seller responses, selecting a seller, and awarding the procurement, usually in the form of a contract. This is an official response to the buyer’s procurement document, including the details the buyer is looking for, how the work will be performed, and pricing. Procurement documents, work performance information, and contracts all are used as inputs for administering procurements in the monitoring & controlling process group.

162
Q

You are the project manager of a data center construction project. Your company made it mandatory to solicit quotes from three separate vendors before submitting the purchase request to the finance department for buying switches, routers, firewalls, PCs, servers, etc., for the data center. What type of input is this policy to the procurement process?

A. Make-or-buy decision

B. Procurement document

C. Source selection criteria

D. Organizational process assets

A

Answer: D

Explanation: Any type of corporate policy or formal and official procurement procedure is an organizational process asset.

163
Q

You are managing a software development project to automate an accounting process. In this Cost Plus Incentive Fee Contract, you have negotiated the following: Target cost: $120,000 and target fee: $8,000 Max fee: $12,000 and min fee: $4,000 Sharing ratio: 80/20 (buyer/seller) The actual cost was $145,000. What is the total price the buyer will pay?

A. $148,000

B. $149,000

C. $144,000

D. $153,000

A

Answer: B

Explanation: There is a cost overrun of $145,000 - $120,000 = $ 25,000. Seller’s fee will be decreased by $25,000 * 20% = $5,000. Thus, seller final fee will be $8,000 - $5,000 = $3,000. The minimum fee was set to $4,000. So, in this case, the final fee will $4,000, not $3,000. Buyer’s total price will be $145,000 + $4,000 = $149,000.

164
Q

Which of the following is the process of documenting project purchasing decisions, specifying the approach, defining selection criteria to identify potential sellers, and putting together a Procurement Management Plan?

A. Conduct Procurements process

B. Plan Procurement Management process

C. Close Procurements process

D. Control Procurements process

A

Answer: B

Explanation: Plan Procurement Management is the process of documenting project purchasing decisions, specifying the approach, defining selection criteria to identify potential sellers, and putting together a Procurement Management Plan.

165
Q

Steve is a program manager overseeing an ERP implementation project where the team has already completed the finance, sales, and admin modules out of seven total modules. Steve was informed that the client has terminated the project as they found a cheaper and faster off-the-shelf solution for their need and no longer want the project to continue. Which of the following is TRUE?

A. The team must keep working on the project to give senior management time to discuss with the client.

B. Steve must stop all work and release the team immediately.

C. Steve must work with the team to document the lessons learned.

D. Steve must close the contract.

A

Answer: C

Explanation: A project can be terminated any time for a certain cause or simply for convenience of the buyer. If a project is terminated before the work is completed, you still need to document the lessons learned and add them to the organizational process assets. There are always important lessons that you can learn when a project goes seriously wrong even when you did nothing to contribute to the disaster.

166
Q

You are in the Control Procurements process and want to document the procurement lessons learned from everyone involved in your project to help improve how your organization will handle procurements in the future. Lessons learned Register is created as a result of the procurement audit and include all of the following EXCEPT:

A. Things that went right or wrong

B. Successes and failures that should be recognized

C. Using the payment system to process considerations as per the terms of the contract

D. Process improvement recommendations and what will be done differently next time

A

Answer: C

Explanation: Unless there was a problem processing or making payment, the payment system will not be a part of the procurement audit. The other remaining choices will be included in the procurement audit and captured in the Lessons Learned Register.

167
Q

In which procurement management process will you ensure that the seller’s performance meets contractual requirements, that both the buyer and seller meet their contractual obligations, and that the legal rights of both the buyer and seller are protected?

A. Procurement performance reviews

B. Inspections and audits

C. Performance reporting

D. Control Procurements

A

Answer: D

Explanation: Control Procurements is the process of ensuring the seller’s performance meets contractual requirements, ensuring that both seller and buyer meet their contractual obligations, and ensuring that legal rights of both seller and buyer are protected. The focus here is to manage the relationship between buyer and seller, monitor contract performance, and make appropriate changes and corrections. Procurement performance reviews, inspections and audits, and performance reporting are tools & techniques used in the Control Procurements process.

