Q&A Technical Terms Flashcards

1
Q

Under NRM 2 how do you measure a steel frame?

A
  • State the components e.g. beams, columns, connections, and floor and roof structures
  • Columns, beams, bracing in tonne.
  • Connections, number or weight depending on type.
  • Purlins and decking, linear meter.
  • Fire protection to surface area of the steel. Measure in m2.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Under NRM 2 how do you measure a concrete frame?

A
  • State components e.g. columns, beams, slabs
  • Concrete by volume
  • Formwork in m2
    • columns formworks is to side
    • beams formwork to sides and soffit
    • slabs formwork to soffit and edges
  • Reinforcement in tonne
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are purlins?

A

Horizontal structural members in a roof that support the roof deck or sheeting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a cold rolled purlin?

A

A lightweight, strong structural steel member formed by cold-rolling steel sheets into a specific shape (typically Z, C, or Sigma) for use in supporting roof or wall panels in buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Under NRM 2 how do you measure piling?

A
  • Piling mats in m2
  • Piling plant as an item
  • Moving piling rig to location in nr
  • State pile details (diameter and depth) in lm
    • sheet pile might be in m2
  • Disposal of excavated material in m3
  • Allowance for breaking through constructions in nr
  • Cutting off top of piles in nr
  • Pile tests in item
  • Pile caps in m
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Collateral Warranties

A
  • Step-in rights
  • Extend the liability of the contractor, sub-contractor or designers to cover third parties
  • Gives the beneficiary direct legal rights, making it easier to recover losses.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are step in rights?

A

Rights for a third party, to step in to a contract and take over a development in order to complete it if the employer becomes insolvent or is otherwise in default.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What do RICS registered firms include in their annual RICS returns?

A
  • Staffing
  • Nature of clients
  • Training provisions
  • Complaints handling procedures
  • PI details
  • If the firm holds clients money
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the RICS rules on holding Clients money?

A
  • Inform RICS
  • Secure accounting and data systems
  • Money is sepearete and identifiable
  • Clients must have access
  • Provide a running balance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you need to do when setting up an RICS practice?

A
  • Obtain RICS start up policy pack
  • Register with RICS
  • Appoint RICS contact officer
  • Complaints handling procedure
  • PII
  • Rules of conduct for firms
  • Use the ‘regulated by RICS’ on all material
  • Locum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the professional obligations of firms?

A
  • Complaints handling procedure
  • Adequate PII
  • With a sole principal must make arrangements for the ongoing nature of the business in the case of their death
  • Cooperate with the RICS
  • Provide all info requested by Standards and Regulation boards
  • Must display ‘regulated by RICS’ on literature
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What changes did you make to go from BREEAM excellent to outstanding?

A
  • 11 credits
  • 1 credit for Considerate Constructors Exemplory Performance
  • 3 credits from the monitoring of construction site impacts and recycling of materials
  • 3 credits for the refrigerant used in the VRF
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the RESET certification?

A

A standard for real time monitoring of internal air quality and energy efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are some instructions that you feel took the contractors time?

A
  • BREEAM
  • Fitwell, inclusion of herb garden
  • RESET Certification
  • Paxton 10full CCTV security system in lieu of Paxton Net 2
  • PV’s, extend the PV supply by 90m2
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are some changes to JCT 2024?

A
  • Supplemental provisions have been made mandatory;
    • Collaboration
    • Notification and negotiation of disputes, old provision 10
  • Changes following the Building Safety Act 2022
    • Principal Contractor and Designer now need to be identified in Article 7
  • Modernisation
    • Gender neutral language
    • Allowance to administer the contract electronically
  • Updates to relevant events and relevant matters
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are capital allowances and how do they affect accounts?

A
  • Tax relief
  • Sometimes can save money on new build carpets for example in new homes
  • Clients will draw down on the capital expenditure over a number of years. The percentage will differ.
17
Q

Do you accept gifts?

A
  • No
  • Decision tree
  • Check value
  • Timing
  • Log register
18
Q

What is the structure of the RICS?

A
  • Self-regulated.
  • Bye laws determine how the RICS is regulated. Who regulates the,?
  • Governing council, manage and agree strategy
  • Regulatory board, Audit committee, Management board they execute the strategy
19
Q

Under CDM what key roles does the Client have?

A
  • Appoint the duty holders
  • Ensure the principal designer and the principal contractor carry out their duties
  • Ensure sufficient resources are available to manage the projects.
  • Notify the HSE if required
  • Ensure the construction phase plan and the health and safety file are prepared.
20
Q

Under CDM what key roles does the Principal Designer have?

A
  • Plan, manage, and monitor the pre-construction phase
  • Coordinate health and safety in the pre-construction phase
  • Identify, eliminate, or control forseeable risks
  • Provide relevant information to other duty holder
  • Liaise with the principal contractor
  • Prepare the health and safety file
  • The principal designer also has the duties of the designer too.
21
Q

Under CDM what key roles does the Principal Contractor have?

A
  • Plan, manage, and coordinate the construction phase to ensure H&S
  • Ensure compliance with H&S
  • Develop Construction Phase Plan
  • Monitor H&S on site
  • Maintain H&S file
  • Coordinate works on site to prevent accidents
22
Q

What types on conflict are there?

A
  • Personal conflict
  • Party conflict
  • Document conflict
23
Q

What are some elements in building reg part b?

A

Fire Safety
- Provisions for safe escape routes
- Requirements for fire detection and alarm systems
- Fire-fighting access
- Compartmentation, design requirements to limit fire spreading

24
Q

What are some elements in building reg part p?

A

Electrical Safety in Residential Properties
- Notifiable work, e.g. new circuits
- Certified equipment
- Ensuring electrical installations are accessible
- Encourages the use of energy efficient electrical systems

25
Q

Breakdown of work to retain steelwork at Erith?

A
  • Remove steelwork and transport away from site
  • Inspection of steelwork
  • Sandblasting of existing finish
  • Any repairs required
  • Intumescent paint
  • Powder-coat finish
26
Q

How does intumescent paint work?

A

When exposed to high temperatures the chemicals in the paint react and expand to form an insulating layer around the steel.

27
Q

What is the build up of a partition wall?

A

Metal frame
- top and bottom tracks installed to the top and bottom of the wall
- metal studs at 400 - 600cm
- insulation, acoustic or thermal
- wall panels, plasterboard, fireboard, moisture resistant board
- joint and finish
- paint or wall covering

  • patressing, PDF panels installed between the tracks at specific places.
28
Q

What is the build up of a party wall?