Project Management Flashcards

1
Q

What is a project?

A

Has an beginning and an end
Interrelated set of activities
Unique outcome from a specific allocation of resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three main goals of a project?

A

Completed on time
Not exceed the budget
Meet specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a collection of projects called?

A

Program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the required steps before starting a project?

A

Define
- Scope
- Time frame
- Resources of the project

Select project manager and team

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the characteristics of a good project manager?

A
  • Facilitator
  • Communicator
  • Decision maker
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the characteristics of a good team?

A
  • Technical competence
  • Sensitive
  • Dedicated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the five steps to planning a project?

A
  1. Define the work breakdown structure
  2. Diagramming the network
  3. Developing a schedule
  4. Implementation
  5. Control and documentation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the work breakdown structure?

A
  • Statement of all the tasks
  • Task is the smallest unit of work effort that consumes both time and resource
  • Each task must have and owner
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How is a work breakdown structure network diagram drawn?

A

Uses boxes and arrows to depict relationships between tasks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the benefits of the structure network diagram?

A
  • Identifies interrelationships between activies
  • Enables estimation of comletion time
  • Crucial activities are highlighted
  • Cost/time tradeoffs can be analyzed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How are activity times estimated?

A
  • Historical data
  • Statistical analysis
  • learning curves
  • Informed estimates
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What do schedules do?

A

Help managers achieve the objectives of the project by
- Estimating completion time through the critical path
- Identify start and finish time for each activity
- Calculate the slack time for each activity”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a path?

A

The sequence of activities between a project’s start and finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the critical path?

A

The sequence of actvities betweeen a project’s start and finish that takes the longest

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the earliest start time?

A

The latest EF of preceding activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the earliest finish time?

A

The ES plus the estimated duration.

17
Q

What is the lastest start time?

A

The LF minus the estimated duration.

18
Q

What is the latest finish time?

A
19
Q

What is activity slack?

A

The maximum time an activity can be delayed without delaying the entire project.
(Activities on the critical path have zero slack)

20
Q

How to calculate activity slack?

A
  • S=LS-ES
  • S=LF-EF