168
Q

You are in charge of the bidding process for a government solar power plant project. You are trying to make sure that no seller receives preferential treatment and that all sellers have a clear, common understanding of the procurement (technical requirements, contractual requirements, etc.). Your key objective is to provide all potential contractors with the information they need to determine if they would like to continue with the contracting process. Which one of the following will assist you with your goal?

A. Source selection criteria

B. Bidder conference

C. Independent estimate

D. Procurement negotiation

A

Answer: B

Explanation: A bidder conference is intended to assure that no seller receives preferential treatment and that all sellers have a clear, common understanding of the procurement (technical requirements, contractual requirements, etc.). The goal of the bidder conference is to make sure that all questions are submitted in writing and issued to sellers as an addendum to the procurement document so that all sellers respond to the same scope of work, there is no collusion among sellers and/or buying agents, and sellers do not save questions for later private meetings in order to gain competitive advantage. Independent estimates are often prepared by the procuring organization to judge whether the statement of work was adequate in its description or that the seller fully understood or responded fully to the statement of work; these estimates also help the organization check the reasonableness of the seller’s response or cost proposal and proposed pricing. The goal of procurement negotiation is to achieve clarification and agreement on the structure and requirements of the contract prior to signing.

169
Q

Lars is a project manager overseeing an online age verification application for one of the very important clients for his organization. Three months in the project, Lars got a call from the client who informed him that they would end the contract due to a change in business direction. The client also discussed the compensation that the seller’s organization is offering to Lars’s organization for the work completed so far. This is an example of which one of the following?

A. Letter of intent

B. Breach of contract

C. Material breach

D. Termination for convenience

A

Answer: D

Explanation: Termination for convenience is a contract clause that permits the buyer to terminate a contract at any time for a cause or convenience. Usually, there will be specific conditions associated with the execution of this clause. A letter of intent is a letter expressing the intention of the buyer to hire the seller. It is not a contract; thus, it does not have any legal binding. Most of the time, the buyer gives a letter of intent to the seller in the following circumstances: – Completion of contract negotiation and finalization will take significant amount of time, but the project needs to be initiated as soon as possible. – The seller has no option but to hire people and order equipment in order to meet contractual requirements before the contract is signed. A breach/default is not meeting contractual obligation by the seller or the buyer. A material breach is so severe that it is not possible to continue work under the contract.

170
Q

During the Plan Procurement Management process, your team developed the procurement document to solicit proposals from prospective sellers and to easily compare their responses. All of the following statements are true about the procurement document EXCEPT:

A. It may include the procurement statement of work and evaluation criteria.

B. It should not be too rigorous to allow any flexibility for the sellers to be innovative.

C. It contains clear, complete, and concise descriptions of performance, design, functionality, reporting, format, and support requirements.

D. It may contain a Request For Proposal (RFP), a Request For Bid (RFB), and a Request For Quotation (RFQ).

A

Answer: C

Explanation: Usually a Statement of Work (SOW) document contains a clear, complete, and concise description of performance, design, functional, reporting, format and support requirements, not a procurement document. Well- designed procurement documents help in easier comparison of seller responses, more complete proposals, more accurate pricing, and decrease in the amount of changes in the project. Procurement documents may contain all the work that is to be completed, as well as terms, conditions, and evaluation criteria. You want the seller to be as innovative as possible when they come up with the design and methods for completing your project. It may contain request for proposal (RFP), invitation for bid (IFB, or request for bid, RFB), and request for quotation (RFQ).

171
Q

Sandi is working as a project manager in a drug manufacturing company, Ultra Medicine, LLC. Ultra-Medicine is very excited to introduce a new drug in the market that will stop the human aging process and drastically improve the quality of health. Sandi initiated a conversation with one of the foreign vendors about outsourcing the production of this new drug. The vendor is also very enthusiastic about the potential of the new drug and has requested a copy of the Statement of Work (SOW) so that they can start learning about it. Which one of the following is FALSE about the SOW?

