project management Flashcards

1
Q

define critical path analysis

A
  • finds a project critical path
  • identifies which tasks must complete on time in order for the whole project to complete on time
  • defines the minimum time in which the project can be completed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

define predecessor

A
  • task in a project that must be completed before another task can start
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what does the circles stand for

A
  • milestones

- and the number represents identification purpose

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

what does the arrows stand for

A
  • represent tasks
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what does the numbers next to each tasks stand for

A
  • represent the time taken for the task
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what is a prototype

A
  • a ‘mock-up’ of a software solution in a primitive form
  • used in the design stage to demonstrate how the system will work and look
  • usually focused on user interface
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

advantages of prototype

A
  1. client get to feel the new system before it is developed and provides feedback upon it
  2. client gets to compare the prototype against the requirements specification
  3. client gets the opportunity to explain their requirements more clearly after seeing the designers interpretation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly