Project Management 5.0 Flashcards

1
Q

When should an Architect use full disclosure?

A

When the Architect is compensated or has an economic interest in the issue. (The Architect should never accept compensation from more than one party, which is a conflict of interest, and the Architect should render decisions impartially when acting as the judge of contract performance. There is no requirement for fully disclosing why you give up a commission, but the Architect does need to fully disclose if they have a personal economic interest in a situation.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are phases in a typical work plan

A

-Plan -Do -Check -Adjust

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A CPM schedule is developed, but after four weeks the contractor encounters major unforeseen conditions. The CPM was supposed to be 400 days, and the float time is 50 days. The unforeseen conditions will cause a 20-day delay in the critical activities path. Will the project be late, and if so, by how many days?

A

Yes, there will be a 20-day delay. (The float time for a CPM schedule is the number of days that a project can “lose” for non-critical activities. The question states that 20 days will be lost to critical activities; therefore, the project will be delayed by 20 days.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

An architect has been asked to recommend a schedule for an upcoming project. The complex project will have a series of interdependent activities and a need to overlay the architect’s scope of services and the timing of contract administration duties into the schedule. Which schedule is the architect most likely to recommend?

A

Critical Path Method (CPM) is the most likely choice in this scenario. CPM schedules are regularly used for large, complex projects and often incorporate the architect’s scope of services and timing of contract administration duties.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is included in an Architect’s minimum construction contract administration services?

A
  • Reporting to the building officials - Reporting to the owner - Shop drawing review - Periodic site visits ( The architect must report to the owner and building official whenever code violations od deviations from the contract documents are observed.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

An architect serving as a project manager for a large project has implemented a schedule in order to keep all parties on track. The architect has received feedback that deadlines have been missed and important information is not appearing in the schedule. What is most likely the reason for the issue?

A

The architect implemented a milestone chart. ( A milestone chart is a great choice for small projects, but it does not provide enough detail to manage a large project.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Prime Agreement

A

Pre-existing owner/ Architect Agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Contracts

A201-2017

A

General Conditions of the Contract for Construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Contracts

C401-2017

A

Standard Form of Agreement Between the Architect and the Consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why the initial information in owner/architect agreements should not be skipped?

A

It is a critical part and the very foundation of the owner/architect agreement. For architects, it can be a tool to teach owners about the design and construction process. For owners, it can be a useful checklist of information they need to provide, and decisions they need to make, that will impact the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Contracts

B101-2017, Article 1

A

Helps to establish the parties’ expectations on the project, and provides a convenient checklist of items the parties should agree upon before executing the agreement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What prompts are included for the parties to insert on the B101-2017?

A

On the B101-2017 the Standard Form of Agreement Between the Owner and Architect, the following includes prompts for the parties to insert: - Information about the owner’s program - The project’s physical characteristics - Representatives of the parties - The owner’s budget - The intended delivery method for the project - Milestone dates for the project - The owner’s sustainable objectives - Consultants to be retained by each party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What prompts are included for the parties to insert on the B101-2017?

A

On the B101-2017 the Standard Form of Agreement Between the Owner and Architect, the following prompts are included for the parties to insert: - Information about the owner’s program - The project’s physical characteristics - Representatives of the parties - The owner’s budget - The intended delivery method for the project - Milestone dates for the project - The owner’s sustainable objectives -Consultants to be retained by each party

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the architect’s obligation to design to budget?

A

The first place to look at is the contract. AIA Contract Documents address this issue in two ways: - AIA Document B101-2017 Standard Form of Agreement Between the Owner/ Architect -AIA Document B103-2017 Standard Form of Agreement Between the Owner/ Architect for a Complex Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Under the terms of B101, the architect is the person best suited to keep the design within the owner’s budget. Why is that the case?

A
  • The architect is responsible for managing the design to meet the budget - The owner has the right to rely upon the architect’s conceptual cost estimating - The architect has considerable freedom in the design process to manage the design to achieve the owner’s budgetary goals ( The key section in the contract regarding this process is Section 6.3)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Contracts

B103-2017

A

Standard Form of Agreement Between the Owner and Architect for a Complex Project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How does B103 approach the budget?