A. The SOW should contain the details of the new drug.

B. The SOW should have the details as required but not so much as to give out all the sensitive information and trade secrets of Ultra Medicine.

C. The SOW should have enough detail for the vendor to figure out if they are capable and qualified to manufacture the drug.

D. Ultra-Medicine must write the SOW with the necessary detail.

A

Answer: D

Explanation: It is not mandatory for the buyer to come up with the SOW all the time. The seller can come up with the SOW through requirements collection tools & techniques. Also, seller can update the buyer’s SOW and get it reviewed and approved.

172
Q

While managing a nanotechnology project to build an elevator/tunnel from the ground to the space station, you need to procure a new material called carbon nanotube, which is extremely strong and resistant to heavy air pressure. Due to patent constraints, there is only one supplier in a different state who can provide you with this material. You checked the supplier’s website and realized that the price listed for the material on the site would be within your approved limit. What should you do in this situation?

A. Consider purchasing the material from the source even though it is a sole source.

B. Keep exploring the option to use some other material to build the tunnel.

C. Notify management that there is only one source; thus, you cannot purchase the material from the single source.

D. Ask the procurement department to take care of this situation.

A

Answer: A

Explanation: In noncompetitive forms of procurement, usually a seller is selected from a list of qualified sellers interested in and capable of doing the job. Even though competition can result in the selection of a better seller and decreased price, there is no reason for going through the entire procurement process unless law requires it. Two types of noncompetitive forms of procurement are described below: Single source (preferred seller): In this case the buyer has worked with the seller before, and due to good experience and other convenience with the seller, the buyer does not want to look for another seller. Sole source (only seller): In this case the seller may be the only one in the market or may have a patent, thus limiting the option of selecting other sellers.

173
Q

As a buyer’s project manager, you always try to bring the seller’s objectives in line with those of yours. You also understand that for the sellers, the focus is on the profit. Your project has an emergency and needs contracted work to be completed as soon as possible. Which one of the following would be most helpful to add to the contract under this crucial situation?

A. A Time is of the Essence clause

B. A robust procurement statement of work

C. A retainage clause

D. Incentives

A

Answer: D

Explanation: Under normal circumstances, if you follow the proper project management processes, you should have good definition of scope. In this situation, you should have a quality procurement statement of work. You need good scope definition as well as incentives as you need the seller to share your need for speed. A quality procurement document alone will not ensure speed. Incentives will bring the seller’s objectives in line with the buyer’s and would be most useful in this case. The “Time is of the Essence” clause states that any delay will be considered as a material breach as delivery dates are extremely important. The “Retainage” clause states that in order to ensure full completion, an amount of money, usually 5 to 10 percent, is withheld from each payment and paid in full once the final work is completed. These two clauses may help but would not be as effective as incentives.

174
Q

Lars is a project manager overseeing an online age verification application for one of the very important clients for his organization. Three months into the project, Lars got a call from the client who informed him that they would not be able to make the partial payment for the design work due to a financial crisis. The client mentioned that they were very unsatisfied with the quality of the requirement document that the seller submitted. The client’s organization also thinks that the contract is no longer valid and needs to be terminated. Lars realizes that once signed, a contract is legally binding unless:

A. The contract is in violation of applicable laws.

B. The buyer’s legal counsel considers the contract to be null and void.

C. The seller fails to perform.

D. The buyer fails to pay for the work.

A

Answer: A

Explanation: It is important to understand that once signed, a contract is legally binding unless it is in violation of any applicable law. The failure to perform or make payment usually does not alter the fact that the contract is binding. The contract will remain in binding if only one party considers that the contract is no longer valid. However, if both parties negotiate and agree to terminate the contract, the contract should move into the Control Procurements process.

175
Q

As a buyer’s project manager, what is the BEST way for you to ensure that the seller is not making extra profits in a Cost Plus Fixed Fee (CPFF) contract?

