Project Management Flashcards
What is a PMP?
Project Management Plan
What does a PMP consist of?
Safety Management Plan Quality Management Plan Resource Management Plan Communication Management Plan Environmental Management Plan
Subcontractor Selection Process
PART 1
1- Break works down into trades
2- Prepare Scope of works
3- Ascertain budget & schedule constraints
4- Select potential contractors based on selection strategy
Experience,
Feedback,
Resources: finance& facilities,
Workload & location,
Insurances/licences adequate & date
Subcontractor Selection Process
PART 2
5- Forward request for proposal/quotation
6- Organise time to meet with subcontractors to ask questions
7- Receive quotes
8- Select contractor
9- Obtain all insurances and licences are adequate and up-to date
10- Organise access and completion dates (PP)
11- Inform of power to issue instructions & form of communication
12- Organise toolbox meeting
13- Brief them on site safety issues
14- Conduct a site induction with all subcontractors