Project details Flashcards

1
Q

When was start on site (BP)

A

20th June 2022

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When was PC (BP)

A

30th May 2024

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When was the original end date (BP)

A

July 2023

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When was the contractor originally selected (BP)

A

August 2021

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How long did the contractor fix their price for (BP)

A

60 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

what was the £/m2 (BP)

A

£17,500/m2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What VE options did you have? (BP)

A

Removing/lower spec of unnecessary doors (50k)
Standard over hand-crafted cornices (60k)
Standardised toilet cubicles over plasterboard (50k)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What contract amendments did you do (BP)

A
  • Onus on the contractor for any divergence between ER’s and CP’s
  • Change payment date to 28 days after due date
  • change schedule 2 timeline from 21 to 14 days for a response
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What construction technologies did you develop (BP)

A

Lathe and plaster walls
Clay pot ceilings
Lime render

How well did you know this?
1
Not at all
2
3
4
5
Perfectly