A. You only pay the fee when the project is completed.

B. You do not authorize any unexpected cost overrun.

C. You audit all invoices and make sure that you are not charged for items not chargeable to the project.

D. You ensure that the sellers are not cutting scope.

A

Answer: C

Explanation: In a Cost Plus Fixed Fee (CPFF) contract, the fee is usually paid on a continuous basis during the life of the project. It is unreasonable and unrealistic not to authorize any unexpected cost overrun. Cutting scope would not be a way for sellers to make additional profits as it decreases the profit for this type of contract. The best way is to audit all invoices and make sure that you are not charged for items not chargeable to the project.

176
Q

While working on a data mining project, you realize that negotiation is essential to develop a good understanding and relationship with the seller as well as to obtain a fair and reasonable price for the product, service, and result. During which procurement process will procurement negotiation occur the MOST?

A. Conduct Procurements

B. Plan Procurement Management

C. Control Procurements

D. Close Procurements

A

Answer: A

Explanation: During Conduct Procurements, negotiation occurs to finalize the terms and conditions of the contract. In this process, a contract or agreement is created that is approved by both parties through much negotiation. In order to settle any pending disputes or concerns, negotiation will also be used in the Control Procurements process. During Conduct Procurements, negotiation occurs to finalize the terms and conditions of the contract. In this process, a contract or agreement is created that is approved by both parties through much negotiation. In order to settle any pending disputes or concerns, negotiation will also be used in the Control Procurements process.

177
Q
  1. Steve is trying to figure out whether a stakeholder is at an “unaware” state or not so that he can identify required actions and communication needed to minimize the gap between the desired and actual level of engagement of this stakeholder. Which of the following is a tool to assess the current and desired state of engagement of a stakeholder on the project?

A. Stakeholder Engagement Assessment Matrix

B. Issue Log

C. Stakeholder Register

D. Stakeholder Engagement Plan

A

Answer: A

Explanation: A Stakeholder Engagement Assessment Matrix is a tool to assess the engagement levels of the stakeholders on a project. The matrix can be utilized to compare the actual engagement levels to the planned levels. Any discrepancies can be examined, and communication to adjust the engagement levels can then be implemented.

178
Q

You are reviewing the Stakeholder Engagement Plan and Communications Management Plan and focusing on meeting and exceeding the stakeholders’ expectations by continuously communicating with them, elucidating and resolving their issues, addressing their apprehensions, and improving project performance by implementing their change requests. Which stakeholder management process are you in at this time?

A. Monitor Stakeholder Engagement

B. Manage Stakeholder Engagement

C. Plan Stakeholder Engagement

D. Identify Stakeholders

A

Answer: B

Explanation: All these activities typically belong to the Manage Stakeholder Engagement process.

179
Q

You are overseeing a web-based application project to automate the business process of one of your clients. You are working on identifying all the internal and external stakeholders who have interest in your project and can positively or negatively impact your project. While identifying the stakeholders, you realize that stakeholder identification is:

A. To be focused only on stakeholders who will contribute positively to your project

B. To be completed in the initial stage of the project life cycle

C. A responsibility of the project sponsor

D. To be carried out throughout the project life cycle

A

Answer: D

Explanation: Stakeholder identification will persist throughout the project life cycle. As the project proceeds through each phase, additional stakeholders may become involved while others will be released from the project. Some stakeholders will be identified during the initiating phase in the project charter, while other stakeholders may only be interested in the end product and will be involved only at the closing phase.

180
Q

Stakeholder management necessitates all of the following EXCEPT:

A. Giving stakeholder extras if needed to meet and exceed their expectations

B. Identifying both internal and external stakeholders

C. Assessing stakeholders’ skills, knowledge and expertise

D. Identifying stakeholders’ influence-controlling strategies

A

Answer: A

Explanation: A: Giving stakeholder extras or gold plating should always be avoided. Gold plating is not the preferred way of meeting and exceeding stakeholder expectations.

181
Q

You are overseeing a project to build a plant for a semiconductor company. You have completed your internal and external stakeholder identification and have come up with a list of thirteen stakeholders for the project. You expect that most of the stakeholders will play an affirmative role in the project and will contribute significantly. While working on your Project Management Plan, you were notified by one of the team members that a stakeholder from the automation department is missing in the published stakeholder list. What will be your best course of action in this situation?

