Project Financial Control And Reporting Flashcards

1
Q

You mentioned you are responsible for cost reporting to the client. Please talk me through how you would produce a cost report and how this would be presented to the client.

A

Set up meeting to go through key client objectives. This would include:

  • benefits
  • timescales
  • packages to use
  • cashflow
  • arrangement of changes
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How do you produce the cashflows on your project and why is this helpful to the client… What do they use it for?

A

I use the programme and the cost plan to determine each packages value and time taken. I then input this to software to establish the cashflow amounts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How did you calculate loss and expense on Tolworth?

A

Relevant Matter has occured

Assess the heads of claims

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What risks did you price on Tolworth and how did you price these?

A

Inert, Non Haz, Hazardous materials from breaking out the slabs
Phase 2 slabs
Japanese Knotweed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the purpose of cost reporting?

A
  • To record all known costs which can be accurately valued
  • To report all costs which are known and can be estimated at the date of the report
  • To forecast costs as can reasonably be foreseen at the date of the report
  • risk allowances necessary as can be reasonably foreseen at the date of the report.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is Final outturn cost controlled by cost reporting?

A

Outturn cost is controlled by the recognition of cost changes incurred and planned implementation of future cost changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are variable costs?

A
Provisional sums
Risk
Loss and expense
Liquidated damages
Variations
Prime cost sums
Re-measurable contracts
Anticipated instructions
Fluctuations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is good cost reporting?

A
  • Always accurately track cost and changes
  • Communicate changes effectively as and when required
  • Keep a rolling final account
  • Good cost report document to keep client informed
  • Good relationship with contractor
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is cost control?

A

The process of valuing and manging changes. To ensure the project is delivered at the right price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Would you issue a final payment certificate?

A

You should never issue a final payment certificate as this would mean you cannot claim for latent defects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is the final account produced?

A

Contractor must submit information within 3 months of PC. If they do not, you will need to prepare this and give notice you will do it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

On your projects, why was it important that the contingency pot was only used for risks which there was no provision for?

A

This is because these risks already have a provision in the contract and using the contingency would not be necessary. All costs which can be foreseen should have a provision within the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the contents of a monthly cost report?

A
Lump sum contracts
• contract sum
• adjustment of variable costs
• adjustment of variations
• adjustment of fluctuations
• claims for loss and/or expense; and
• adjustment of risk allowances.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Are there any costs you would exclude from a cost report?

A

If it is a construction cost report i would exclude professional fees, 3rd party costs, land costs, agency costs, finance cost and legal fees.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

On the basis that most clients don’t want to read a whole report, what do you convey in the Executive Summary?

A

Budget, forecast cost, risk, approved changes, unapproved canges, provisional sums, cashflow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Would you include contractor claims in your cost report? What about loss and expense and LDs?

A

Yes these would be listed under the unapproved variations until they have been approved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How have you controlled costs in the design stages of a project?

A

Change control and showed differences using precontract cost trackers.
Order of Cost Estimates
Cost Plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the purpose of a cashflow? Who produces one and how?

A

For client:

  • To monitor progress against agreed programme
  • To be able to monitor loan payments and withdrawing money from funder
  • To manage resources

For contractor:

  • To monitor subcontractor’s progress against subcontractors
  • To manage resources
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What change control procedures have you implemented?

How did they work?

A

Agreement of CC procedure with client
EA raises ECR / Contractor notifies of change
EA requests quotation (to be submitted within 14 days)
Contractor submits cost
QS assess and agree
EA instructs

20
Q

How do you deal with provisional sums in a cost report?

A

Provisional sums are recorded separately to other packages in terms of package value, purchase orders and spend to date.

21
Q

If a client suggests there is an error in the Cost Report – how would you go about resolving the problem?

A

I would clarify what the error is with the client and then do an inspection of the error. If i find that the client is correct, I will apologize and rectify the error. I will also let the client know of my complaints handling procedure.

22
Q

What is the general risk allowance method?

A

The balance of remaining risk allowance should be maintained throughout the remainder of the project.

23
Q

How did you deal with contractor’s claims in your cost report?

A

These should be treated as unapproved changes until they have been assessed for scope and cost.

24
Q

How would you prepare a final account?

A
  • Check the contract procedures for final account including the timescales.
  • Ensure to resolve all the variable costs (changes, loss and expense, liquidated damages, prime costs, dayworks, provisional sums).
  • If there are any disputes which cant be resolved in any other way, the statutory obligation is to go to adjudication.
25
How do you deal with verbal instructions on JCT (including timescales)?
The contractor must confirm the client's EA team within 7 days of stating the change. The EA must then dissent from the change or it will take place.
26
What are the requirements for the FA on SBC and D&B?
6 months Con to submit 3 months to assess If Contractor doesn't QS to prepare
27
Who has ownership of the contingency?
Although I manage the client contingency the client ultimately has ownership
28
Would you use the contingency pot on variations?
I would always seek approval by the client in writing
29
How to control costs pre and post contract?
PRE - Cost Plans - Value Management - Cost Tracking POST - Cost Reports - Valuations
30
What would you do if your client didn't want a cost report?
Explain the benefits of a cost report | Carry out my own cost report to monitor costs for my own benefit
31
What would you do if your project was over budget?
Seek cost saving exercises Ask the Contractor to seek cost savings in design Request additional funding
32
What would you advise your client if your behind on a cashflow?
Behind on programme Resequencing of work Weather Sourcing of subbies
33
What is ISO 9001?
The standard is used by organizations to demonstrate their ability to consistently provide products and services that meet customer and regulatory requirements and to demonstrate continuous improvement.
34
What if your contractor are overclaiming on their valuations and against their cashflow?
It could show: - poor cashflow of contractor - financial concerns to recoup cash
35
How are unapproved changes (risks) dealt with?
Included in the Cost Report as "Anticipated Change" to reflect on the potential outturn cost
36
What was your role of the change control?
PM / CA agreed change control | To agree variation and report
37
How was your cost reporting protocol agreed?
TBC
38
How can you prepare a cashflow?
PRE Programme vs Anticipated Cost Post Programme vs Contract value Contractors cashflow
39
What are the uses for a cashflow?
Help client understand drawdowns Help track progress Help contractors understand cash and to reinvest Helps client to obtain loan and bank to monitor progress
40
What is your cost control procedure during the design phase?
Agree cost control procedure and communicate w/project team Designer to submit CRF Advise client of cost Client sign off
41
What are some appendices to your CR?
Change control log | Risk log
42
What is included on the CRF?
Project, Date, and Issuer Cost implications (MAX) Programme implications Approval from client
43
What is a PC Sum?
This is a cost included in the tender / pricing document for the supply only rate of a material
44
What is in the Cost Reporting guidance note?
``` Purpose of CR Contents of a CR Establishing a budget Reporting on contingencies CR Example ```
45
What is included in a project cost report?
More of a holistic view of costs on the project including: ``` Construction Cost Professional Fees Stats Third Party Fees Land Fees Agency Fee Legal Fees ```
46
What is a defined provisional sum?
Means a sum of money set aside to carry out work that cannot be described and given in quantified items in accordance with the tabulated rules of measurement.
47
What is an undefined provisional sum?
Means a sum provided for work that is not completely designed, but for which the information required for a defined provisional sum cannot be provided