Project Finance (Control & Reporting) Flashcards

1
Q

What Is a Post Contract Cost Report

A

Document that is produced periodically that sets out the financial position of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the purpose of a Post Contract Cost Report

A

To enable the client to make informed decisions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is included within a cost report

A
Variations
Provisional Sums 
Valuations
Anticipated Final Account
Forecast Cash flow V Actual Cash flow
Advanced Warnings 
Any Claims
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a cash flow

A

A cash flow distributed construction costs in to monthly forecasts in accordance with the contractors construction program

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What Shape is a cash flow curve

A

‘S’ shaped, Slow start at the beginning of the project and lower costs towards the end of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What could it mean if the actual cash flow is above the ‘S’ curve

A

Contractor working slower then anticipated
Re-sequencing of work
Poor financial Health
Difficulties in securing labour/materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What could mean if the actual cash flow is below the ‘S’ curve

A

Acceleration

Materials delivered to site ahead of time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a change/variation

A

An alteration to the scope of works in a construction contract
Impact on cost/time/qaulity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Contractor led change procedure

A
  • Change request for issues by contractor
  • Client team review (design/cost/program)
  • Design team sign off
  • EA/CA has 7 days since CRF to instruct
  • CRF log updated
  • Design & construction proceed in accordance of the instruction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Client led change procedure

A
  • Change request for issues by Client
  • Contractor to produce design, cost and program implications
  • Design team sign off
  • EA/CA has 7 days since CRF to instruct
  • CRF log updated
  • Design & construction proceed in accordance of the instruction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What procedure is used when the client wants to find out implications before instructing

A

Variation Quotation Procedure / Schedule 2 Quotation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Explain the process of the Variation Quotation Procedure / Schedule 2 Quotation

A
  1. CA/EA provides information to the Contractor (similar level to tender stage) to allow them to
    prepare a quotation for the works
    o This typically includes the statement that at least 3 sub-contractor quotes must be
    sought to ensure competition and value.
  2. The contractor has 7(SBC)/10(DB) days after receiving the information to notify the CA/EA if
    he will provide a quote or if he requires additional information
    o If additional information is required the contractor shall not be obliged to provide a
    quotation and the variation shall not be carried out until further information from
    the CA/EA
  3. Once the Contractor has all the information required he can provide a quotation to the
    CA/EA or QS. Quotation to include:
    o Amount of adjustment to the contract sum including preliminaries (but excluding
    loss and/or expense claims)
    o Details of any time adjustments (extension of time) to the programme
    o Any details of loss and/or expense claims
    o A fair and reasonable cost for preparing the quotation
    o Base date for the valuation of the works
  4. Costs must be submitted 21(SBC)/14(DB) days after whatever occurs last out of the receipt
    of instruction or receipt of additional sufficient information if requested
  5. CA/EA has 7(SBC)/10(DB) days from the receipt of the quotation to either accept the
    quotation or withdraw the instruction
  6. If the Employer withdraws the instruction the Contractor is still entitled to the reasonable
    cost of preparing the quotation/estimate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Loss & Expense

A

A means for the contractor to recover/be reimbursed of any direct loss and/or expense
incurred because the regular progress of the Works or any part of them has been or is likely
to be materially affected by any Relevant Matter/by the Employer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the process for Loss and/or Expense

A
  1. Contractor must give written notice to CA/EA as soon as the likely effect of a Relevant
    Matter becomes reasonably apparent.
  2. Notification shall be accompanied with/followed by the Contractor’s initial assessment of:
    o Particulars of the expected effects of the Relevant Matter
    o Estimation of the ascertained amount of loss and/or expense that he has incurred or
    will incur (Heads of Claim)
    o Necessary information for the CA/EA/QS to ascertain loss and/or expense.
  3. CA/EA determines whether any delays or loss and/or expense claimed are caused by
    Relevant Matters.
  4. Contractor updates assessment and information at monthly intervals until all information
    needed by the CA/EA/QS to ascertain the total loss and/or expense is supplied.
  5. CA/QS have 28 days of receipt of initial assessment and 14 days of each subsequent monthly
    update, to notify the Contractor of the ascertained loss and/or expense incurred
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How many days does the CA/EA/QS has to respond to respond of receipt of the initial assessment

A

28 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly