Project Cost Management Processes Flashcards

1
Q

Estimate Costs

A

The process of developing an approximation of the monetary resources needed to complete project activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Determine Budget

A

The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Control Costs

A

The process of monitoring the status of the project to update the project budget and managing changes to the cost baseline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Level of Accuracy

A

Activity cost estimates will adhere to a rounding of the data to a prescribed precision (e.g., $100, $1,000), based on the scope of the activities and magnitude of the project, and may include an amount for contingencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Units of Measure

A

Each unit used in measurements (such as staff hours, staff days, weeks, or lump sum) is defined for each of the resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Organizational Procedures Links

A

The work breakdown structure (WBS) (Section 5.3.3.1) provides the framework for the cost management plan, allowing for consistency with the estimates, budgets, and control of costs. The WBS component used for the project cost accounting is called the control account (CA). Each control account is assigned a unique code or account number(s) that links directly to the performing organization’s accounting system.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Control Thresholds

A

Variance thresholds for monitoring cost performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the baseline plan.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Rules of Performance Measurement

A

“Earned value management (EVM) rules of performance measurement are set. For example, the cost management plan could: Define the WBS and points at which measurement of control accounts will be performed, Establish the earned value measurement techniques (e.g., weighted milestones, fixed-
formula, percent complete, etc.) to be employed, and Specify the earned value management computation equations for determining the projected estimate at completion (EAC) forecasts and other tracking methodologies.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Reporting Formats

A

The formats and frequency for the various cost reports are defined.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Process Descriptions

A

Descriptions of each of the three cost management processes are documented.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly