Project Cost Management Terms Flashcards
Actual cost (AC)
The actual amount of monies the project
has spent to date.
Analogous estimating
An approach that relies on historical
information to predict the cost of the
current project. It is also known as topdown estimating and is the least reliable
of all the cost-estimating approaches.
Bottom-up estimating
An estimating approach that starts from
zero, accounts for each component of the
WBS, and arrives at a sum for the
project. It is completed with the project
team and can be one of the most timeconsuming and most reliable methods to
predict project costs.
Budget estimate
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.
Commercial database
A cost-estimating approach that uses a
database, typically software-driven, to
create the cost estimate for a project.
Contingency reserve
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events
Cost aggregation
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
Cost baseline
A time-lapse exposure of when the
project monies are to be spent in relation
to cumulative values of the work
completed in the project.
Cost budgeting
The cost aggregation achieved by
assigning specific dollar amounts for
each of the scheduled activities or, more
likely, for each of the work packages in
the WBS. Cost budgeting applies the cost
estimates over time.
Cost change control system
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
Cost management plan
The cost management plan dictates how
cost variances will be managed.
Cost of poor quality
The monies spent to recover from not
adhering to the expected level of quality.
Examples may include rework, defect
repair, loss of life or limb because safety
precautions were not taken, loss of sales,
and loss of customers. This is also known
as the cost of nonconformance to quality.
Cost of quality
The monies spent to attain the expected
level of quality within a project. Examples
include training, testing, and safety
precautions.
Cost performance index (CPI)
Measures the project based on its
financial performance. The formula is CPI
= EV/AC
Cost variance (CV)
The difference of the earned value
amount and the cumulative actual costs
of the project. The formula is CV = EV –
AC.
Definitive estimate
This estimate type is one of the most
accurate. It’s used late in the planning
processes and is associated with bottomup estimating. You need the WBS in
order to create the definitive estimate.
The range of variance for the estimate
can be from –5 percent to +10 percent.