Project Integration ITTo Flashcards
What is the input to the process “ Develop Project Charter “ which talks about economic feasibility study to establish validity of the benefits of a selected component as part of the project?
Project Business Case - A documented economic feasibility study used to establish the validity of the benfits of a selected component lacking sufficient definition and that it is used as a basis for the authorization of further project management activities
What is the output to the process “ Develop Project Charter” which talks about high level and strategic constraints and assumptions as identified in the business case?
Assumption log
What is the input to the process ‘ Develop Project Charter’ which talks about different alignment in forms of contracts, MOUs, SLAs, LOAs.
Agreements - Agreements are used to define initial intentons for a project.
What is the T&T in the process ‘ Develop Project Charter ‘ which takes into account processes viz. conflict management, facilitation and meeting mgmt?
Interpersonal and team skills
What is the input in the process ‘ Develop Project Charter’ which is a documented explanation for creating, maximizing and sustaining the advantages of a projet?
Benefits Management plan
What is the input in the process ‘ Develop Project Management Plan’ which formally authorize existance of the project?
Project Charter
What is the input in the process ‘ Develop Project Management Plan’ which takes into account external factors such as Govt. regulations, legal norms, infrastructure etc?
Enterprise Environmental Factors (EEF0
What is the T&T in the process ‘ Develop Project Management Plan” which takes into account activities such as brainstorming, focus groups and interviews?
Data Gathering
What is the input in the process ‘Direct and Manage Project Work’ which directs implementing and corrective action, preventative action or defect repair?
Approved Change Requests
What is the primary T&T in the process DIRECT and MANAGE PROJECT WORK which provides access to IT software tools, configuration management systems, knowledge respositories to manage project work?
PMIS
What is the output in the process DIRECT & MANAGE PROJECT WORK whcih are the raw observations and measurements identified during activities being performed?
Work Performance Data
What is the output in the process DIRECT & MANAGE PROJECT WORK which are unique and verifiable products, results or services required to complete a project?
Deliverables
What is the output in the process DIRECT & MANAGE PROJECT WORK which captures action plans and issues occuring during a project and created for the first time in this process and revised subsequently?
Issue Log
What is the output in the process DIRECT & MANAGE PROJECT WORK which captures the challenges faced, realized risks and opportunities during a project and document the same as learnings for future projects
Lesson Learned Register
What is the T&T in the process MANAGE PROJECT KNOWLEDGE which enables people to share tacit knowledge and integrate knowledge of diverse team members?
Knowledge management