Question Pack Flashcards

1
Q

Can you tell me what specialist services Purcell were appointed to undertake?

A
  • Lead Designer and Consultant for the Fabric Safety survey and repair project.
  • Principal Designer
  • Sub-consultant appointment of Structural Engineer
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How did you ensure that Purcell acted within their agreed scope of services?

A

I tracked our progress using our activity schedule, which was based upon the employer requirements.

I informed the client via early warning notices of any unforeseen circumstances or additional work required. From these they would decide if they would agree for us to undertake the unplanned work at their cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Talk me through the process you undertook when carrying out the condition survey?

A

Desk top study: Check the previous survey and works documents provided by the client.
Check history
Check building materials to understand properties and typical defects.
When on site, I ensured I was wearing the correct PPE for the MEWP surveys.
I attended site with printed elevations of the building, supplied by the client. I worked systematically across the elevations, recording defects on the elevations. I assigned priority of repair to each defect.
I considered PPM requirements while assigning priority of repair to defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Talk me through how you assigned priority to each defect?

A

For each defect, I selected a priority of repair appropriately so the Client could plan repairs accordingly.
The priorties where 0 to 1 years (immediatly / asap), 1-3 years (high importance), 3-10 years, 10+ years.
0-1 years were defects which had the potential to me immediate health and safety risks or risk to the building.
1-3 years - were defects which although not immediate health and safety risks, could turn into high risks soon, or if not repaired within the time frame could turn into larger more expensive defects to rectify. Essential maintenance.
3-10 years - not immedatly hazardous, however the client should be aware and plan for the repairs as it is important maintnenace.
10+ years - nice to have - distant requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Talk me through how you updated the risk management strategy?

A

As part of Purcell’s professional services and CDM duties, I provided a designers risk register. I included risk relating to access, building fabric, deleterious materials. I updated this on a regular basis throughout the project and presented it to the Project Manager for the Client’s information.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you give me examples of health and safety issues that you identified within your designers risk register?

A
  • Asbestos in window putty - R&D surveys required
  • Noisy works disrupting the business of the Parlaimentary estate
  • Dust from cutting out works
  • Covid 19
  • Heavy lifting
  • Pidgeon guano as risk to site personnell
  • Requirement for suitable training for use of MEWP’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What did the pre-construction information include?

A

**- Construction Phase Plan
**- Overview of the project
- Health and Safety File first issue
- Environmental restrictions
- Clients conditions and management requirements
- Start and finish dates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who’s responsibility is it to provide the PCI?

A

The Client. The PD should assist the Client in preparing this for every Designer and Contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Is the PCI a live document?

A

Yes. It should be updated when new information as the work progresses and more information is attained.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Talk me through some of the queries you received from the contractor and how you resolved them?

A
  • The contractor notified me that when further defects where found in the stonework during construction. They asked me to attend site to decide how to proceed with repair of the findings.
  • The contractor asked me for a specifciation of window film to prevent cracked glass from falling.
  • They asked me to approve material samples (stone and mortar) for use in stone indents.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Talk me through the process of issuing an early warning notice?

A

When an instance that has not been accounted for comes into realisation, contractually, the consultant must raise the issue to the client via an EWNas soon as they know about the issue. This notifies the Client of the issue, and provides a vehicle for them to assess the risks with the consultant. The EWN includes option for notifying the client if the matter could increase the costs, delay the project, or impair the services of the consultant. Following the early warning notice, the consultant may submit a compensation event to to the client for accommodating the change in agreed services mentioned in the EWN.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Talk me through how you prepared your fee quotation for the addition in work?

A

I used Microsoft excel to prepare a fee quotation. I calculated the amount of time I expected it would take to update the design drawings and repair schedules for each of the Purcell personnel, involved, then added how much time I thought it would take for RIBA Stage 5 input. I multiplied the time by each team members hourly rates to create a compensation event. I reviewed this with the Purcell Partner and submitted to the Client for their review.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Talk me through the repair process involved in securing unstable pieces of stone?

A

There were a few instances where finials had become loose. These needed re-pinning back to their bases. Some of these did not have any metal bar securing them. Therefore, I referred to the NBS specification I had prepared which included suitable methodology. This involved acquiring a pinning specification from the structural engineer to add into the design drawings. I stated that the threaded stainless steel bar specified by the SE needed to be back filled by resin. I stated that the joint would need to be pointed using an NHL 3.5 lime mortar. As this was just a Fabric Safety project, some pieces of stone were retained for their re-fixing during a fully comprehensive stone repair project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How did you ensure the repair strategy achieved legislative requirements?

