Project Risk Management Flashcards

1
Q

Acceptance

A

A risk response appropriate for both positive and negative risks, but often used for smaller risks within a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Ambiguity risks

A

Risks that have an uncertain, unclear nature, such as new laws or regulations, the marketplace conditions, and other risks that are nearly impossible to predict.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Avoidance

A

A risk response to avoid the risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Brainstorming

A

The most common approach to risk identification; usually completed by a project team with subject mater experts to identify the risks within the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Business risks

A

These risks may have negative or positive outcomes. Examples include using a less experienced worker to complete a task, allowing phases or activities to overlap, or forgoing the expense of formal training for on-the-job education.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cardinal scales

A

A ranking approach to identify the probability and impact using a numerical value, from 0.01 (very low) to 1.0 (certain).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Checklists

A

a quick and cost-effective risk identification approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Data precision

A

The consideration of the risk ranking scores that takes into account any bias, the accuracy of the data submitted, and the reliability of the nature of the data submitted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Decision tree

A

A method to determine which of two or more decisions is the best one. The model examines the costs and benefits of each decision’s outcome and weighs the probability of success for each of the decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Delphi technique

A

An anonymous method of querying experts about foreseeable risks within a project, phase, or component of a project. The results of the survey are analyzed by a third party, organized, and then circulated to the experts. There can be several rounds of anonymous discussion within the Delphi Technique, without fear of backlash or offending other participants in the process. The goal is to gain consensus on project risks within the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Enhancing

A

A risk response that attempts to enhance the conditions to ensure that a positive risk event will likely happen.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Escalating

A

A risk response that is appropriate for both positive and negative risk events that may outside of the project manager’s authority act upon.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Expected monetary value (EMV)

A

The monetary value of a risk exposure based on the risk’s probability and impact in the risk matrix. This approach is typically usd in quantitative risk analysis because it quantifies the risk exposure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Exploit

A

A risk response that takes advantage of the positive risks within a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

External risks

A

These risks are outside of the project, but directly affect it, such as natural disasters, labor issues, etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Flowcharts

A

System or process flowcharts show the relationship between components and how the overall process works. These are useful for identifying risks between system components.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Influence diagrams

A

An influence diagram charts out a decision problem. It identifies all of the elements, variables, decisions, and objectives and also how each factor may influence another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Ishikawa diagrams

A

Cause-and-effect diagrams

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Low-priority watch list

A

Low-priority risks are identified and assigned to a watch list for periodic monitoring.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Mitigation

A

A risk response effort to reduce the probability and/or impact of an identified risk in the project.

21
Q

Ordinal scales

A

A ranking approach that identifies and ranks the risks from very high to very unlikely or to some other value.

22
Q

Organizational risks

A

The performing organization can contribute to the project’s risk through unreasonable cost, time, and scope expectations; poor project prioritization; inadequate funding or the disruption of funding; and competition with other projects for internal resources.

23
Q

PESTLE

A

A prompt list used for risk identification. Examines political, economic, social, technological, legal, and environmental domains.

24
Q

Probability and impact matrix

A

A matrix that ranks the probability of a risk event occurring and its impact on the project if the event does happen; used in qualitative and quantitative risk analyses.

25
Q

Project management risks

A

These risks deal with faults in the management of the project: the unsuccessful allocation of time, resources, and scheduling; unacceptable work results; and poor project management.

26
Q

Pure risks

A

These risks have only a negative outcome. Examples include loss of life or limb, fire, theft, etc.

27
Q

Qualitative risk analysis

A

This approach qualifies the risks that have been identified in the project. Specifically qualitative risk analysis examines and prioritizes risks based on their probability of occurring and their impact on the project should they occur.

28
Q

RAG rating

A

An ordinal scale that uses red, amber, and green (RAG) to capture the probability, impact, and risk score.

29
Q

Residual risks

A

Risks that are expected to remain after a risk response.

30
Q

Risk

A

an uncertain event or condition that can have a positive or negative impact on the project.

31
Q

Risk identification

A

The systematic process of combing through the project, the project plan, the work breakdown structure, and all supporting documentation to identify as many risk that may affect the project as possible.

32
Q

Risk management plan

A

A project management subsidiary plan that defines how risks will be identified, analyzed, responded to, and monitored within the project. The plan also defines the iterative risk management process that the project is expected to adhere to.

33
Q

Risk management planning

A

The agreed-upon approach to the management of the project risk processes.

34
Q

Risk owners

A

The individuals or entities that are responsible for monitoring and responding to an identified risk within the project.

35
Q

Risk register

A

The risk register is a project plan component that contains all of the information related to the risk management activities. It’s updated as risk management activities are conducted to reflect the status, progress, and nature of the project risks.

36
Q

Risk report

A

The risk report explains the overall project risks and provides summaries about the individual project risks.

37
Q

Risk response audit

A

An audit to test the validity of the established risk responses.

38
Q

Risk responsibilities

A

The level of ownership an individual or entity has over a project risk.

39
Q

Risk score

A

The calculated score based on each risk’s probability and impact. The approach can be used in both qualitative and quantitative risk analysis.

40
Q

Secondary risks

A

New risks that are created as a result of a risk response.

41
Q

Sensitivity analysis

A

A quantitative risk analysis tool that examines each risk to determine which one has the largest impact on the project’s success.

42
Q

Sharing

A

A risk response that shares the advantages of a positive risk within a project.

43
Q

SWOT analysis

A

SWOT analysis is the process of examining the project from the perspective of each characteristic: strengths, weaknesses, opportunities, and threats.

44
Q

TECOP

A

A prompt list used in risk identification to examine the technical, environmental, commercial, operational, and political factors of the project.

45
Q

Technical, quality, or performance risks

A

Technical risks are associated with new, unproven, or complex technologies being used on the project. Changes to the technology during the project implementation can also be a risk. Quality risks are the levels set for expectations of impractical quality and performance.

46
Q

Transference

A

A risk response that transfers the ownership of the risk to another party.

47
Q

Variability risks

A

A type of risk based on the variations that may occur in the project, such as production, number of quality errors, or even the weather.

48
Q

VUCA

A

A prompt list used in risk identification that examines the volatility, uncertainty, complexity, and ambiguity of risk factors within the project.