Project Planning Flashcards

1
Q

What is project planning?

A
  • Breaking down the work into parts and assign these to project team members
  • Anticipate problems that might arise and prepare tentative solutions to those problems.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is project scheduling (3 points)

A

How to organize the project in tasks - how and when they will be executed.

Estimate calendar time needed

Estimate resources needed to complete each task.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the activities of project scheduling

A

Split project into tasks

Organize tasks

Minimize task dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the components of project activities (tasks)?

A

A duration (days/months)
An effort estimate (persondays)
deadline
defined end-point (successful tests, etc)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Milestones vs deliverables

A

Milestones are points in the schedule against which you can assess progress
Deliverables: work products delivered to the customer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is work breakdown structure

A

hierarchical tree struscture of deliverables and tasks that need to be performed to complete a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does WBS contain?

A

A description of all significant work.

A clear task decomposition for assignment of responsibilities.

A framework for scheduling, budgeting, and expenditure tracking.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the two main ways to organize the representation of work?

A

By functional responsibilities.

According to life-cycle phases, showing each phase as a top-level breakdown.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a Gantt chart

A

A timeline chart (also called a Gantt chart) is a horizontal bar chart which helps to plan, coordinate, and track specific tasks in a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Finish to start (FS)

A

Task B cannot start until task A finishes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Start to start (SS)

A

Task B cannot start until A starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Finish to finish (FF)

A

task b cannot finsih until task a finishes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Start To finish

A

task B cannot finish until A starts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Steps in building an activity on node network

A

Identify the specific activities and their duration.
How many days it takes to finish an activity (task)

Determine the proper sequence of the activities.

Construct a network diagram.

Estimate the time required for each activity.
Earliest start/finish and latest start/finish.

Determine the critical path.

Update the graph as the project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is identifying activities (Node Network)

A

This consists in identifying the activities that are required to complete the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is determining the activity sequence (Node Network)

A

This is determinitng the order of the activities, this is usually paired with the identification process; some others will require more analysis to figure out order

17
Q

Construct the network diagram.

A

This means showing the sequence of serial and parallel activities.

18
Q

Estimate time required for activities

A

commonly used unit of time for activity completion, but any consistent measure is fine

19
Q

The 4 types of time quantities for an activity

A

Earliest start time (ES)

Earliest finish time (EF)

Latest start (LS)

Latest finish (LF)

20
Q

What is earliest start time

A

The earlierst time at whcih teh eactivity can start given that its precedent activities must be completed first.

21
Q

Earliest finish time (EF)

A

Equal to the earliest start time for the activity plus the time required to complete the activity.

22
Q

Latest start time (LS)

A

Equal to the latest finish time minus the time required to complete the activity

23
Q

What is latest finish time (LF)

A

The latest time at which the activity can be completed without delaying the project.

24
Q

What is the forward pass rule

A

Used to determine earliest times:

Earliest start date for the current activity = earliest finish date for the previous

When there is more than one previous activity, take the latest earliest finish

25
Q

What is the backward pass

A

Used to determining the latest times

The latest start and finish times are the latest times that an activity can start and finish without delaying the project.

Start from the last activity:

Latest finish (LF) for last activity = earliest finish (EF).

Work backwards:

Latest finish (LF) for current activity = Latest start for the following
More than one following activity - take the earliest LS.

Latest start (LS) = LF for activity – duration.

26
Q

What is a float

A

The difference between the earliest start date (ES) and the latest start date (LS).

Float is a measure of how much the start or completion of an activity may be delayed without affecting the end date of the project.

zero float means it’s critical - any delay will affect completion of entire project