A

In B103, the architect has the right to rely upon the estimate provided by the owner’s cost estimator, and the architect will be paid additional compensation to make changes, due to inaccuracies or incompleteness in those estimates or market conditions the architect could not reasonably anticipate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Designing to Budget

A

Is a process of managing the project cost to stay within the client’s budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

On B101 the “ designing to budget” process anticipates…

A

… that the architect will consult with the owner regarding program, budget, and schedule; - Provide conceptual estimates of construction cost - Design with the intent to stay within budget - Update the estimates as the design progresses and inform the owner of variances from the budget - Obtain the owner’s approval of the design at each phase before moving on to the next one.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

At the conclusion of the construction documents phase, if the lowest qualified bid is over the owner’s budget the owner may—among other possible remedies—require the architect, at …

A

… no additional charge, to perform redesign services to bring the cost within the budget. (B101-2017 Section 6.7) But if price increases due to market conditions the architect could not reasonably anticipate, then the architect will be paid to make changes to meet the budget as an additional service.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Spearin Doctrine

A

The gap between the Standard of Care and defect-free documents. Costs associated with the Spearin Doctrine are borne by the owner, as the architect developed them in accordance with the standard of care and not as a result of negligence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Scope Creep

A

Occurs when a project’s original scope is stretched or expanded by ambiguities, events, or conduct.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Why should an architecture firm have a quality control program?

A

-To ensure the client’s expectations are met -To ensure the standard of care for professional practice is provided - To reduce liability and risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Contingencies

A

Are intended to cover unforeseen events and should be included in fee planning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Peer reviews

A

A process during which a firm subjects its architectural work to the scrutiny of experts in similar building types. Experts come from outside of the firm itself, which contributes to the objectivity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Remedial Charrettes

A

Is a collaborative process during which the original kickoff team corrects quality problems and identifies corrective action

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Components of a local comprehensive plan

A
  • Downtown - Land use - Housing - Community health
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Stipulated sum or Lump sum Method

A

Or fixed-price is a method for establishing the total construction cost of a project. It can represent a minimized risk to an owner because the owner knows the cost of services prior to beginning work on the design. This results in more accurate budgeting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Performance zoning

A

An approach to land use planning that is based on quantifiable performance standards that regulate the intensity of land use to prevent adverse impact on abutting and nearby properties. It is characterized by a development that can be evaluated based on measurable performance criteria, such as pollution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Benchmarking

A

A process used to estimate the performance of a project when compared to similar projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Net assignable area

A

The sum of all areas in a building assigned to, or available for assignment to, a specific use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are the elements of quality management in construction procurement?

A
  • Constant monitoring and documentation - Feedback for program improvement - Effective in-house protocols
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What are the practical ways to manage quality?

A
  • Encourage regular self-checking - Use peer reviews - Implement an in-house third-party review
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Project closeout checklist

A

Will ensure all project tasks are complete. Nothing should extend past closeout.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What is commonly included in a quality management program?

A
  • The program is strictly enforced - The program is consistently managed - The program is clearly defined
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What are most often alleged in claims against architects?

A
  • Negligence - Breach of contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Breach of contract

A

Change of scope can often result in a breach of contract. One of the parties to contract fails to perform as required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Benefits of quality management in post-construction?

A
  • Architect can leave a good impression. - Architect can make an appeal for future work. - Architect can provide responsive support as needed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

Appraisal Costs

A

Costs associated with measuring and monitoring activities related to quality. These costs are with the supplier and customer’s evaluation of purchased materials, products, and services to ensure that they conform to specs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Fast-Track Delivery Method

A

When the overall time for design and construction must be compressed. In this method, the construction process is allowed to begin before the design process is completed.

Fast-track construction requires many prime contracts and a great deal of coordination, but it can reduce the time and cost of a project substantially.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Integrated Project Delivery Method

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Design-Bid-Build Method

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Design-Build Method

A
44
Q

Guaranteed maximum price (GMP)

A
45
Q

Methods for establishing the total construction cost of a project

A
  • Fixed-price method (Stipulated sum or Lump sum)
  • Cost-plus-fee with a GMP
  • Cost-plus-fee without a GMP
46
Q

RFP

A

Request For Proposal

47
Q

Addenda

A

Only used during the bidding and negotiation phase.

48
Q

Construction Change Directives

A

When a change needs to be made right away to allow the project to proceed, but the owner and contractor cannot agree on a price or time revision, the architect can issue a construction change directive. (AIA Document G714)

It must be signed by both the owner and the architect but does not have to be signed by the contractor.

49
Q

AIA Document G714

A

Construction Change Directive

50
Q

Quality Control Techniques

A
  • Programming
  • Checklist
  • Process-Based Systems
  • Quality Management Meetings
  • Staffing
  • Quality Circles
  • Corporate Knowledge
51
Q

Project records include …

A
  • General Administration of the Project
  • Programming
  • Schematic Design
  • Design Development
  • Construction Documentation
  • Bidding and Negotiation
  • Construction Administration
  • Project Closeout and Follow-up
52
Q

What is the difference between additional service and supplemental service?

