PROJ 595 Entire Course New Flashcards
DEVRY PROJ 595 Final Exam Set 1 NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-final-exam-set-1-new
For more classes visit
http://www.assignmentcloud.com
Question 1. (TCOs A and B) An EVM analysis employs which factors to evaluate risks? (Points : 5)
Question 2. (TCO G) You have completed all design drawings and have a complete scope for your project. You need to hire a contractor to build the product to your designs. Which type of contract would be best in this situation? (Points : 5)
Question 3. (TCO D) In which risk response strategy is the responsibility for the risk moved to a third party? (Points : 5)
- (TCOs A and B) You have been appointed as a project manager for a high-dollar project for a government agency, and you have been asked by your boss to identify the stakeholder groups and the individuals who make up those groups in order to start the stakeholder analysis. Identify at least six groups of stakeholders and the individuals who comprise those groups, and explain when the stakeholder identification process should take place during the planning of the project. (Points: 20)
(TCO B) Due to globalization within your industry, you have been appointed as the project manager for an R & D project. Your task is to create a new technologically advanced solar cell. You want to employ the PMBOK® Guide risk management process. Senior management would like you to briefly describe the process and all its steps. Please create a short briefing for senior management below. (Points : 40)
(TCO I) You are the project manager on a critical project for your corporation. You have decided to employ fault-tree analysis on your project. What is fault-tree analysis, and how can it be applied to your project? (Points : 25)
(TCO H) Senior management is concerned about risk owners on your project. What is the role of a risk owner in the risk management process? (Points: 20)
(TCO F) You are a project manager for a large healthcare R & D project. Senior management has asked you to utilize a sensitivity analysis and a tornado diagram to quantify risks on your project. Senior management’s major concern is the price of raw materials in the development of the new drug. Describe how to perform a sensitivity analysis and use a tornado diagram to quantify risks to your project. (Points : 25)
TCO G) Describe and discuss when one should use an FPEPA contract. Compare and contrast this to a typical FP contract. (Points: 20)
(TCO E) Senior management has just returned from a risk management workshop. One of the topics was reserve analysis. Management does not completely understand the concept and asks you what the purpose is of performing reserve analysis during the risk management process. (Points : 20)
TCO D) You are the project manager for an important healthcare project. You are performing qualitative risk analysis. Below are the values of probability and impact for the top six risks that were given to you by project team. Assuming a neutral stakeholder tolerance, which risks must be addressed proactively if possible?(Points : 25)
TCO C) You are the project manager for a large health information technology project. You are confronted with an important decision on your project: How much scenario testing is appropriate for this project? Employ decision tree analysis to provide senior management with the best course of action for this decision
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-final-exam-set-1-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Final Exam Set 2 NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-final-exam-set-2-new
For more classes visit
http://www.assignmentcloud.com
- (TCOs A and B) Quantitative risk analysis does all of the following, except (Points : 5)
Question 2. 2. (TCO G) You need to ensure your project is completed by July 1 of next year. You do not have time to do all the design work yourself, so you decide to contract out that work. Which type of contract would likely be best in this situation? (Points : 5)
Question 3. 3. (TCO D) Which risk response strategy is most appropriate for risks on the watch list? (Points : 5)
Question 4. 4. (TCOs A and B) You have been appointed as a project manager for a high-dollar project for the public sector, and you have been asked by your boss to identify the stakeholder groups and the individuals who make up those groups in order to start the stakeholder analysis. Identify at least six groups of stakeholders and the individuals who comprise those groups, and explain when the stakeholder identification process should take place during the planning of the project. (Points : 20)
Question 5. 5. (TCO B) Due to globalization within your industry, you have been appointed as the project manager for an R & D project. Your task is to create a new technologically advanced solar cell. You want to employ the PMBOK® Guide risk management process. Senior management would like you to briefly describe the process and all its steps. Please create a short briefing for senior management below. (Points : 40)
Question 6. 6. (TCO C) You are the project manager for a large health information technology project. You are confronted with an important decision on your project: How much posttesting of the design is appropriate for this project? Employ decision tree analysis to provide senior management with the best course of action for this decision.
Question 7. 7. (TCO D) You are the project manager for an important healthcare project. You are performing qualitative risk analysis. Below are the values of probability and impact for the top six risks that were given to you by project team. Assuming a neutral stakeholder tolerance, which risks must be addressed proactively if possible?
