Project Def And WBS Config Flashcards

1
Q

Where do u assign proj type, Tcode and location

A

OPSA; Control; Basic Data; proj.type field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Where do u assign the user defined fields for the WBS elements

A

OPSA; Control; Basic Data; “Field Key” field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where do u assign the version profile for the the project?

A

OPSA; Control; Basic Data; version prof. Field or ????

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Where do u define how the WBS will b displayed on the overview screen

A

OPSA; Control; Basic Data; Display Options

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you define lowest level displayed on the screen?

A

OPSA; Control; Basic Data; Level of detail

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where do u assign the partner determination procedure for a project

A

OPSA;Control; Basic Data; PartnDet.Proc. Field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Where do set the default indicator for Account Assignment for the WBS

A

OPSA; Control; Basic Data; All acct. asst elem check box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Where do u define only one root for the project definition at?

A

OPSA;Control; Basic Data; only one root check box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Where do u define assignment of only one Proj Def for a WBS?

A

OPSA; control; Basic Data; “Trsfr to proj.def.”Check box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Where do u configure the summarization of master data reporting

A

In OPSA; control; basic data; by setting the proj. summ. MastDa check box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Settings for validation including automatic

A

OPSA; Control; validations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Settings for substitutions including automatic

A

OPSA; Control; substitutions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Where do you configure project stock

A

OPSA; Control; Project stock section

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Which project stock does RA use

A

Non-valuated project stock

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where do u assign the project status profile?

A

OPSA; Control; Status management; “PD sts. Profile” field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Where do u assign the WBS status profile?

A

OPSA; Control; Status management; WBS status prof.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Where do you set the change documents indicator for a project?

A

OPSA; Control; change documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Where do u set the project summarization settings for WBS Elements?

A

OPSA; Control; project summarization; “All WBS elements” indicator

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Where do u set the billing element’s summarization setting

A

OPSA; Control; Project Summarization; “Billing Elements” check box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Where do u set the account assignment element summarization setting

A

OPSA; Control; Project summarization; “Acct Asst Elements” check box

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Where do you set the default controlling area for the project

A

OPSA; Organization; in the controlling area field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Where do you set the default company code for the WBS element?

A

OPSA; Organization; in the “company code” field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Where do u set the default business area for the WBS

A

OPSA; Organization; “business area “

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Where is the plant set as the default for the project.

A

OPSA; Organization; “plant” field

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Where is the functional area set as default for the project?
OPSA; Organization; “functional area” field.
26
Where is the profit center set as default for the project in the config?
OPSA; Organization; “ profit center“ field
27
Where is the project currency set as default for the project and config?
OPSA; organization; “project currency “ field
28
Where is the factory calendar set as default for the project in the configuration?
OPSA; Plg board/dates; default values; “factory calend.” Field
29
Where is the default time unit for a project set in configuration?
OPSA; Plg board/dates; default values; “ time unit” field
30
Where is the default network profile set for project in the configuration?
OPSA; Plg board/dates; Network; “network profile” field
31
Where do u assign the object class in configuration.
OPSA; Controlling; costs/revenues/payments “object class “ field
32
What is the purpose of the object class field?
Co reporting of type of project
33
Where do u set the default statistical indicator for a project
OPSA; Controlling; costs/revenues/payments; “Statistical” indicator
34
Where do u set the default integrated planning indicator?
OPSA; Controlling; costs/revenues/payments; integrated planning
35
What do u set if you want planning to flow to the Cost center from the WBS?
The integrated planning indicator on the project profile
36
Where do u set the planning profile for the project in the configuration?
OPSA; Controlling; planning/budgeting; “planning profile” field and in Tcode ????
37
Where do you set the default budget profile for a project?
OPSA; controlling; Planning/budgeting; budget profile field and Tcode????
38
Where do you set the default costing sheet for a project?
OPSA; controlling; period end closing; “costing sheet” field or Tcode ????
39
Where do u set the default interest profile for a project in config
OPSA; period end closing ; “interest profile“ field, or Tcode ????
40
Where do you set the default investment profile for a project?
OPSA; period end closing; “investment profile” field ; or Tcode ????
41
Where do you set the default RA key for a project?
OPSA; controlling; Period end closing; “Results Analysis key” field; or Tcode????
42
Where is the default settlement profile set for a project in the config?
OPSA; controlling; “settlement profile” field or Tcode ????
43
Where is the default settlement rule strategy set for project?
OPSA; controlling; ” settlm rule strat. field or Tcode ????
44
How do u assign overhead costs to a project?
Costing sheet
45
What is project type used by RA?
Non valuated project stock
46
What transaction code is used to maintain project types and config?
OPSO
47
Transaction code is used to specify applicants for WPS elements
OPS7
48
Transaction code is used to specify person responsible for WBS elements
OPS6
49
What transaction code is used to define priorities for WBS elements?
OPTN 
50
What is the transaction code to define field selection for work breakdown structure?
OPUK
51
What’s the transaction code to create user defined field for WBS elements?
OPS1
52
What’s the transaction code to maintain validations?
OPSI
53
What’s the table and field name for project profile?
PROJ-PROFL
54
What’s the table and field name for WBS level?
PRPS-STUFE
55
What is the table and Field name for project type?
PRPS-PRSRT
56
Is there an enhancement for checking user defined fields?
Yes on the WBS element only
57
What is the transaction code to Divine project numbering
TCJED
58
What is the purpose of selection profile?
To create selection of obj by multiple user statuses at once.
59
What is the min proj profile config?
Basic data, time scheduling, costs/revenues/finances, and org data
60
What is the ACL list
Access control list. Used to assign authorizations and should b activated
61
How do u stop the budget from going over
Setup availability control navy uses status profiles.
62
What Tcode do you use to define parameters for WBS scheduling in config?
Tcode OPTQ
63
What project stock is the navy using?
Valuated project stock
64
What’s the transaction code for creating a PS status profile
OK02
65
What are the project settlement profile configuration settings?
Indicate settlement amount Set default values Set indicators Set receiver objects Document settings
66
In the project settlement profile, configuration setting what are the default values that are possible to be set?
Allocation structure Source structure PA transfer structure Default object type
67
In the project settlement profile, configuration setting what are the indicators that are possible to be set?
100% validation % settlement Equivalence numbers Amount settlement Costing PA
68
What is the transaction for settlement
Cj88