A

Supplemental services are services that are not included as basic services but are identified as the architect’s responsibility at the time the agreement is executed. Additional services are services that may arise as the project proceeds. (B101-2017 Owner-Architect Agreement)

53
Q

Substantial Completion

A

Is a legal term in construction contracts to define the stage of a contractor’s work that is sufficiently complete in accordance with the applicable construction agreement. ( It doesn’t mean that the project is completely done.)

54
Q

What does it implicate when the architect claims that the project is at “Substantial Completion”?

A
  • The client is allowed to move in
  • Occupancy must meet code
  • Warranties start
55
Q

RFI

A

Request For Information

56
Q

Punchlist

A

Is part of the project closeout portion of the construction process. It is a document prepared during key milestones or near the end of a project listing work that has not been completed or not conforming to contract specifications that the general contractor must complete prior to final payment.

57
Q

Change Orders

A

Can go all the way to the end of the project. It may happen when all the construction is done.

58
Q

Phase 1 Environmental Site Assessment (ESA)

A

A site visit to observe current and past conditions and uses of the property and adjacent properties. It is the introductory phase of investigating if there is a potential for environmental risk or contamination on a property that would affect its value and if additional investigation and testing are warranted. It is the owner’s responsibility to look after it and the architect is responsible to review, fully understand and respond to the reports provided by the owner.

59
Q

When an Architect is asked to put together a program …

A

The architect is asked to do the following:

  • Research and analysis
  • Assembling data, information, and goals

The architect is NOT:

Designing when asked to put a program together

60
Q

FAR

A

Floor Area Ratio

61
Q

What are the aspects of review for Zoning Code analysis?

A
  • FAR (Floor Area Ratio)
  • Setbacks
  • Parking
62
Q

Floor Area Ratio (FAR)

A
63
Q

Easements

A

A right which a person has over land owned by someone else. Easements are normally attached to the land rather than to a person and can be considered to last in perpetuity.

64
Q

Setbacks

A

Is the minimum distance which a building or other structure must be set back from a street or road, a river or other stream, shore, or flood plain, or any other place which is deemed to need protection.

65
Q

Metes and Bounds

A

An old type of survey.

Are the boundaries of a parcel of real estate identified by its natural landmarks. Are often used in a “legal description” of a land. The legal description is the geographical description of a land that identifies its precise location and is kept with the deed of the land.

66
Q

What is the first and second aspect of the process of establishing a Building Code Analysis?

A

First: Occupancy

Second: Construction Type

67
Q

Means and Methods of Construction

A

A term used to describe the techniques and tactics (usually temporary structures) a contractor employs to complete the construction of a permanent project or structure.

The way things are going to be built and the schedule in which they will be built

68
Q

Initial Budget Projections

A
69
Q

MEP

A

Mechanical, Electrical, and Plumbing

70
Q

Hourly Multiplier

A

x 3 - 4

sometimes

x 2.5 - 5.5

It can vary from state to state

71
Q

Mediation

A

A conference between opposing parties facilitated by a neutral, mutually agreed-upon mediator.

72
Q

AIA Document A101-2017

A

Owner and Contractor Agreement

Change orders could be due to the essence of the contract which is the following:

The Scope

The cost

The schedule

73
Q

IDM

A

Initial Decision Maker (part of the dispute resolution)

Is the person identified in the agreement to render initial decisions on claims in accordance with section 15.2 under the AIA’s General conditions

An initial decision is a condition precedent to mediation, and mediation is a condition precedent to any bidding form of dispute resolution.

74
Q

Lien

A

Is a claim made against a property by a contractor or subcontractor who has not been paid for work done on that property. Liens are designed to protect professionals from the risk of not being paid for services rendered.

75
Q
A
76
Q

Does the client have the copyright to the drawings?

A

The client has the right of use which is different than copyright unless it has been specified on the contract that the client has copyright.

77
Q

Bridge Loan

A

It allows a homeowner to borrow against the equity in their existing residential property in order to buy a new home.

78
Q

Zoning Variance

A

It allows the property owner to construct a building that goes against the physical requirements held within a zoning ordinance.

79
Q

What does float mean in construction management?

A

It is defined as a difference between the early start and late start of construction activity. It is a delay in time for a particular activity in construction, without affecting the deadline of completion of the project.

80
Q

Instruments of Service

A

In the AIA A201-2007 General Conditions, the document defines the various forms of work product prepared by the architect as “instrument of service”

They are defined as “representations, in any medium of expression now known or later developed, of the tangible and intangible creative work performed by the architect and the architect’s consultants under their respective professional services agreement. “

The design, documents, specifications, and reports are prepared by or on behalf of the prime consultant or consultants, including but not limited to plans, sketches, drawings, graphic representations, and computer-generated designs and materials.