A. Add the stakeholder in your stakeholder list immediately and update everyone.

B. It is too late to add any more stakeholders and consider their requirements, so ignore the stakeholder.

C. Validate the information received from the team member.

D. Set up a meeting with the stakeholder and the team member.

A

Answer: C

Explanation: Before you take any other step, you should validate the information received from the team member.

182
Q

You have been managing a government railway project and dealing with several stakeholders. You have spent a considerable amount of time identifying all your internal and external stakeholders and their interest, influence level in your project, and their key expectations. As part of your analysis of the level of engagement of stakeholders in your project, you have classified them as: Unaware: Stakeholders are ignorant about the project and apparent impacts. Neutral: Stakeholders are aware of the project and apparent impacts but neither accommodating nor resistant. Resistant: Stakeholders are aware of the project and apparent impacts and opposed to changes. Supportive: Stakeholders are aware of the project and apparent impacts and accommodating to changes. Leading: Stakeholders are aware of the project and apparent impacts and enthusiastically involved in making certain the project is a success. What sort of techniques are you using in this case?

A. Information gathering techniques

B. Stakeholder Analysis

C. Delphi technique

D. Data Representation – Stakeholder Engagement Assessment Matrix

A

Answer: D

Explanation: A Data Representation technique such as Stakeholder Engagement Assessment Matrix is used to classify stakeholders as per their level of engagement in the project during the Plan Stakeholder Engagement process.

183
Q

You identified all people who would be impacted by the project and documented relevant information regarding their interests, expectations, involvement, and influence on the project success in a stakeholder register. The stakeholder register will NOT be used as an input to which of the following processes?

A. Collect Requirements and Identify Risks

B. Plan Risk Management and Plan Resource Management

C. Plan Quality Management and Plan Communications Management

D. Develop Project Charter and Perform Integrated Change Control

A

Answer: D

Explanation: The Stakeholder Register will be used as an input to the Collect Requirements, Plan Resource Management, Plan Risk Management, Identify Risks, Plan Quality Management, and Plan Communications Management processes. It is not an input to the Develop Project Charter and Perform Integrated Change Control processes. The Develop Project Charter process is executed prior to the Identify Stakeholder process where the Stakeholder Register will be developed.

184
Q

Your company, ITPro Consultancy, has assigned you as the project manager to upgrade the call center in your organization. The number of calls the customer support agents have to answer each month has increased drastically in the last five months, and the phone system is approaching the maximum load limit. While identifying the stakeholders, you realize that there are more than 180 potential stakeholders, 19 team members, and 6 different vendors that you will need to deal with. What will be your BEST course of action?

A. Have an urgent meeting with the sponsor and request him not to include some of the stakeholders.

B. Identify an effective approach to determine the needs of all stakeholders.

C. Identify the key stakeholders and concentrate only on their needs.

D. Report to the management that the project is too large to manage by one person.

A

Answer: B

Explanation: In order to minimize numerous changes later in the project, you need to identify all stakeholders and their needs as early as possible. Stakeholder analysis will be a more complicated task if there are numerous stakeholders and an effective way to determine their needs must be identified.

185
Q

Project Stakeholder Management consists of processes to identify the internal and external stakeholders, determine their expectations and influence over the project, develop strategies to manage them, and effectively engage them in project execution and decision. Which one of the following is the key objective of the Stakeholder Management?

A. Keeping the stakeholders happy and satisfied

B. Maintaining a robust communication with all stakeholders

C. Keeping a positive relationship with all stakeholders

D. Establishing a good coordination among stakeholders

A

Answer: A

Explanation: Keeping stakeholders happy and satisfied is the main objective of the stakeholder management. Maintaining a robust communication, keeping a positive relationship, and establishing a good coordination will collectively contribute to achieve stakeholder satisfaction.