A
  • Our repair strategy was intended to be like-for-like repairs only, therefore the repairs themselves did not require listed building consent.
  • The contractors asked me to review the scaffold drawings. I passed them to our structural engineer to provide indpepentant strucutural review. When I looked at the deisgns myself, I saw that the scaffold contractor had specificed threaded masonry anchors to be empedded into the Grade 1 listed stonework. This would require listed building consent. Therefore I asked the scaffolders to re-design the scaffold so they would not require any mansonry anchors. This involed buttressing of the scaffold and hooking a gantry over parapet walls. This prevented a delay in the project and harm to the listed building.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Did you have to obtain listed building consent?

A

No. The nature of the works were for like for like repair. The works would not change the character of the listed building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What safety implications did you consider, prior to the of the MEWP?

A
  • Could the working at height be avoided? No it could not.
  • I made sure that I undertook a 1 day training course to use a MEWP. This involved harness training and rules for being inthe MEWP basket.
  • That I was wearing all correct PPE, inc. harness, tether, hard had, boots, hellow jacket, gloves, safety glasses.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Talk me through the tender process?

A
  • Included as part of the Multi-Disciplinary Design services scope was for Purcell to assist with Procurement of Contractors including input into tender documents and evaluation. The contractors tendering had to price the tender documents which I produced.
  • The tender docuements were based of an earlier survey supplied by the client.
  • I aided the Client’s tender process by comparing the tender returns.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Why do I want to become a chartered surveyor?

A
  • I believe I have a range of skills that can be beneficial to the profession and built environment
  • I want to more responsiblity and develop in my role as a building surveyor.
  • I would like to gain trust in the workplace, where Clients, colleagues , contractors and indstury professionals feel they can rely on me becuase of my extertise, supported by professional qualification.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the role of the RICS?

A

To promote the usefulness of the profession to the public advantage in the UK and rest of the world. It focusses on protecting the public and upholding the reputation of the RICS within society.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the key functions of the RICS?

A

The Royal Institution of Chartered Surveyors promotes and enforces the highest professional qualifications and standards in the development and management of land, real estate, construction and infrastructure.

19
Q

What is the Royal Charter?

A
  • Sets out difference between a Chartered Surveyor and a surveor
  • The Royal Charter sets out Bye-Laws and Regulations for it’s members to abide by.
  • Requires RICS to act in the public interest
  • It sets a gold standard of excellence and integrity
19
Q

What are the 5 Principles for Better Regulation?

A

Proportionality, Accountability, Consistancy, Targeting and Transparancy

19
Q
A
20
Q
A
21
Q

Is preventative repair or maintenance philosophically acceptable or unacceptable for heritage buildings?

A

Unacceptable

22
Q

What are the 4 methods of dispute resulotion?

A

1) Mediation
2) Ajudication (3rd party independant decision)
3) Arbitration
4) Litigation

RICS Dispute Resolution Service (DRS) is the world’s oldest and largest provider of alternative dispute resolution (ADR) services in the land, property and construction industries

Mediation - Involved 3rd party helping the two parties come to a dispute. Parties pay their own costs. Encouraged by the courts
Ajudication - 3rd party independant decision. Binding in Law unless taken to arbirtation or litigation. Unique to construction industry. It is a statutory right. 28 day process.
Arbitration Confidential process, alternative to litigation. Legally binding. Can only involve 2 parties.
Litigation Involves a couprt providing a final and binding decision.

Sometimes courts will not proceed if the parties have not tried mediation first.

23
Q

What is a tribunal?

A

Tribunals are formed of a panel of specialist judges with a knowlege of many cases of the specialism.
Panel chosen by the government.
Less formal than court

Example; construction tribunal.

24
Q

Who is the preseident of the RICS

A

Anne Gray

Since Janurary 2023

25
Q

Do Purcell use RIBA professional service contract.

A

Find this out

26
Q

What are the RICS Bye-Laws?

A

They set out general regulatory principals and procedures for management of the RICS.

RICS rules and regulations set out more specific details fo rthe operation of the RICS members and firms

27
Q

What do you understand by the term self regulation?

A

The RICS are regulated throgh bye laws and RICS’s own rules and regulations
Having the Royal Charter means that the government should be confident that the RICS appropriatly and dillegently, in line with the five principles of better regulation:
- Proportionality
- Accountability
- Consistency
- Targeting
- Transparency

28
Q

What are the five principles of better regulation:

A
  • Proportionality
  • Accountability
  • Consistency
  • Targeting
  • Transparency
29
Q

Name some examples of RICS bye-laws:

A
  • “B5.3.1 - Every Firm shall comply with any Regulations or Rules which may be laid down to govern the manner in which Firms carry on their business.”
  • The Members of RICS shall consist of the following classes:
    (a) Chartered Members, comprising:
    (i) Fellows;
    (ii) Professional Members;
    (b) Non-Chartered Members; and
    (c) Honorary Members.

-

30
Q

Can you give me a brief summary of the RICS rules and regulations?

