Provisional Sums & Prime Cost Sums Flashcards
827 What is a provisional sum?
This is a JCT term for an amount of money that is set aside to deal with a particular aspect of a project where the full scope is not sufficiently defined, designed or detailed to allow accurate pricing. The NEC does not deal with provisional sums.
828 How are provisional sum expended?
The contract administrator (JCT contracts) should issue an instruction for its expenditure. Where the contract includes provisional sums the final amount payable will be adjusted (the provisional sum is omitted and replaced with the actual cost of the work)
829 How are provisional sums dealt with in the final account?
830 How does the NEC incorporate provisional sums?
The NEC does not recognise provisional sums. The NEC approach is that if an element of work is so unclear that it is excluded until it can be clearly defined.
831 What types of provisional sums are there?
Defined and undefined.
832 What is the difference between a defined and an undefined sum?
Defined: Is a sum where the contractor has deemed to have allowed for programme and prelims within the contract
Undefined: Where the contractor has not allowed for planning, programming and prelims implications. This may mean the contractor is entitled to an EOT and or additional prelims when then works are undertaken.
833 Would the contractor be entitled to claim additional prelims and or EOT when expending a defined provisional sum?
No under a defined provisional sum the contractor is deemed to have allowed for programme and prelims within their price.
834 What are prime cost sums?
- A sum of money included in a unit rate to be expended on materials or goods from suppliers. I.e. supply only bricks
- It is a supply only rate for goods or materials where the quantity is unknown
- PC sums exclude all the cost for fixing, installation, fees OH & P etc.
835 What is the difference between PC sums and defined provisional sums?
PCS only includes for the goods or materials. Whereas a defined provisional sum includes the cost of supply, fixing and all other associated costs.
Pricing of contracts
836 Can you name some of the pricing documents that you might use at tender stage?
- Bill of quantities
- Priced activity schedule
- Schedule of rates
- Contract sum analysis
- Schedule of work
837 Can you name some of the pricing options for construction contracts?
.
- Lump sum – NEC Option A
- Remeasurable – NEC Option B & D
- Target cost – NEC Option C
- Cost reimbursable – NEC Option E
- Guaranteed maximum price – Not an NEC options but Target costs contracts can do this
838 What is a lump sum contract?
One where the price of the works is fixed at contract signature. The contractor bears the risk for the cost exceeding the price. This is only amended if the Client instructs a change or one of the NEC compensation events is triggered
839 What are the key advantages of a lump sum contract?
- For the Client it shifts some of the construction risk onto the contractor
- It provides cost certainty for the Client from an early stage
- The contractor may benefit from this. If they can deliver the project for less than the priced agreed they will improve their profits.
840 What are the key disadvantages of a lump sum contract?
- That as the construction risk is shifted to the contractor this may attract a premium as the contractor holds more risk. This may lower their profits
- That it can be more costly to make changes to the design
- The lump sum price is only as good as the design it was priced from. Errors in this could be costly.
841 What is a cost plus contract?
This is where the contractor gets the cost incurred during the project (delivering the scope) plus a predetermined fee %. Also known as cost reimbursable contracts.