Project Procurement Management Terms Flashcards

1
Q

Alternative dispute resolution

A

When there is an issue or claim that must
be settled before the contract can be
closed, the parties involved in the issue
or claim will try to reach a settlement
through mediation or arbitration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bid

A

From seller to buyer. Price is the
determining factor in the decision-making
process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Bidder conference

A

A meeting of all the project’s potential
vendors to clarify the contract statement
of work and the details of the contracted
work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Claims

A
These are disagreements between the
buyer and the seller, usually centering on
a change, who did the change, and even
whether a change has occurred. Claims
are also called disputes and appeals, and
are monitored and controlled through the
project in accordance with the contract
terms.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Contract change control system

A
This defines the procedures for how the
contract may be changed. The process
for changing the contract includes the
forms; documented communications;
tracking; conditions within the project,
business, or marketplace that justify the
needed change; dispute resolution
procedures; and the procedures for
getting the changes approved within the
performing organization.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Contract statement of work (SOW also

CSOW)

A
This document requires that the seller
fully describe the work to be completed
and/or the product to be supplied. The
SOW becomes part of the contract
between the buyer and the seller.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Cost plus award fee contract

A

A contract that pays the vendor all costs
for the project, but also includes a buyerdetermined award fee for the project
work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost plus fixed fee contract

A
A contract that requires the buyer to pay
for the cost of the goods and services
procured plus a fixed fee for the
contracted work. The buyer assumes the
risk of a cost overrun
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Cost plus incentive fee

A

A contract type that requires the buyer to
pay a cost for the procured work, plus an
incentive fee, or a bonus, for the work if
terms and conditions are met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost plus percentage of costs

A
A contract that requires the buyer to pay
for the costs of the goods and services
procured plus a percentage of the costs.
The buyer assumes all of the risks for
cost overruns.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Direct costs

A

These are costs incurred by the project in
order for the project to exist. Examples
include the equipment needed to
complete the project work, salaries of the
project team, and other expenses tied
directly to the project’s existence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Fixed-price contracts

A

Also known as firm fixed-price and lumpsum contracts, these are agreements that
define a total price for the product the
seller is to provide.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Fixed-price incentive fee

A

A fixed-price contract with opportunities
for bonuses for meeting goals on costs,
schedule, and other objectives. These
contracts usually have a price ceiling for
costs and associated bonuses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Fixed-price with economic price

adjustments

A

A fixed-price contract with a special
allowance for price increases based on
economic reasons such as inflation or the
cost of raw materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Force majeure

A

An “act of God” that may have a negative
impact on the project. Examples include
fire, hurricanes, tornadoes, and
earthquakes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Independent estimates

A

These estimates are often referred to as
“should cost” estimates. They are created
by the performing organization or outside
experts to predict what the cost of the
procured product should be.

17
Q

Indirect costs

A

These are costs attributed to the cost of
doing business. Examples include
utilities, office space, and other overhead
costs.

18
Q

Invitation for Bid (IFB)

A

From buyer to seller. Requests the seller
to provide a price for the procured
product or service.

19
Q

Letter contract

A

A letter contract allows the vendor to
begin working on the project immediately.
It is often used as a stopgap solution.

20
Q

Letter of intent

A

A letter of intent is not a contract, but a
letter stating that the buyer is intending to
create a contractual relationship with the
seller.

21
Q

Make-or-buy decision

A

A process in which the project
management team determines the costeffectiveness, benefits, and feasibility of
making a product or buying it from a
vendor.

22
Q

Privity

A

The contractual relationship between the
buyer and the seller is often considered
confidential and secret.

23
Q

Procurement management plan

A

A project management subsidiary plan
that documents the decisions made in the
procurement planning processes.

24
Q

Procurement planning

A

A process to identify which parts of the
project warrant procurement from a
vendor by the buyer.

25
Q

Proposal

A

A document the seller provides to the
buyer. The proposal includes more than
just a fee for the proposed work. It also
includes information on the vendor’s
skills, the vendor’s reputation, and ideas
on how the vendor can complete the
contracted work for the buyer.

26
Q

Purchase order (PO)

A
A purchase order is a form of unilateral
contract that the buyer provides to the
vendor showing that the purchase has
been approved by the buyer’s
organization.
27
Q

Quotation

A

From seller to buyer. Price is the
determining factor in the decision-making
process.

28
Q

Request for Proposal (RFP)

A

From buyer to seller. Requests the seller
to provide a proposal to complete the
procured work or to provide the procured
product.

29
Q

Request for Quote (RFQ)

A

From buyer to seller. Requests the seller
to provide a price for the procured
product or service

30
Q

Risk-related contractual agreements

A
When the project management team
decides to use transference to respond to
a risk, a risk-related contractual
agreement is created between the buyer
and the seller
31
Q

Screening system

A

A tool that filters or screens out vendors

that don’t qualify for the contract.

32
Q

Seller rating systems

A
These are used by organizations to rate
prior experience with each vendor that
they have worked with in the past. The
seller rating system can track
performance, quality ratings, delivery,
and even contract compliance.
33
Q

Terms of Reference

A

Defines the obligations for the seller,
what the seller will provide, and all of the
particulars of the contracted work. Terms
of reference is similar to the statement of
work.

34
Q

Time and materials contract

A
A contract type in which the buyer pays
for the time and materials for the
procured work. This is a simple contract,
usually for smaller procurement
conditions. These contract types require
a not-to-exceed clause, or the buyer
assumes the risk for cost overruns.
35
Q

Weighting system

A

This takes out the personal preferences
of the decision maker in the organization
to ensure that the best seller is awarded
the contract. Weights are assigned to the
values of the proposals, and each
proposal is scored.