A

1) Honesty, integrity, professional obligations
2) Professional compentance, services by compentant indivuals with necessary expertise
3) Good quality and diligent service
4) Respect, encourage diversity, and inclusion
5) Act in public interest, take reponsiblity for actions, prevent harm, maintain public confidencne in the profession

31
Q

What are the minumimm levels of Professional Indemnity insruace (PII) required?

A

Turnover of £100k or less = £250k
Turnover of £100k to £200k = £500k
Turnover of £200k + = £500k

Insured on a claims made basis.
Insured for each and every claim

32
Q

What are the requirements regarding Professional Indemnity Insurance set by the RICS?

A
  • Policy cover must be made on an each and every claim basis
  • RICS sets out the minumum levels of indemity (£100k or less - £250k min limit of indemnity, 100-200k = £500, 200k = 1,000,000.)
  • The RICS sets out the maximum levels of uninsured excess
  • Run-off cover must be in place for at least 6 years.
  • The policy should include cover for past and present employees, directors and partners.
33
Q

Prior to working with a new client, what pre-appointment checks would you undertake?

A
  • Ensuring that I am sufficiently knowledgeable, skilled and competent to carry out the work required.
  • Checking for conflicts of interest in line with the RICS professional guidance on conflicts of interest.
  • Anti-money laundering checks, in line with the Anti-Money Laundering Directive and RICS professional statement Countering Bribery and Corruption, Money Laundering and Terrorist Financing.
  • Ensuring that the firm has sufficient PII insurance to cover the value of the instruction
  • Formalise the engagement in written terms of engagement
34
Q

What must a surveyor do in relation to the Money Laundering and Terrorist Financing (Amendment) Regulations 2022?

A
  • Undertake checks on clients, including requesting individuals’ ID and proof of address or confirmation of a business’s details with Companies House
  • This information must be kept for a minumum of 5 years following delivery of services.
35
Q

What is ISO 9001?

A
  • A QMS. Quality managment system.
  • ISO 9001 Requires firms to follow a clear process of planning, doing, acting and checking. A QMS is a set of interrelated policies, processes and procedures in the core areas that affect a firm’s ability to meet a client’s requirements.
36
Q

MEPFS
How was the contractor selected?

A

Parliament Contractors framework.
I aided the reviewing process for the Client by scoring tenders. The criteria were:
- Quality
- Price
- Expertise
- Methodology
- Check others??????

37
Q

Give a brief synopsis of the new RICS Rules of Conduct

A

1) Honesty, Integrity, Professional Obligations
2) Maintain professional competence, services provided by competent individuals with necessary expertises
3) Good quality and diligent service
4) Treat others with respect, encourage diversity and inclusion
5)M&F Act in the public interest, take responsibility for their actions to prevent harm and maintain public confidence in the profession.

38
Q

What did the new 2022 Rules of Conduct replace?

A

Rules of conduct for members
Rules of conduct for firms
Global and Professional Standards

39
Q

What are the 6 ethical principles that the Rules of Conduct are based on?

A

5 are: Integrity, high standard of service, respect, taking responsibility, promoting trust.

40
Q

Give an example behaviour for each of the new 5 rules of conduct

A

1) Honesty, Integrity, Professional Obligations
- Do not mislead others
2) Maintain professional competence, services provided by competent individuals with necessary expertises
- Check that subcontractors have the necessary knowledge, skills and resources to to their tasks
- Members and firms only undertake work that they have the knowledge, skills and resources to carry out competently
3) Good quality and diligent service
- Firms have good quality checking processes. Purcell are ISO 9001 accredited and we keep to these standards.
- Good, clear communication with client & other partie
4) Treat others with respect, encourage diversity and inclusion
- members and firs do not discriminate between sex, religion, race.
5)M&F Act in the public interest, take responsibility for their actions to prevent harm and maintain public confidence in the profession.
- Members and firms respond to complaints

41
Q

READING How did you ensure compliance with Part L?

A

As space for roof build up was limited, the new roof build up consisted of 22mm Marine Ply deck, vapour control layer, 75mm thickness Celotex GA4000 cold liquid applied waterproofing system.

42
Q

READING. How did you insure sufficient falls on the roof?

A
43
Q

Please explain the process for cleaning leadwork at Reading Town Hall

A

1- Begin by photographing the areas for cleaning to record leadwork condition at beginning.
2 - Clean leadwork with strong lemon based detergent and hessian sacking.
For stubborn stains use nylon brush/pad.
3- Neutralise cleaning product with warm soapy water
4 - Rinse soapy water away thoroughly
5- Dry using clean dry cotton cloths, allow time to air dry to ensure no dampness remains
6 - Apply Patination Oil as per manufacturers recommendations. Ensure patination has adequate time to
dry before evening moisture gets into air.

Undertake the above steps for a discreet sample area first, then once approved by the architect, repeat the steps for the full area for cleaning.

44
Q
A