Project Delivery Models Flashcards

1
Q

DESIGN-BUILD is best for:

A

RISK / COST / TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

DESIGN-BUILD

A

Single Contract between the owner and the construction / design entity.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

DESIGN-BUILD price:

A

Determined after concept design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CM - CONSTRUCTOR is best for:

A

TIME / COST / RISK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CM-CONSTRUCTOR price:

A

• Determined as early as 100% DD
• Cost - Plus - Fixed fee w/GMP
• Cost - Plus - Fixed fee w/o GMP

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CM - AGENT best for:

A

RISK / TIME

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

NEGOTIATED SELECT TEAM

A

• Contractor is selected early.
• Contract terms determined before CDs are complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

NEGOTIATED SELECT TEAM is best for:

A

QUALITY / COST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

NEGOTIATED SELECT TEAM price:

A

Determined after Construction Documents are complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

BRIDGING is best for:

A

RISK / QUALITY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

BRIDGING

A

Architect / Engineer is hired as a consultant at the start of process.
• A/E develops project requirements, preliminary and scope drawings.
• A/E reviews work of Design-Build firm on behalf of owner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BRIDGING price:

A

Determined after competitive bidding process based on A/E preliminary scope drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

COST + FIXED FEE is best for:

A

SCOPE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

COST + FIXED FEE

A

GC is paid a variable rate determined by labor, material, overhead, and established profit fee. Selected after CDs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

COST + FIXED FEE price:

A

Final price determined at completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

INTEGRATED PROJECT DELIVERY is best for:

A

QUALITY / TIME / COST

17
Q

INTEGRATED PROJECT DELIVERY

A

All parties are incentivized to optimize the design, improve costs, enhance quality, and avoid confrontation. No litigation.

18
Q

INTEGRATED PROJECT DELIVERY price:

A

Target cost is usually developed early through various contract alternatives.