Project Risks Flashcards

1
Q

What are the two typical risk areas?

A

1) Entity Risks (Sponsor, Contractor, Host Government)

2) Transaction Risks (FX, Inflation, Liquidity, Pricing, Country, Legal, Environment, Force Majeure)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are typical risks in developing countries and emerging markets?

A

technical, environmental, economic and political risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is meant by “project delivery methods” regarding risks?

A

risk mitigation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Entity Risks: Sponsor: Objectives

A
  • limiting further development costs
  • minimizing transaction costs
  • recovering development stage expenses
  • long term: CF generation potential
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Entity Risks: Contractor: Objectives

A
  • is concerned with difficulty of predicting events that could adversly impact the parameters of the project and avoiding them
  • concerned with the underlying financing documents, including whether the sponsor has arranged sufficient financing to pay the contractor for work performed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Entity Risks: Host Government: Objectives

A

Short term: political benefits and attracting other developers to a country
Long term: improve economic prosperity and perhaps political stability
- H.G. usually takes part of the project risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are (in general) typical risk sectors?

A
  • FX and Interest Rate
  • Inflation, Liquidity and product pricing
  • country/ political risk
  • Legal Risks
  • Environmental Risk
  • Opposition
  • Force Majeure
  • Functional- &Operational Risk
  • Completion Risk
  • Supply Risk
  • Financing Risk
  • Technological Risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the three time frames PF risks can be divided in in which the elements of credit exposure assume different characteristics?

A

1) Engineering and construction phase
2) Start-up phase
3) Operations phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is the Engineering and Construction Phase characterized and what are typical risks?

A

1) Risk is highest; no CFs are generated; length can vary from several month to several years
2) Siting and permitting (political risk), completion risk, building materials, cost overruns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are characteristics of the Start-up Phase?

A
  • may last for period of many month
  • banks to be satisfied
  • phase is especially significant if the loan becomes “non-recourse” once the project has been completed
  • potential conflict of interest
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are typical risks during the operational phase?

A
  • raw material/ supply risk
  • off-take and sales risk
  • technology/ obsolescence risk (technological failure)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Mitigating construction and completion risk

A
  • Turnkey contract
  • fixed price lump sum contract
  • cost overruns
  • completion guarantee
  • Liquidated damages in construction contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Mitigating operational risks

A
  • take- or pay contract

- take- and pay contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Mitigating Financial risks

A
  • Futures
  • Forwards
  • Options
  • Swaps
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the two other types of risk mitigation (can be applied to different types of risks)?

A
  • Guarantees (Limited, unlimited, indirect, etc.)

- Insurance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why are project finance transaction particularly vulnerable to force majeure risks?

A
  • complexity of transactions
  • numerous participants in project
  • physical nature of construction activity
  • associated technical and performance risks
  • impact of geographic distance and transport of raw materials