Project Costs & Budgeting Flashcards
To use cost information effectively, an architect should apply what index?
A regional index should be applied to the national average for this information to be useful.
When do contractors use the unit cost method?
This method is used to establish a bid or negotiated price.
Profit is a percentage of what four items?
The four items used to calculate this cost item are
• labor
• materials
• equipment
• overhead
How does matrix costing work?
This project costing method uses a matrix to break down the elements of a project into items that are compared for their cost effectiveness and efficiency.
What negative impact can result from value engineering?
Reducing costs by reducing quality can result from this activity.
At what stage of the project is the parameter method most useful to refines project budget?
This method of project budgeting is best employed during design development and the early phases of construction documentation.
How does a life cycle cost analysis differ from a life cycle assessment?
The first evaluates the alternatives and their cost in present time, while the second analyzes the impact of the system or product over a period of time.