Protest, MOD, WB Reading 4-7 to 4-9 Flashcards

1
Q

What is a bilateral modification?

A

A negotiated equitable adjustment resulting from the issuance of a change order

Requires the signature of the Contracting Officer and the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a change order?

A

Change to a contract where the KO directs the contractor to make change with or w/o consent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a change order?

A

Written order signed by PCO, directing the contractor to make a change without prior agreement

Authorized by the “Changes Clause” under noncommercial efforts

Limitations to Changes

  • Place of delivery
  • Change in packaging
  • Change to design or specifications

Contractor must continue performance, as changed

Creates “undefinitized” Government liability & contractor may be entitled to equitable adjustment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define in-scope modification:

A

An “in-scope” modification does not:

Place an undue burden on the contractor

Does not disrupt the competitive aspect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define out of scope modification:

A

Changes that are “Out-of-Scope” are considered “Cardinal Changes”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cardinal changes are:

A

Are NOT in scope

Should be the exception, not the rule

  • Are not prohibited
  • May require a J&A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a constructive change?

A

Oral or written act or failure to act by Government official (in a position of authority) construed by contractor as having same effect as a written change order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A constructive change must involve:

A

Change in performance beyond minimum contract requirements, and

Word or deed by Government representative which requires contractor effort that is not a necessary party of the contract

Requires Ratification

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IAW Modification policy, only _______________ are empowered to execute modifications on behalf of the Government.

A

Contracting officers (KOs)

Preference for priced modifications if time permits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Unilateral modifications are:

A

Change order issued per the changes clause (within scope of contract)

Only contracting officer’s signature needed

May be used for administrative changes such as paying office change, fund cite change, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Bilateral modification requires:

A

Requires the signature of the Contracting Officer and the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Unilateral modification requires:

A

Only contracting officer’s signature needed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What part of the FAR addresses PROTESTS?

A

FAR 33

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a protest?

A

a written objection by an interested party to any of the following:

(1) A solicitation or other request by an agency for offers for a contract for the procurement of property or services.
(2) The cancellation of the solicitation or other request.
(3) An award or proposed award of the contract.
(4) A termination or cancellation of an award of the contract, if the written objection contains an allegation that the termination or cancellation is based in whole or in part on improprieties concerning the award of the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

In what three fora can an interested party file a protest?

A

i. Agency
ii. Government Accountability Office (GAO)
iii. U.S. Court of Federal Claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How long should it take to resolve an agency protest?

A

35 days

17
Q

How long should it take to resolve a GAO protest?

A

100 days

18
Q

What is the deadline for filing a protest?

A

no later than 10 days after the basis of protest is known or should have been known, whichever is earlier

19
Q

How many days does a contractor have to request a debriefing?

A

3 days

20
Q

How many days does the government have to respond to and schedule a request for debriefing?

A

5 days

21
Q

What is contract administration?

A

involves those activities performed by government officials after a contract has been awarded to determine how well the government and the contractor performed to meet the requirements of the contract

22
Q

Contract administration encompasses:

A

all dealings between the government and the contractor from the time the contract is awarded until the work has been completed and accepted or the contract terminated, payment has been made, and disputes have been resolved

23
Q

In contract administration, the focus is on:

A

obtaining supplies and services, of requisite quality, on time, and within budget

24
Q

The responsibility for contract administration may be retained by the contracting office …….

A

referred to as “cradle to grave” or delegated, partially or entirely, to a contract administration office (CAO)

25
Q

Post award orientation can be either by:

A

conference, letter or some other form of communication, facilitates the establishment of a good working relationship

26
Q

A post award orientation aids both government and contractor personnel to:

A

(1) achieve a clear and mutual understanding of all contract requirements
(2) identify and resolve potential problems

However, is not a substitute for the contractor’s fully understanding the work requirements at the time offers are submitted, nor is it to be used to alter the final agreement arrived at in any negotiations leading to contract award

27
Q

Products not delivered on time can be requested by:

A

consideration

28
Q

Post award orientation:

A

is not always necessary (ex: supply items)

dependent upon requirement, complexity of requirement

29
Q

Alternative Dispute Resolution (ADR) technique is known as:

A

partnering

should be discussed with the contractor to help avoid future contract administration problems

30
Q

Past performance information is:

A

relevant info

for future source selection purposes regarding a contractor’s actions under previously awarded contracts

31
Q

Past performance information includes:

A

(1) Conforming to contract requirements and to standards of good workmanship;
(2) Forecasting and controlling costs;
(3) Adherence to schedules, including the administrative aspects of performance;
(4) Reasonable and cooperative behavior and commitment to customer satisfaction;
(5) Reporting into databases
(6) Integrity and business ethics; and
(7) Business-like concern for the interest of the customer.

32
Q

FAR 42.1503 requires that agencies:

A

furnish a copy of their contractor performance evaluations to contractors and that contractors be given an opportunity to respond

33
Q

Step one in contract administration is:

A

Read the Contract

34
Q

Partnering is known as:

A

Alternative Dispute Resolution (ADR) technique

35
Q

Limitations to Changes in change orders:

A
  • Place of delivery
  • Change in packaging
  • Change to design or specifications