PURPOSE Flashcards

1
Q

The purpose of this document is to provide users with the basic minimum and recommended elements for ,,,,

A

developing,
implementing, and
maintaining a RBI program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The approach (RBI) emphasizes safe and reliable operation through ,,,,,,

A

risk-prioritized inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A spectrum of complementary risk analysis approaches (,,,,,,,,) can be considered as part of the inspection planning process

A

qualitative through fully quantitative

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The expected outcome from the application of the RBI process should be ,,,, ,,,,,.

A

the linkage of risks with appropriate inspection, process control, or other risk mitigation activities to manage the risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The RBI process is capable of generating:

A
  • a ranking by relative risk
  • a detailed description of the inspection plan
  • a description of any other risk mitigation activities
  • the expected risk levels
  • identification of risk drivers
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

General:

This RP contains both minimum program requirements to qualify ,,,,,,,

A

for interval extension beyond rule-based (1/2 life) requirements
&
provides additional suggested guidelines on using risk analysis to develop an effective RBI program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Work Process Requirements:

Work process requirements include the following:

A
  • A documented management system
  • Sufficient data shall be captured and maintained
  • The basis for both the POF and COF shall be documented
  • The various inputs used to assess both the POF and COF shall be captured
  • The POF, COF, and risk results shall be captured in the documentation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Data Requirements:

Data inputs and assumptions shall be validated by qualified personnel such as ,,,,,, to review operating parameters used

A

process engineer/operator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Damage Mechanisms and Failure Modes:

The RBI team shall consult with a ,,,, to define the equipment damage mechanisms, damage modes (optional), and potential failure modes

A

corrosion specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Damage Mechanisms and Failure Mode

A qualified ,,,,, shall be responsible for assessing the types of damage mechanisms and their applicability and severity to the equipment

A

corrosion specialist

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

POF Analysis :

POF analysis requirements include the following:

A
  • shall address all credible damage mechanisms
  • evaluated to identify active and credible damage mechanisms
  • determine the effectiveness in finding the identified mechanisms
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

COF Analysis:

COF analysis requirements include the following:

A
  • estimate the consequences that are likely to occur due to a failure
  • The major factors in evaluating the consequences of failure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Evaluation of Risk:

Risk shall be determined by combining the ,,,,

A

POF & COF (Risk = probability × consequence)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Evaluation of Risk:

Overall risk shall include the ,,,,,

A

probability of loss of containment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Output:

Output requirements include the following:

A

-Items with unacceptable risk to the owner-user
(In addition, higher risk items should also be prioritized)
-The inspection strategy shall be a documented
-Inspection results such as the identification of damage mechanisms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

RBI Reassessment and Updating:

Requirements for RBI reassessment and updating include the following;

A
  • Changes are inevitable and the results from the RBI assessment shall be updated
  • the results shall be reviewed to determine if an RBI reassessment is necessary
  • The governing inspection codes (such as API 510, API 570, and API 653) and jurisdictional regulations, if any,
    shall be reviewed in this context
17
Q

RBI Benefits and Limitations:

The primary work products of the RBI assessment and management approach are ,,,,

A

plans

18
Q

RBI Benefits and Limitations:

equipment plans highlight risk from ,,,,, and/or from ,,,,,

A

a safety/health/ environment perspective

an economic standpoint.

19
Q

RBI Benefits and Limitations:

RBI plans should include ,,,, along with ,,,,.

A

cost-effective actions

projected risk mitigation

20
Q

RBI Benefits and Limitations:

Implementation of these plans provides one of the following:

A
  • an overall reduction in risk for the facilities and equipment assessed;
  • an acceptance/understanding of the current risk
21
Q

RBI Benefits and Limitations:

In some cases, in addition to risk reductions and process safety improvements, RBI plans may result in ,,,,,,

A

cost reductions

22
Q

RBI Benefits and Limitations:

RBI is based on sound, proven risk assessment and management principles. Nonetheless, RBI will not compensate for

A

a) inaccurate or missing information;
b) inadequate design or faulty equipment installation;
c) operating outside the acceptable IOWs;
d) not effectively executing the plans;
e) lack of qualified personnel or teamwork;
f) lack of sound engineering or operational judgment

23
Q

Using RBI as a Continuous Improvement Tool:

Utilization of RBI provides a ,,,, for continuously improving the inspection of facilities and systematically reducing the risk associated with pressure boundary failures

A

vehicle

24
Q

RBI as an Integrated Management Tool:

RBI is a risk assessment and management tool that addresses an area of risk management not completely addressed in other organizational risk management efforts such as ,,,,

A

process hazards analyses, (PHA)
IOWs, or
Reliability centered maintenance. (RCM)

25
Q

RBI as an Integrated Management Tool:

RBI produces plans that identify the actions that should be taken to provide ,,,,

A

reliable and safe operation

26
Q

RBI as an Integrated Management Tool:

An RBI effort can provide input into an organization’s annual planning and budgeting to
define the ,,,,,

A

staffing and funds required to maintain equipment operation at acceptable levels of performance and risk

27
Q

RBI as an Integrated Management Tool:

RBI define and maintain IOWs as well as a robust MOC process as a basis to manage and control ,,,,,

A
  • damage mechanisms in fixed equipment.