Project Scope Management Flashcards

1
Q

Plan Scope Management - Inputs?

A
  1. Project charter
  2. Project management plan
  3. Enterprise environmental factors
  4. Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Plan Scope Management - Tools & Techniques?

A
  1. Expert judgement
  2. Data analysis
  3. Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Plan Scope Management - Outputs?

A
  1. Scope management plan

2. Requirements management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Collect Requirements - Inputs?

A
  1. Project charter
  2. Project management plan
  3. Project documents
  4. Business documents
  5. Agreements
  6. Enterprise environmental factors
  7. Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Collect Requirements - Tools & Techniques?

A
  1. Expert judgement
  2. Data gathering
  3. Data analysis
  4. Decision making
  5. Data representation
  6. Interpersonal and team skills
  7. Context diagram
  8. Prototypes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Collect Requirements - Outputs?

A
  1. Requirements documentation

2. Requirements traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define Scope - Inputs?

A
  1. Project charter
  2. Project management plan
  3. Project documents
  4. Enterprise environmental factors
  5. Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define Scope - Tools & Techniques?

A
  1. Expert judgement
  2. Data analysis
  3. Decision making
  4. Interpersonal and team skills
  5. Product analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define Scope - Outputs?

A
  1. Project scope statement

2. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Create WBS - Inputs?

A
  1. Project management plan
  2. Project documents
  3. Enterprise environmental factors
  4. Organizational process assets
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Create WBS - Tools & Techniques?

A
  1. Expert judgement

2. Decomposition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Create WBS - Outputs?

A
  1. Scope baseline

2. Project documents updates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Validate Scope - Inputs?

A
  1. Project management plan
  2. Project documents
  3. Verified deliverables
  4. Work performance data
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Validate Scope - Tools & Techniques?

A
  1. Inspection

2. Decision making

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Validate Scope - Outputs?

A
  1. Accepted deliverables
  2. Work performance information
  3. Change requests
  4. Project documents updates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Control Scope - Inputs?

A
  1. Project management plan
  2. Project documents
  3. Work performance data
  4. Organizational process assets
17
Q

Control Scope - Tools & Techniques?

A
  1. Data analysis
18
Q

Control Scope - Outputs?

A
  1. Work performance information
  2. Change requests
  3. Project management plan updates
  4. Project documents updates