Questions Flashcards
1
Q
To verify the compliance of a credit or prerequisite, a qualified member of the project team submits this:
a. Letter of attestation
b. LEED Scorecard
c. CIR
d. Credit Forms
A
Credit Form
CIRs are issued to ask clarifications on an issue (prerequisite, credit, or MPR). They cost $220 each.
2
Q
To qualify as a regional material, within what distance must a material be extracted, harvested or recovered, and manufactured?
a. 250 miles
b. 100 miles
c. 500 miles
d. 1000 miles
A
500 miles