Project Management Flashcards

1
Q

AIA B101 Initial Information

A
Project objective 
Site information
Owner’s program
Physical, legal, financial, time parameters
Key personnel 

It is noted that this information may change

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

AIA B101 Article 2

A

Architect’s Responsibilities

Standard of care
Insurance requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AIA B101 Article 3

A

Basic Services

Coordinate with owner’s consultants
Prepare a schedule of architectural services for approval including expected dates for start of construction and substantial completion- time limits can’t be exceeded by owner without reasonable cause
Administer the project
Prepare and keep project schedule
Consider alternatives
Present and submit documentation to owner
Evaluate budget and cost of work (preliminary estimate- only contractor can guarantee prices)
Design services
Construction procurement services
Contract administration services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Architect construction procurement services

A

Assist owner in obtaining bids or negotiated proposals
Assist in awarding contract and preparing contracts
Produce bidding documents, hold bid meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Architect contract administration services

A

Site visits
Keep owner informed of progress and defects
Not responsible for exhaustive or continuous inspections
Not responsible for means of construction, building techniques or safety precautions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

AIA B101 Owner Responsibilities

A

Provide architect with info about program, schedule and budget
Furnish land surveys
Geotechnical services
Tests, inspections and reports required by law
All legal, insurance and accounting services needed for the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Architect responsibilities re budget

A

Architect shall without additional compensation modify documents as necessary to comply with budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Instruments of service

A

Drawings specifications and documents owned and authored by architect and architects consultants

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Waiver of consequential damage

A

Limits claims to damages resulting from a breach of the agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Hazardous materials

A

Architect and architects consultants have no responsibility for discovery, handling, removing hazardous materials or exposure of persons to them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Third party claims

A

Privity- nothing in contract gives rights to sue or enforce to anyone other than those who are parties to the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Waiver of rights

A

Same as waiver of subrogation

Owner and architect can’t sue each other for damages covered by insurance and insurance companies can’t sue parties in the project to recover paid insurance loss

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Right to photograph

A

Architect has right to photograph the project unless owner has notified architect it is confidential- otherwise owner must give reasonable access for photography

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Termination

A

Either party can terminate with 7 days notice if other party substantially fails to meet agreement
Owner may terminate for convenience with 7 days written notice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Cost of work

A

Cost of labor and materials plus allowance for overhead and profit

Does not include professional fees, land costs, financing costs or other that are responsibility of owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Additional services that can be added to agreement

A
Programming
Site eval and planning 
Value analysis with owner consultant
Historic preservation 
Security planning
CA when a different architect is designer 
Facility support
Commissioning 
Regional planning
LEED certification
Interior design
FFE design
17
Q

Add services not in agreement

A

architect should not begin without authorization:

Making changes to initial information from owner
Making changes to project
Fulfilling owner request for extensive sustainable alternatives or certification
Making changes required due to changes in law or code
Preparing digital data for transmission to owner consultants and contractors
Design or documentation for alternate bid or proposal requests
Architect should not begin with it authorization:
Preparing for and attending public meetings/hearings
Preparing for and attending dispute resolution unless architect is a party
Evaluating bidders
Providing consultation about replacement of work due to fire or other cause during construction
Assisting initial decision maker unless it is the architect
Any service necessary due to owner failure to make timely decision or other failure by owner or owner consultant

18
Q

Add services to avoid delay in construction

A

architect should begin and notify owner promptly:

Reviewing submittal out of sequence
Responding to RFIs that aren’t compliant with spec or could be answered with available info
Preparing change orders that require evaluation of contractors proposals
Evaluating extensive numbers of claims
Evaluating substitutions
Providing construction services 60 or more days after expected date of substantial completion

19
Q

Liquidated damages

A

Fees paid by contractor to owner for every day project is late- except due to uncontrollable circumstances

20
Q

Definition of work

A

Contractor’s obligation to make improvements to the project

21
Q

Definition of project

A

The work plus construction by other contractors

22
Q

Instruments of service

A

Tangible and intangible creative work of the architect and architect’s consultants

23
Q

AIA A201 contractor responsibilities

A
Warranty of materials and workmanship 
Permits fees and taxes 
Concealed or unknown conditions- must notify owner within 21 days
Providing construction schedule, keeping it up to date and confirming with it 
Maintain record documents at job site
Submittals
Delayed design 
Indemnification
24
Q

AIA A201 Architect responsibilities

A

Site visits
Rejecting work that doesn’t confirm with contract documents- however this doesn’t create a duty or responsibility
If something is wrong or architect observes a safety problem architect should notify both contractor and owner
Responsible for shop drawings and submittals conformance to cds but contractor responsible for accuracy completeness and coordination of work
Architect prepares change orders
Final decisions about aesthetic issues as long as they are consistent with CD intent

25
Q

Change order

A

Written by architect signed by owner, contractor and architect
States extent of change and how it affects cost and schedule

26
Q

Construction change directive

A

Agreement between owner and architect - does not require contractor agreement
Change order is issued after contractor provides info about changes in cost and schedule

27
Q

Minor change in work

A

Ordered by architect alone where change is consistent with cds and doesn’t affect budget or schedule

28
Q

Mechanics lien

A

Claim by one party against property of another for satisfaction of a debt

29
Q

Surety bond

A

Also contract bond

Agreement among three parties - surety agrees to be responsible to obligée (owner) for default of principal (contractor)

30
Q

Termination or suspension of project

A

Contractor may terminate if work has stopped for more than 30 days through no fault of contractor or contractor’s subcontractors for
Court order
Act of government
Architects failure to certify payment or give a reason for not doing so
Owners failure to pay
Owners failure to give evidence that financial arrangements have been made to fulfill obligations
Work has been delayed for 120 days over 365 day period

Owner may terminate for convenience

31
Q

Consequential damages

A

Owner and contractor agree to waive

Owner:
Rental expenses
Loss of use, income, profit
Loss of productivity

Contractor:
Expenses in running office
Loss of financing or business
Loss of profit other than profit from work