Project Management (Overview) Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

The primary job of a project manager is to complete the project according to its specifications:

a: Within budget
b: On Schedule
c: With the expected degree of quality
d: All of the above

A

d: All of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

True or False. The critical path schedule shows how the tasks on the schedule are inter-related.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

By preparing a ________________ project managers will better understand the cash needed at the intervals that the monies will be disbursed.

a: Preliminary cash flow schedule
b: Budget
c: Tracking schedule
d: None of the above

A

a: Preliminary cash flow schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

True or False. Quality of construction should be addressed in the specifications. Companies that are bidding can take these expectations into consideration when they are doing their estimates.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Adding __________time is a method of alotting more time in the project schedule to account for unforeseen delays.

a: Uncertainty
b: Chance happening
c: Contingency
d: Extra

A

c: Contingency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

True or False. A critical path schedule will be developed by the use of a calendar.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Project managers rely on information provided by ____________to effectively schedule their projects:

a Subcontractors
b: Records of similar past projects
c: Expediters
d: Both a & b

A

d: Both a & b

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

For a small construction company, who would typically be the project manager?

a: Prime contractor (general contractor)
b: Superintendent
c: Architects
d: None of the above

A

a: Prime contractor (general contractor)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

In order to schedule time slots for all of the individual tasks involved in completing a project, first we need to identify each ______________.

a: Subcontractor
b: Phase of the project
c: Task
d: All of the above

A

c: Task

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A major benefit of the critical path method of scheduling is it shows how one project task will be dependent on the completion of other tasks that come before it in a ________________.

a: Logical sequence
b: Building project
c: Orderly fashion
d: Descending order

A

a: Logical sequence

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

This chart graphs the starting and finishing times for individual tasks that make up the project.

a: Bar chart
b: Gantt chart
c: Duration chart
d: Either A or B

A

d: Either A or B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

True or False. Contingency time is providing extra time in the schedule for unforeseen delays.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When using subcontractors, be sure to clearly describe the level of quality expected in their job specifications, this will help them _____ the job accordingly.

a: Bid
b: Understand
c: Plan
d: Track

A

a: Bid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

True or False. A permit to build a home could still be granted if the building department doesn’t receive the prints, plans and specifications.

Note: The building official is given the power to grant a permit when drawings are not necessary. But that would never include a project like building a house!

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The overall direction of the project is the responsibility of the _____________.

a: Project coordinator
b: Home owner
c: Financial advisor
d: Project manager

A

d: Project manager

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

When two contracting firms unite their forces to construct a project it is called a:

Note: Some states even require that joint ventures purchase an additional license.

a: Partnership
b: Merger
c: Conglomerate
d: Joint venture

A

d: Joint venture

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

In a residential building project by a contractor, to whom is the building permit issued?

a: Home owner
b: General contractor
c: Superintendent
d: Any of the above

A

b: General contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The _________ method is an analysis that provides a diagram that depicts the longest continuous sequence of activities in a project, determining the overall amount of time to complete a project.

a: Bar Chart
b: Gantt Chart
c: Critical Path
d: Calendar Scheduling

A

c: Critical Path

19
Q

______________ is a form of managing tasks that is best for simple, less complicated projects. It enables the contractor to link specific tasks to a date, manage deliveries, payments and employment schedules in a very simple, straightforward way.

a: Gantt Charting
b: Critical Path method
c: Calendar scheduling
d: Queue scheduling

A

c: Calendar scheduling

20
Q

The _________ is responsible for all work phases and coordination of work.

a: Contractor
b: Superintendent
c: Expediter
d: Project manager

A

d: Project manager

21
Q

Which is NOT true about project scheduling?

a: A bad project schedule can result in contractors not knowing when to do their work.
b: Improper scheduling may increase total job time
c: Project schedule are only required on major projects
d: If a project schedule is too general or too detailed, it can be unusable

A

c: Project schedule are only required on major projects

22
Q

True or False. Quality of construction, materials and work methods should be addressed in the specifications. Companies that are bidding can take these expectations into consideration when they are doing their estimates.

A

True

23
Q

Adding __________time is a method of allotting more time in the project schedule to account for unforeseen delays.

a: Uncertainty
b: Chance Happening
c: Extra
d: Contingency

A

d: Contingency

24
Q

Project managers rely on information provided by ____________to effectively schedule their projects:

a: Subcontractors
b: Records of similar past projects
c: Expediters
d: Both A and B

A

d: Both A and B

25
Q

When the project is nearing completion, a ________________is created during a walk through to determine any details that still need to be addressed in order to fully complete the project.

a: Punch List
b: Job Sheet
c: Detail Survey
d: Final Report

A

a: Punch List

26
Q

What are the steps involved in closing out each project?

a: Onsite walk-through to develop a punch list
b: Contractor/architect provide certificate
c: Owner makes final payment
d: All of the above

