Project Evaluation and Review Technique and Critical Path Method Flashcards
Are two commonly used project management techniques for evaluating, scheduling, and
regulating large projects.
Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM)
These strategies offer a systematic approach to managing
activities, funds, and timetables, helping working groups to maximize productivity while
mitigating risks.
Project Evaluation and Review Technique (PERT) and Critical Path Method (CPM)
The main idea of PERT-CPM is to ___________, and to create a network model by breaking
down a project into individual activities and establishing dependencies among them,
taking into account probable uncertainties, allowing effective decision making.
identify critical activities and
determine the shortest possible duration
IMPORTANCE OF PERT-CPM
● Determine the project duration and individual tasks required time
● Determines critical path and identifying tasks that can and cannot be delayed
● Overviewing the dependencies of each activities in a project
● Effective utilization of resources
● Enables efficient cost and quality control
Are used to increase project effectiveness and efficiency
PERT and CPM
APPLICATIONS OF PERT-CPM
● Construction Projects
● Engineering Projects
● Information Technology Projects
● Research and Development Projects
● Event Planning and Management
● Manufacturing Operations
● Supply Chain Management
Is a tool used to analyze and represent the tasks involved in completing a given project. It helps to estimate the time required to complete each task. Thus, it is probabilistic in nature.
PERT
The first step in PERT is to _________ to complete the project. Tasks should be broken down into smaller, manageable
units to ensure accurate estimation and analysis.
Task Identification
Once tasks are identified, the next step is to _________ in which they must be completed. Some tasks may be dependent on
the completion of others, while some can be performed concurrently.
Task Sequencing
PERT requires __________ to
complete each task. Three time estimates are typically used:
Estimation of Task Duration
The shortest possible time required to complete a task
assuming everything goes according to plan.
Optimistic Time (O)
The best estimate of the time required to complete a task
under normal conditions.
Most Likely Time (M)
The longest possible time required to complete a task
assuming everything goes wrong.
Pessimistic Time (P)
These estimates are used to calculate an expected time (TE) for each task, often using
the formula:
TE = (O + 4M + P) / 6
PERT uses _______ to identify the longest path of dependent tasks through the project network. The critical path represents the shortest time in which the project can be completed. Any delay in tasks on the critical path will directly impact the overall project timeline.
Critical Path Analysis
Is used to visually represent the sequence of tasks, their interdependencies, and the critical path. Tasks are represented as nodes, and arrows represent the flow and sequence of tasks.
Network Diagram
Refers to the amount of time a non-critical task can be delayed without affecting the overall project timeline. Tasks with float can be delayed without causing a delay in the project’s completion.
Float or Slack
PERT also involves __________ to different tasks based on their importance, dependencies, and criticality to the project timeline.
This ensures that resources are utilized efficiently to complete the project on time.
Resource Allocation