186
Q

You are in the process of evaluating and monitoring overall stakeholder relationships and ensuring stakeholders’ appropriate engagement in the project by adjusting plans and strategies as required. The Work Performance Data that is an input to this Monitor Stakeholder Engagement process usually comes from:

A. Validate Scope

B. Perform Integrated Change Control

C. Monitor and Control Project Work

D. Direct and Manage Project Work

A

Answer: D

Explanation: All Work Performance Data comes from executing process group. In this case, Work Performance Data comes as an output of the Direct and Manage Project Work, an executing process.

187
Q

A stakeholder register includes all of the following items EXCEPT:

A. Stakeholder classification: Internal/external, neutral/resistor/supporter, and others.

B. Identification information: Name, title, location, organization, role in the project, position, and contact information.

C. Assessment information: Key requirements and expectations, potential impact, importance, and influence on the project.

D. Strategies: The strategies to interact with stakeholders, increase their positive influence, and control their negative influence.

A

Answer: D

Explanation: The strategies to interact with the stakeholders are included in the Stakeholder Management Plan, not in the Stakeholder Register.

188
Q

One of your primary goals in your project is to have more interaction and build a positive relationship with your stakeholders. You are particularly interested about 4 stakeholders and trying to figure out which one you should make it a priority to get to know. The first one is an employee from the Sales Department who thinks that the product of the project will drastically improve productivity. The second one is Chief Information Officer (CIO) who has been very helpful to all your projects. The third one is a programmer from IT department who is the Subject Matter Expert (SME) but has no interest in introducing the product in his department. And the last one is the Engineering Department Head who will be using your product but known to be very resistant to changes. You should be giving the highest priority to:

A. The employee from the Sales Department.

B. The Chief Information Officer (CIO)

C. The programmer from IT department

D. The Engineering Department Head

A

Answer: D

Explanation: As the Engineering Department Head this person may have significant influence on other stakeholders in his department. You need to reassure this key stakeholder about your product since he is not open to changes or he will use his influence to disrupt your project.

189
Q

One of your best friends in charge of maintaining customers’ finances and investments is working in the same financial institution with you. She shared a secret with you and asked you not to divulge the secret to anyone. She told you that she has been using clients’ money to invest in the stock market and has made a substantial amount of money doing so. She also asked you to join with her so that both of you can make a fortune. What should you do in this kind of situation?

A. Report your friend to the appropriate authority.

B. Explore different stock options and find out the best way to make a large amount of money.

C. Find out if what your friend is doing is really illegal or not.

D. Ask your friend to stop the illegal activity, but do not mention it to anyone else.

A

Answer: A

Explanation: You are obligated to report any illegal activity to the appropriate authority.

190
Q

You did not utilize all the tools & techniques of risk identification and disregarded a potential risk. The risk shows up during the project planning phase and surprises the team. What kind of response is expected from you as a project manager?

A. Have a discussion with the sponsor and seek guidance.

B. Develop the risk response plan and determine preventive and corrective actions.

C. Take responsibility and evaluate the impact of the risk item.

D. Immediately inform the customers about the risk event.

A

Answer: C

Explanation: One of the mandatory standards in the PMI code of ethics and professional conduct is responsibility. Responsibility is the act of making and taking ownership of our decisions, admitting our mistakes, and being responsible for our decisions and actions. As a project manager, you must take responsibility for the failure in identifying the risk and evaluate the impact to develop the risk response plan. Once you have the detail on the risk item, you can have a discussion with the customer. Also, you may escalate the risk to the sponsor if the risk is beyond your control.

191
Q

You recently found out that one of your best friends has been pretending to be a PMP. She thinks that the certification is helping her immensely, but she never thought of pursuing it in real life due to the difficulty of the exam. What will be your BEST course of action?

A. Report to your friend’s boss.

B. Hand your friend over to the police immediately.

C. Encourage your friend to get the real certification.

D. Contact PMI and report the situation.

A

Answer: D

Explanation: You are obligated to report any PMI code of ethics and professional conduct violation to PMI.

