Question 1 Flashcards

1
Q

What is :

  • Planned Value
  • Earned Value
  • Actual cost
A

Planned value is the budgeted cost of the work that is scheduled.

Earned value is the budgeted cost of the work that is performed

Actual cost is the actual cost of the work performed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What do these things stand for:

  • EV
  • PV
  • AC
A

Earned Value

Planned Value

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is CPI?

What is SPI?

A

Cost Performance Index - Allows you to see the project budget status (e.g over budget)

Schedule Performance Index - Allows you to see the project schedule status (e.g behind schedule)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How do you work out the CPI and SPI

A

ALWAYS USE EV

CPI - EV/AC
COST - ACTUAL COST

SPI - EV/PV
SCHEDULED - PLANNED VALUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What do SPI and CPI percentages mean?

A

SPI

<100 = Behind Schedule
100   = On Schedule/Time
>100 = Ahead of Schedule
———————————————
CPI
<100 = Over budget
100   = In line with budget
>100 = Under budget
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is SV and CV

And how do you work it out?

A

Schedule Variant = EV-PV

Cost Variant = EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly