Project Delivery Methods Flashcards
What are the owner’s responsibilities in design-build?
Duties normally performed by the architect:
- construction contract administration
- reviewing and approving submittals
- approving changes submitted by the designer-builder
- visiting the site
- rejecting nonconforming work
- certifying substantial completion
Who provides GMP?
The contractor
How many agreements does the owner need in IPD?
Typically multiple with independent firms.
How many agreements does the owner need in design-build?
One.
Is attorney a consultant?
Yes
Implicit client of the job?
All building users
What is a significant component if the project quality?
Sustainable design
What is often refined during design?
Project scope
Privity
Legal obligation of parties
Risks for the architect
Can this be accomplished with standard of care?
Level of quality.
Fee.
What affects the project delivery selection for the owner?
Capabilities-preconceived notions
Three main types of PD
Design-bid-build, Construction management, Design-Build. (IPD is sometimes considered the 4th)
Negotiated select team
A variation of DBB. A contractor is selected early in the design process. Subcontractors are selected after that. The final contract is based on early pre-negotiated terms.
Cost plus fixed fee
Contractor is selected at the completion of CD. The scope is unpredictable, the GC is paid for labor, overhead and fee for profit that is fixed and won’t change regardless of increase in project cost.
CM-adviser
Acts only as constructability and cost management consultant during design and construction, will NOT build the building. CM adviser can be used with any of PD.
Draw a CM adviser diagram
.
CM-Agent
Provides early consulting.
Acts on behalf of the owner in assembling and coordinating construction trades prior to and during construction.