Question 8. 8. (TCO E) Senior management is very interested in creating an effective risk monitoring and control system that is tied to a performance monitoring system for your project. Describe what a good monitoring and control and performance measurement system for your project would look like. Be sure to include an example to help illustrate your answer. (Points : 20)
Question 9. 9. (TCO F) You are a project manager for a large healthcare R & D project. Senior management has asked you to utilize a sensitivity analysis and a tornado diagram to quantify risks on your project. Senior management’s major concern is the price of raw materials in the development of the new drug. Describe how to perform a sensitivity analysis and use a tornado diagram to quantify risks to your project. (Points : 25)
Question 10. 10. (TCO G) Describe and discuss when one should use an FPEPA contract. Compare and contrast this to a typical FP contract. (Points : 20)
Question 11. 11. (TCO H) You are in a status meeting with key project stakeholders. You are discussing residual and secondary risks in your project. The stakeholders are becoming concerned about these concepts. The key stakeholders ask for an explanation and example of each. How would you describe each? Provide an example of a residual and a secondary risk. (Points : 20)
Question 12. 12. (TCO I) You are the project manager on a complete overhaul of your corporation’s IT infrastructure. You have decided to employ fault-tree analysis on your project. What is fault-tree analysis, and how can it be applied to your project? (Points : 25)
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-final-exam-set-2-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Final Exam Set 3 (NEW)
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-final-exam-set-3
For more classes visit
http://www.assignmentcloud.com
Question 1.
(TCO A) Qualitative risk analysis
Question 2.
(TCO A) You are the project manager of a new, innovative project. One overarching principle you adhere to is
Question 3.
(TCO B) Project assumptions are created in the scope statement. These assumptions are revisited in which process of risk management?
Question 4.
(TCO D) In which risk response strategies are risks guaranteed to not occur if they are negative and guaranteed to occur if they are positive after the response plan is initiated?
Question 5.
(TCO E) One the key functions of risk monitoring and control is to
Question 6.
(TCO H) When using the ATOM process to manage risks, which is the importance of an initiation meeting?
Question 7.
(TCO A) When is a risk register created? What is its importance of a risk register to a project?
Question 8.
(TCO B) List and briefly define five specific tools and techniques that can be used to identify risk associated with projects.
Question 9.
(TCO D) Explain avoidance as a risk response strategy, and provide an example of its use in a project.
Question 10.
(TCO E) Describe what characteristics a performance measurement system, to be employed in a risk monitoring and control process for a project, should have. Include an example to help illustrate your answer.
Question 11.
(TCO H) What is the importance of including stakeholders and risk owners in the creation and approval of risk response plans?
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-final-exam-set-3
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Midterm Exam Set 2 NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-midterm-exam-set-2-new
For more classes visit
http://www.assignmentcloud.com
1. (TCO A) A stakeholder analysis in risk management (Points : 5)
Question 2. 2. (TCO A) When using the ATOM process to manage risks, an initiation meeting should be used for (Points : 5)
Question 3. 3. (TCO B) All of the below are risk identification methods, except (Points : 5)
Question 4. 4. (TCO D) In risk response planning, which is the difference between active and passive acceptance? (Points : 5)
Question 5. 5. (TCO E) A common tool for use in risk monitoring and control is (Points : 5)
Question 6. 6. (TCO H) When using the ATOM process to manage risks, which is the importance of an initiation meeting? (Points : 5)
Question 7. 7. (TCO A) When is a risk register created? What is its importance of a risk register to a project? (Points : 10)
Question 8. 8. (TCO B) You are the project manager for a major technological project. You are concerned about doing qualitative risk analysis. How do you ensure consistency when doing qualitative risk analysis across all risk evaluators? (Points : 15)
Question 9. 9. (TCO D) Explain transference as a risk response strategy, and provide an example of its use in a project. (Points : 15)
Question 10. 10. (TCO E) What is the purpose of performing reserve analysis during the risk management process? (Points : 15)
Question 11. 11. (TCO H) You are in a status meeting with key project stakeholders. You are discussing residual and secondary risks in your project. The key stakeholders ask for an explanation and example of each. How would you describe each? Provide an example of a residual and a secondary risk. (Points : 15)
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-midterm-exam-set-2-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Midterm Set 1 NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-5-midterm-set-1-new
For more classes visit
http://www.assignmentcloud.com
- (TCO A) Qualitative risk analysis
- (TCO A) When using the ATOM process to manage risks, an initiation meeting should be used for
- (TCO B) A watch list is a
- (TCO D) In risk response planning, which is the difference between active and passive acceptance?
- (TCO E) A common tool for use in risk monitoring and control is
- (TCO H) When using the ATOM process to manage risks, which is the importance of an initiation meeting?
- (TCOA) Explain when risk breakdown structure is created, and explain the importance of a risk breakdown structure in risk management
- (TCO B) Explain the qualitative risk analysis process
- (TCO D) Explain transference as a risk response strategy, and provide an example of its use in a project
- (TCO E) Describe the function and process of performing a risk audit during a project
- (TCO H) What is the role of a risk owner in the risk management process?
