PSM 1 Flashcards
Upon what type of process control is Scrum based?
(choose the best answer)
A. Complex
B. Defined
C. Hybrid
D. Empirical
D. Empirical
Scrum is founded on empiricism and lean thinking. Empiricism asserts that knowledge comes from experience and making decisions based on what is observed.
What does it mean to say that an event has a timebox?
(choose the best answer)
A. The event must happen at a set time.
B. The event can take no more than a maximum amount of time.
C. The event must happen by a given time.
D. The event must take at least a minimum amount of time.
B. The event can take no more than a maximum amount of time.
Timeboxed events are events that have a maximum duration.
The CEO asks the Developers to add a “very important” item to a Sprint that is in progress. What should the Developers do?
(choose the best answer)
A. Add the item to the next Sprint.
B. Add the item to the current Sprint without any adjustments.
C. Add the item to the current Sprint and drop an item of equal size.
D. Inform the other members of the Scrum Team so the team can decide what to do.
D. Inform the other members of the Scrum Team so the team can decide what to do.
The items selected for a Sprint have been selected as most valuable with the Product Owner. The items serve the Sprint’s goal. No changes should be made that endanger the Sprint Goal. No one external to the Scrum Team can force changes on the Developers.
During a Sprint, a Developer determines thatthe Scrum Teamwill not be able to complete the items in their forecast. Who should be present to review and adjust the Product Backlog items selected?
(choose the best answer)
A. The Developers.
B. The Product Owner and the Developers.
C. The Product Owner and all stakeholders.
D. The Scrum Master, the project manager, and the Developers
B. The Product Owner and the Developers.
During the Sprint, scope may be clarified and re-negotiated between the Product Owner and the Developers as more is learned. It is important to be transparent when challenges arise since ultimately the entire Scrum Team is accountable for creating a valuable, useful Increment.
True or False: It is mandatory that the product Increment be released to production at the end of each Sprint.
False
The product Increment should be usable and releasable at the end of every Sprint, but it does not have to be released.
Who has the final say on the order of the Product Backlog?
(choose the best answer)
A. The Developers.
B. The Product Owner.
C. The Scrum Master.
D. The Stakeholders.
E. The CEO.
B. The Product Owner.
The Product Owner is the sole person responsible for ordering the Product Backlog.
The Developers should not be interrupted during the Sprint and the Sprint Goal should remain intact. These are conditions that foster creativity, quality and productivity.
(Which one the following answers is FALSE?)
A. The Sprint Backlog is fully formulated in the Sprint Planning event and does not change during the Sprint.
B. The Developers may work with the Product Owner to add or remove work if they find themselves with more or less capacity than expected.
C. As a decomposition of the selected Product Backlog items, the Sprint Backlog changes and may grow as the work emerges.
D. The Product Owner can help clarify or optimize the Sprint when asked by the Developers.
A. The Sprint Backlog is fully formulated in the Sprint Planning event and does not change during the Sprint.
The Sprint Backlog makes visible all of the work that the Developers identify as necessary to meet the Sprint Goal. The Developers modify the Sprint Backlog throughout the Sprint, and the Sprint Backlog emerges during the Sprint.
Which statement best describes a Product Owner’s responsibility?
(choose the best answer)
A. Keep stakeholders from distracting the Developers.
B. Managing the project and ensuring that the work meets the commitments to the stakeholders.
C. Directing the Developers.
D. Maximizing the value of the work the Scrum Team does.
D. Maximizing the value of the work the Scrum Team does.
The Product Owner is accountable for maximizing the value of the product and the work of the Scrum Team.
When many Scrum Teams are working on a single product, what best describes the Definition of Done?
(choose the best answer)
A. Each Scrum Team uses its own, but must make their definition clear to all other teams so the differences are known.
B. All Scrum Teams must have a Definition of Done that makes their combined Increment valuable and useful.
C. It depends.
B. All Scrum Teams must have a Definition of Done that makes their combined Increment valuable and useful.
The Increment must be valuable and useful. This means that when many Scrum Teams are working on a single product, they are expected to adhere to a single Definition of Done for the Increment.
