Project details Flashcards
1
Q
When was start on site (BP)
A
20th June 2022
2
Q
When was PC (BP)
A
30th May 2024
3
Q
When was the original end date (BP)
A
July 2023
4
Q
When was the contractor originally selected (BP)
A
August 2021
5
Q
How long did the contractor fix their price for (BP)
A
60 days
6
Q
what was the £/m2 (BP)
A
£17,500/m2
7
Q
What VE options did you have? (BP)
A
Removing/lower spec of unnecessary doors (50k)
Standard over hand-crafted cornices (60k)
Standardised toilet cubicles over plasterboard (50k)
8
Q
What contract amendments did you do (BP)
A
- Onus on the contractor for any divergence between ER’s and CP’s
- Change payment date to 28 days after due date
- change schedule 2 timeline from 21 to 14 days for a response
9
Q
What construction technologies did you develop (BP)
A
Lathe and plaster walls
Clay pot ceilings
Lime render