Project Deliver Methods Flashcards
1
Q
Design-Bid-Build
A
- Primary - COST
- Secondary - Risk
- cost is determined after design
- 1 contract
2
Q
Negotiated Team
A
- Primary - QUALITY
- Secondary - Cost
- cost determined after design
- 1 contract
3
Q
Cost Plus Fee
A
- Primary - SCOPE
- no Secondary
- cost determined at completion
- 1 contract
- puts owner at risk, since owner won’t know final cost until completion
4
Q
CM as Advisor
A
- Primary - RISK
- Secondary - Quality
- construction cost not applicable since contractor is just an advisor
- many contracts
5
Q
CM as Agent
A
- Primary - RISK
- Secondary - Time
- cost determined at completion
- many contracts
- usually used when owner does not have a lot of construction experience
6
Q
CM as Contractor (CM@Risk)
A
- Primary - TIME
- Secondary - Cost / Risk
- cost determined after design
- 1 contract
7
Q
Design-Build Standard
A
- Primary - RISK
- Secondary - Cost
- cost determined before design
- 1 contract
8
Q
Design-Build Bridging
A
- Primary - RISK
- Secondary - Quality
- cost determined after design
- 1 contract
- used when owner does not know much about Architecture or Construction
9
Q
IPD (Integrated Project Delivery)
A
- Primary - QUALITY
- Secondary - Cost / Time
- cost is determined early
- 1 contract