When does a Sprint conclude?
(choose the best answer)
A. When all Product Backlog items meet their Definition of Done.
B. When the Sprint Retrospective is complete.
C. When the Product Owner decides enough has been delivered to meet the Sprint Goal.
D. When all the tasks are completed by the Developers.
B. When the Sprint Retrospective is complete.
The Sprint is a container for the following timeboxed events: Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. Sprints are fixed length events of one month or less to create consistency, and a new Sprint starts immediately after the conclusion of the previous Sprint.
The Sprint Retrospective concludes the Sprint, and is timeboxed to a maximum of three hours for a one-month Sprint. For shorter Sprints, the event is usually shorter
Though not typical, a Sprint can end if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to end the Sprint prematurely.
The timebox for a Daily Scrum is?
(choose the best answer)
A. Two minutes per person.
B. 15 minutes.
C. 4 hours.
D. The same time of day every day.
E. 15 minutes for a 4-week sprint. For shorter Sprints it is usually shorter.
B. 15 minutes.
The Daily Scrum is a 15-minute event for the Developers of the Scrum Team. The Scrum Master serves the Scrum Team by ensuring that all Scrum events take place and are positive, productive, and kept within the timebox.
The timebox for the Sprint Review is:
(choose the best answer)
A. 4 hours and longer as needed.
B. As long as needed.
C. 2 hours.
D. 1 day.
E. 4 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
E. 4 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
Sprint Review is a maximum four-hour timeboxed event for one-month Sprints. For shorter Sprints, the event is usually shorter.
When might a Sprint be abnormally cancelled?
(choose the best answer)
A. When it becomes clear that not everything will be finished by the end of the Sprint.
B. When the Sprint Goal becomes obsolete.
C. When the Developers feel that the work is too hard.
D. When the sales department has an important new opportunity.
B. When the Sprint Goal becomes obsolete.
A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.
Which of the following are examples of a Scrum Team practicing Scrum poorly or not exhibiting traits of a self-managing Scrum Team?
(choose the best three answers)
A. The Developers are collaboratively selecting their own work during the Sprint.
B. The Developers invite external stakeholders to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.
C. The Developers create their own Sprint Backlog, reflecting all work that is required to meet the Definition of Done.
D. The Developers are working within the boundaries of their organizations functional description and nicely handing off work from analyst to developer to tester to integration.
E. The Developers have all the skills they need to create a valuable, useful Increment.
F. Stakeholders attend the Daily Scrum to check on the Scrum Team’s progress.
B. The Developers invite external stakeholders to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog.
D. The Developers are working within the boundaries of their organizations functional description and nicely handing off work from analyst to developer to tester to integration.
F. Stakeholders attend the Daily Scrum to check on the Scrum Team’s progress.
- The Daily Scrum is for the Developers. It should not be used by external stakeholders to check progress.
- During Sprint Planning the Scrum Team should be crafting the Sprint Goal based on the set of Product Backlog items selected for the Sprint. The Developers identify the necessary work to meet the Sprint Goal.
- Scrum Team members do not have titles, and no sub-teams; such as testing, architecture, or operations are recognized. Accountability belongs with the Scrum Team as a whole, regardless of whether team members have specialized skills.
What is the main reason for the Scrum Master to be at the Daily Scrum?
(choose the best answer)
A. To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burn-down.
B. To make sure every team member answers the three questions.
C. They do not have to be there; they only need to ensure the Developers have a Daily Scrum.
D. To gather status and progress information to report to management.
C. They do not have to be there; they only need to ensure the Developers have a Daily Scrum.
The Scrum Master only ensures that all Scrum events take place and are positive, productive, and kept within the timebox.