Project Deliver Methods Flashcards

1
Q

Design-Bid-Build

A
  • Primary - COST
  • Secondary - Risk
  • cost is determined after design
  • 1 contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Negotiated Team

A
  • Primary - QUALITY
  • Secondary - Cost
  • cost determined after design
  • 1 contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cost Plus Fee

A
  • Primary - SCOPE
  • no Secondary
  • cost determined at completion
  • 1 contract
  • puts owner at risk, since owner won’t know final cost until completion
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

CM as Advisor

A
  • Primary - RISK
  • Secondary - Quality
  • construction cost not applicable since contractor is just an advisor
  • many contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CM as Agent

A
  • Primary - RISK
  • Secondary - Time
  • cost determined at completion
  • many contracts
  • usually used when owner does not have a lot of construction experience
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CM as Contractor (CM@Risk)

A
  • Primary - TIME
  • Secondary - Cost / Risk
  • cost determined after design
  • 1 contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Design-Build Standard

A
  • Primary - RISK
  • Secondary - Cost
  • cost determined before design
  • 1 contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Design-Build Bridging

A
  • Primary - RISK
  • Secondary - Quality
  • cost determined after design
  • 1 contract
  • used when owner does not know much about Architecture or Construction
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

IPD (Integrated Project Delivery)

A
  • Primary - QUALITY
  • Secondary - Cost / Time
  • cost is determined early
  • 1 contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly