Project Management Flashcards

1
Q

what is slack time ?

A

LS - ES or LF-EF

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what is crashing

A

shortening the activity time in a network to reduce time on the critical path so total completion time is reduced