192
Q

Higher management is exploring the option to open a branch office in a foreign county to outsource backup, storage, and support activities. While conducting the feasibility study, you found out that women are not allowed to work in several sectors, and the country’s law also postulates that the salary of a woman should be 60 percent of that of a man’s for the same job. The country is very welcoming to your business, and the process of opening a new business is simple and fast. Experts with required expertise are easily available, and your company will also save a substantial amount of money in labor, equipment, raw materials, and low taxes. What should be your recommendation? While conducting the feasibility study, you found out that women are not allowed to work in several sectors, and the country’s law also postulates that the salary of a woman should be 60 percent of that of a man’s for the same job. The country is very welcoming to your business, and the process of opening a new business is simple and fast. Experts with required expertise are easily available, and your company will also save a substantial amount of money in labor, equipment, raw materials, and low taxes. What should be your recommendation? A. Ignore the law and compensate the women you will be hiring equally.

A. Ignore the law and compensate the women you will be hiring equally.

B. Consider not hiring any women to avoid conflicts.

C. Negotiate with the official and ask to be excused from laws discriminating women.

D. Consider not opening the branch office in this country.

A

Answer: D

Explanation: One of the mandatory standards in the PMI code of ethics and professional conduct is fairness. Fairness includes making decisions impartially and objectively and avoiding favoritism and discrimination against others. As a project manager you need to make sure that there will be no discrimination against others based on, but not limited to, gender, race, age, disability, nationality, or sexual orientation. You also need to make opportunities equally available to all qualified candidates. Your best course of action will be to recommend not opening the branch office in this country.

193
Q

Your company has been working with numerous financial institutions for several years and has built spectacular relationships with them. Recently you submitted a proposal in response to a bid for a data and disaster center project for one of these financial institutions in which your company has no previous experience and lacks required expertise. Which of the following is TRUE regarding this situation?

A. It is a common practice to exaggerate expertise and experience when submitting a proposal for a bid.

B. You have not violated the PMI code of ethics and professional conduct, but you have violated the procurement code.

C. There is no violation in this situation.

D. You have violated the PMI code of ethics and professional conduct.

A

Answer: D

Explanation: You have violated the PMI code of ethics and professional conduct. As a project manager, you should be honest about the experience and expertise of your organization.

194
Q

You are one of the members of the proposal evaluation team responsible for evaluating and awarding contracts to eligible vendors. While reviewing the list of potential vendors, you notice that one of your good friends is a participant in the bidding process. You know that your friend is an expert in his domain and the project will be greatly benefited if he is awarded the contract. What will be the BEST course of action in this situation?

A. Keep silent and continue with the procurement process.

B. Convince the proposal evaluation team to award your friend the contract.

C. Inform the sponsor and the evaluation team about your relationship.

D. Offer your friend some good tips to increase his chance of winning the bid.

A

Answer: C

Explanation: Since there is a potential conflict of interest, you should discuss the relationship with the sponsor and evaluation team. It will be up to the evaluation team and sponsor to decide whether you should disassociate yourself from the bidding process or not.

195
Q

As a project manager, you are assigned to oversee a network infrastructure project in a foreign country for six months. At the end of the first introductory meeting, all six participants from your team were given exclusive gifts. When you were reluctant to accept your gift, you were told that it is a custom in their country to give this kind of gift to business partners. What will be your BEST course of action?

A. Decline the gift as accepting it will be considered personal gain in your country.

B. Decline the gift as accepting it will be considered conflict of interest in your country.

C .Accept the gift and inform your management so that your integrity will not be questioned later on.

D. Accept the gift as you do not consider it to be a conflict of interest or integrity issue.

A

Answer: C

Explanation: You should accept the gift because if you decline and reciprocate the gesture, it can severely affect your relationship with the customer. You should also immediately inform your management so that your integrity will not be questioned later on.

196
Q

You are implementing a WIMAX network for one of your clients in a rural area. You recently implemented a similar network for another client and installed several towers and POPs for them throughout the same region. The current client can save a considerable amount of time and money if they can rent the existing infrastructure instead of setting up their own towers and POPs. You have a nondisclosure agreement with the previous client, and you are not supposed to disclose any information on their infrastructure or network architecture. What will be your BEST course of action?

A. Ignore the nondisclosure agreement as it is not legally enforceable and share the network architecture and infrastructure from the previous project.