81
Q

Retainage

A

Is the withholding of a portion of the funds that are due to a contractor or subcontractor until the construction project is finished. It is meant to serve as a financial incentive and an assurance that the contractor will complete the project in a satisfactory manner.

82
Q

Assemblies cost estimate

A

Is a sequential approach to estimating, which represents how the building is to be constructed. It is best used as a budgeting tool in the planning stages of a project because the accuracy of the estimate is typically plus or minus 15%.

83
Q

Arbitration

A

Is a process in which a dispute is submitted to an impartial outsider who makes a decision that is usually binding on both parties. The arbitrator enforces his own point of view on the contending parties and the opinions of the participants are not given any predominance.

84
Q

REPC

A
85
Q

Barrister Review

A

Lawyer Review

86
Q

Litigation

A

Involves the representation of stakeholders involved in a governmental, commercial, or residential construction project. Litigation attorneys typically prosecute or defend claims for professional negligence of design professionals ( both architects and engineers)

87
Q

Negligence

A

When an architect is unable to uphold the performance and safety standards outlined in their contract, developers can take legal action by either filling a claim for breach of contract or suing the architect for negligence.

88
Q

E and O insurance policy

A

Architect errors and omissions insurance is a professional liability. Is expensive insurance that protects design professional from claims related to mistakes that occur in the design, planning, and specifications stage of a construction project

89
Q

GL insurance policy

A

General Liability insurance is usually purchased by all of the parties in the construction process. it is designed to protect the insured party against liability arising out of direct bodily insured and property damage to third parties

90
Q

Pro Forma Documentation

A

Is the most important tool for developers. This malleable document calculates all the variables that go into putting a deal together with the intent of giving you the liability to make informed decisions regarding the project’s expected financial performance.

91
Q

Quality Assurance Plan

A

It is a plan carried out before the construction project starts. Is a process that manages for quality. It lists the processes, standards, and policies that need to be carried out and ensures they are known to the people who need to know them.

92
Q

Bid Bond

A

It is a type of construction bond that protects the owner or developer in a construction bidding process. It is a guarantee that you, as the bidder, provide to the project owner to ensure that if you fail to honor the terms of the bid, the owner will be compensated.

93
Q

Performance Bond

A

Is a third-party agreement involving the contractor, the owner, and the bonding company that guarantees the completion of a construction project in accordance with the contract documents. It is usually provided by an insurance company to make sure a contractor completes designated projects.

94
Q

P and L

A

Profit and Loss is the budget for a construction business and shows the income (or revenue) you have received or will receive and the expenses you have spent or will spend over a period of time.

95
Q

Cash Flow Report

A

Is an analysis of all the cash that came in and went out for a given period and shows how much money you actually have on hand at a certain point in time.

96
Q

RFP

A

Request for Proposal

97
Q

RFS

A

Request For Services

98
Q

RFQ

A

Request For Qualification

99
Q

Feasibility Study

A

It is a study that considers the critical aspects of your proposed project. It allows us to test the viability of the project before undertaking any really significant expense. It attempts to answer the big questions early in the decision-making process.

100
Q

Cost Plus Fee Contract

A

It is a type of contract in which the actual cost to build your project plus a management and coordination fee for the general contractor. The management and coordination fees are generally a predetermined percentage of the actual costs. Unlike the Fixed-cost, in the Cost Plus contract, the owner pays the contractor the actual costs of the materials and labor plus an additional negotiated fee or percentage over the amount.

101
Q

Lead Time

A

The amount of time that elapses between placing an order for an item and its delivery to the site, but can also refer to the time required for the preparation of drawings, approvals processes, and so on.

102
Q

ASHRAE 90.1

A

American Society of Heating, Refrigerating and Air Conditioning Engineers.

It is a standard that provides minimum requirements for the energy-efficient design of buildings

103
Q

SMACNA

A

Sheet Metal Ait Conditioning Contractor’s National Association

104
Q

Fee per phase

A

Phase’s percentage, multiplied by total working fee

105
Q

What are the steps to Quality Management Improvement

A
  • Review current processes
  • identify Current process weaknesses
  • Standardize and stabilize workflow
  • Measure performance
  • Improve quality continuosely
106
Q

Liquidated Damages

A

Are funds covering the costs for each day the project continues past the agreed-upon date of completion. These funds are typically deducted from what the owner owes to the contractor for the work.