Project Management Framework & Processes Part 2 Flashcards
- many Projects may be spawned
- Cost and staffing levels are low at the start, peak in the intermediate phases and drop rapidly as the project closes
Product’s Life Cycle
- depends on the industry
- IT: Requirement Analysis, Design, Implementation, Testing and Deployment
Construction: Feasibility, Planning, Design, Production, Turnover and Startup
Project Life Cycle
plan - do - act - check
Project Management Processes
Process Groups
- Initiating Process Group
- Planning Process Group
- Executing Process Group
- Monitoring and Controlling Process Group
-Closing Process Group
Knowledge Areas
- Project Integration Management
- Project Scope Management
- Project Schedule Management
- Project Cost Management
- Project Quality Management
- Project Resource Management
- Project Communications Management
- Project Risk Management
- Project Procurement Management
- Project Stakeholder Management
Initiate project for planning
Provide Project Charter (which gives authority to the Project
Manager)
Intiating
Complete the project work as per the PM plan
Executing
Measure project performance against the PM plan
Monitoring and Controlling
Do formal closure of project
Includes Product verification
Documenting Lessons Learned is also required
Closing
A detailed project schedule can be created only after
creating the:
a. Project budget
b. Work breakdown structure
c. Project management plan
d. Detailed risk assessment
b. Work breakdown structure