B. Install new towers and POPs for the existing customer and ignore the fact that the existing infrastructure can be used for the benefit of both organizations.

C. Seek guidance from your Project Management Office (PMO).

D. Have a discussion with your previous client and seek permission to share the information on the existing infrastructure.

A

Answer: D

Explanation: You need to work in the best interest of your client and try to save money and time for them if possible by exploring the option of using the existing infrastructure rather than installing new towers and POPs. Even if the nondisclosure agreement is not legally enforceable, you are ethically bound to comply with it. The best course of action will be to have a discussion with the previous client and seek permission to share the information on the existing infrastructure. Seeking guidance from the PMO will not be essential since approval from the PMO to share the information will not make it acceptable.

197
Q

You are participating in a bid in a foreign country for a company that wants to procure several expensive pieces of hospital equipment. You are told by the procuring organization that you need to obtain a trade license from the local authority and that the entire process will take approximately four weeks. There is only one week left for the bidding, and you cannot really wait four weeks for the trade license. While discussing it with one of the local officials, you discover that you can fast-track the process and obtain the trade license in three days if you pay an “urgent fee” of $750. Which of the following should you consider if the fee is within the approved limit in the budget?

A. Wait four weeks if needed, but do not pay the additional fee under any circumstance.

B. Pay the urgent fee and obtain the license in three days.

C. Negotiate the urgent fee and try to lower it as much as possible.

D. Participate in the bidding without the local trade license.

A

Answer: B

Explanation: In this case, the fee has a valid purpose and should not be considered a bribe. You should pay the urgent fee of $750 and obtain the trade license.

198
Q

Your company just assigned you as a project manager for a large data center project. You were asked by the sponsor to complete the project in six months and within $120,000. You soon realize that both the time and cost estimation from higher management is impractical. Your estimation shows that the project could take as long as ten months and that the cost will be at least 20 percent more than the initial estimation. The sponsor tells you that she is considering another project manager to take care of the project in case you do not agree with her time and cost estimations. What will be your BEST course of action?

A. Excuse yourself from the project.

B. Document the time and cost constraints and carry on with the project as instructed.

C. Submit your detailed time and cost estimations and justification to the sponsor.

D. Have an urgent meeting with the client and explain the situation.

A

Answer: C

Explanation: You cannot simply refuse to manage the project because you do not agree with the time and cost estimations of the sponsor. As a project manager, you are expected to present truthful and accurate information regarding time, cost, and other project objectives. So you should submit your detailed time and cost estimations and justification for the longer duration and additional budget. If your justification is reasonable, the sponsor should agree with your argument. Continuing with the project with unrealistic time and cost expectations will be a recipe for failure. Having an urgent meeting with the client will not be appropriate in this situation.

199
Q

You are in charge of a very important, big-budget video game project. You have thirteen identified stakeholders and ten team members in the project. You notice that one of the team members who has a major role in the project has been meeting with an anonymous stakeholder to discuss the project details. What should you do in this situation?

A. Have a discussion with the team member and express your concern.

B. Report it to the functional manager.

C. Have a meeting with the team member and the unidentified stakeholder.

D. Make sure you continue to keep an eye on the team member.

A

Answer: A

Explanation: At first you should have a discussion with the team member to find out why she is meeting with the unidentified stakeholder. Reporting the incident to the functional manager will not be appropriate until you identify any problem.

200
Q

You are overseeing a software project to develop a challenging and innovative video game. One of your friends, who is a connoisseur in this field and has several of his very popular games in the market, has requested you to give him a copy of the game prior to its release so that he can check it out and provide his feedback. You know his feedback will be valuable to find any defects and improve the game. What should you do in this situation?

A. Ask your friend to sign a nondisclosure agreement prior to giving him a copy.

B. Give him a copy of the game since he is an expert and may provide valuable feedback about the game.

C. Make sure that your friend will provide you with the required feedback and suggestions prior to giving him a copy of the game.

D. Decline the request as the game is the intellectual property of your company.

A

Answer: D

Explanation: You should decline the request as the video game is the intellectual property of your organization.