Question 1 Flashcards
What is :
- Planned Value
- Earned Value
- Actual cost
Planned value is the budgeted cost of the work that is scheduled.
Earned value is the budgeted cost of the work that is performed
Actual cost is the actual cost of the work performed
What do these things stand for:
- EV
- PV
- AC
Earned Value
Planned Value
Actual Cost
What is CPI?
What is SPI?
Cost Performance Index - Allows you to see the project budget status (e.g over budget)
Schedule Performance Index - Allows you to see the project schedule status (e.g behind schedule)
How do you work out the CPI and SPI
ALWAYS USE EV
CPI - EV/AC
COST - ACTUAL COST
SPI - EV/PV
SCHEDULED - PLANNED VALUE
What do SPI and CPI percentages mean?
SPI
<100 = Behind Schedule 100 = On Schedule/Time >100 = Ahead of Schedule ——————————————— CPI
<100 = Over budget 100 = In line with budget >100 = Under budget
What is SV and CV
And how do you work it out?
Schedule Variant = EV-PV
Cost Variant = EV-AC