A

d: All of the above

27
Q

This chart graphs the starting and finishing times for individual tasks that make up the project.

a: Bar Chart
b: Gantt Chart
c: Duration Chart
d: Either A or B

A

d: Either A or B

28
Q

In a construction project, _________ time is the amount of time that a task in a project network or path can be delayed without causing a delay to other, subsequent tasks or to the overall completion date.

a: Contingency
b: Float
c: Duration
d: Flex

A

b: Float

29
Q

_______________ is a procedure that analyzes the requirements of a project and determines how best to decrease costs, increase profits, improve quality and performance, and enhance customer satisfaction.

a: Construction Analysis
b: Quality Assurance
c: Cost Coding
d: Value Engineering

A

d: Value Engineering

30
Q

What helps with keeping track of a job’s expenses?

A

Purchase Orders

31
Q

What is the difference between FOB Freight Prepaid and FOB Freight Allowed?

A

Prepaid: Requires the seller to pay for all shipping charges
Allowed: Requires the buyer to pay for shipping

32
Q

What are the 5 main discounts provided to contractors for early payment of bills?

A

Net 10: Payment is due 10 days after receiving the invoice
1/10 Net 30: 1% discount if paid within 10 days; otherwise the entire amount is due within 30 days.
1/10 EOM: 1% discount if paid by the 10th fay of the month after the purchases are shipped.
COD: Cash on Delivery
EOM: Payment due at the end of the month.

33
Q

What can negative cash flow lead to?

A
  • An increased need to borrow money
  • Paying subs and suppliers late
  • Dipping into lines of credit
  • Missing tax deadlines
  • Inability to cover multiple projects at one time
  • Taking money from resources that could otherwise be used to grow the company
34
Q

What are Cost Codes used for?

A

To monitor and evaluate a contractor’s costs during the course of a construction project. They are assigned to specific job categories, such as supervision, clean-up, labor/materials and project general conditions.

35
Q

What is Value Engineering?

A

A procedure that analyzes the requirements of a project and determines how best to decrease costs, increase profits, improve quality and performance, and enhance customer satisfaction.
It helps to balance function, performance, quality, safety and cost, providing maximum value for the project.

36
Q

True or False. Subcontractors also have a contract with the owner.

A

False. Only you do, make sure you can rely on their work.

37
Q

What is Calendar Scheduling?

A

A form of managing tasks that is best for simple, less complicated projects. It allows you to link specific tasks to a date, to manage deliveries, payments, employment schedules etc. All in a simple calendar.

38
Q

What is a Bar Chart or Gantt Chart?

A

Using this chart, you can show starting dates through completion of all phases of work and how they may overlap. This schedule will be reviewed at each progress meeting, the goal being to keep everyone on course.

39
Q

What is a Critical Path Schedule?

A

A logical sequence of activities within a project that have the longest duration times, allowing you to project the earliest completion date.
This is more elaborate and detailed than a bar chart.

40
Q

What is Q Scheduling?

A

This is the newest scheduling technique, no interference between any two activities is allowed at the same location. Trades pass through the different segments of the project in a sequence.

41
Q

What is Contingency Time

A

Providing extra time in the schedule for unforeseen delays.

42
Q

What is Float Time?

A

The time that occurs in between one task and its relation to the next.
EX: Task A has a duration of 6 days and is happening at the same time as Task B, which has a duration of 9 days. This means Task A has float time of 3 days in which to finish any outstanding work.

43
Q

What are the 12 Formal Steps for Close out?

A
  1. The contractor submits formal notice to the architect and the owner that the construction project is substantially complete.
  2. Based on his observation and discussions with the contractor, the architect documents substantial completion with the owner and the contractor. This may activate certain warranties, depending on the terms of the contract
  3. If the project was a phased one, often the architect and owner will sign off on certain building systems being substantially complete. Be sure this is clearly documented since start dates for warranties and guarantees may vary.
  4. The owner and architect make an on-site walk-through punch list noting any necessary corrections. The contractor makes the corrections noted on the punch list, and upon acceptance by the owner, the architect will issue a certificate of completion to the contractor with a copy to the owner. This officially documents that the terms of the contract have been met by the contractor.
  5. The contractor documents and delivers all keys, record drawings, as-built drawings, testing and balancing reports, and any other documents required by the contract.
  6. The contractor submits all guarantees, warranties, certificates, and bonds required by the contract.
  7. All operation and maintenance manuals are sent to the owner.
  8. The final payment request, including approved and signed change orders, is submitted by the contractor as a final accounting of the project.
  9. All final lien waivers and affidavits are submitted. The contractor must show the owner that all invoices from subcontractors and material suppliers have been paid.
  10. The architect sends a final certificate of payment to the owner; a copy also goes to the contractor.
  11. The contractor provides the certificate of occupancy that indicates that building officials have approved the structure for use.
  12. The owner makes final payments to the contractor and notifies the architect.