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-5-midterm-set-1-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Risk Paper 2 NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-risk-paper-2-new
For more classes visit
http://www.assignmentcloud.com
PROJ 595 Risk Paper 2
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-risk-paper-2-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Week 3 Risk Paper 1 (2 Papers) NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-3-risk-paper-1-2-papers-new
For more classes visit
http://www.assignmentcloud.com
Write a two- to four-page paper regarding a project, either real or fictitious, where one is able to discuss how risks were identified, ranked, and monitored. The student is also welcome to write about a major purchase or major decision in his or her life, such as buying a new car, buying a new home, or even the decision to return to school to earn a degree. All of these are considered projects or procurements that require some form of formal or informal risk review.
Remember to cite and reference any sources that were used in the project or in the decision-making process. At a minimum, students should connect this assignment back to the text and support their decision-making processes with key concepts from the text. One of the elements of this assignment is to connect the material from the course to actual risk decisions. You are also welcome to use any of the checklists from the text to support the decision-making process.
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-3-risk-paper-1-2-papers-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Week 4 Course Project(2 Project) NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-4-course-project-new
For more classes visit
http://www.assignmentcloud.com
Course Project Part I
For this project, you may choose a project that is of interest to you. When selecting a project, avoid picking one that is either too big or too small. For example, do not decide to build a new stadium for your local professional sports team (too big) or to plant your summer garden (too small).You will only be addressing the risk issues in the project so you will not need to be looking at the detail required for a business plan. The scope statement and the WBS are required in addition to the risk management plan. It is important to pick one that you understand so that you will be able to create the risk management plan that is realistic with sufficient detail where your contingency plans will be relevant.Since you will need to create a risk management plan, your project should be somewhat risky.
1. Create a risk management plan for your project. To do this, you must first create a scope and a WBS for your project.
2. Perform risk management planning as defined in the lecture.
3. Identify risks for your project, including any issues that may impede or impair the completion of the project. You must identify at least 5 positive and 15 negative risks.
4. Prioritize the risks by performing qualitative risk analysis.
Perform risk response planning for your project by creating detailed risk response plans for those risks needing responses. This should include both proactive responses and reactive contingency plans as appropriate.
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-4-course-project-new
For more classes visit
http://www.assignmentcloud.com
DEVRY PROJ 595 Week 6 Course Project Part II (2 Project) NEW
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-6-course-project
For more classes visit
http://www.assignmentcloud.com
Course Project Part II
For this part, you will be creating two decision trees concerning specific risks or events from the project you developed in part 1. The first one will be a decision tree used to make a decision. You will be calculating an expected value based upon this decision tree. The second will be for a basic risk or event where you will be creating a fault or event tree illustrating what makes up the fault or event. With each of these, you will need to discuss the process and results of your tree.
The risks or events you use will be from the project you used in the part one. You will need to start the report with a short introduction of that project so that there is continuity and the reader will understand the events and risks being discussed. You do not have to include part one in your part two report.
Details:
Create one decision tree with an expected value and a fault or event tree that would support the exploration of risk for the project you used for part one of the course project. (That is two trees in all.) Provide a one paragraph project description of the part 1 project but you do not have to repeat all the other information in this part.
•The decision tree must be created to support a major risk-related decision likely to be faced by the project. The calculation of expected values is a requirement of this project.
•The fault or event tree should offer at a minimum a listing of potential risks and impacts in the event of a smaller failure.
For example, a smaller failure could be the loss of water pressure or a fire in a construction project rather than examining what risk was involved with the collapse of the construction project.
Write a discussion of the risks that supports the fault tree, event tree, or decision tree that has been created. Make a separate write up for each of these smaller risks associated with the fault tree or event trees. Your paper should have a general introduction that should introduce the decision tree and fault or event trees that will be discussed, and then the paper should have a discussion regarding each tree. See the sample outline below for details.
The part 2 paper regarding the identified risks and decision trees should be from six to ten pages in length. Note that this page length is a guideline.
At leastthree authoritative, outside references are required (anonymous authors or web pages are not acceptable). These should be referenced where used in the paper and listed on the last page titled, Works Cited.
Risks such as “project is over budget” or “project does not meet schedule” are too broad. Be specific.
Comments on how to create an acceptable tree and project paper
Each fault or event tree should offer at a minimum a listing of two or more potential risks and impacts in the event of two smaller failures. (This means for each tree you will have at a minimum two sub-faults with multiple causes for each of them.)
Use “and” and “or” gates properly. Understand the difference. When you use an ‘and’ gate it indicates that it take both of the conditions for the fault to occur. If either of the conditions could cause a problem this indicates the use of an ‘or’ gate.
There are examples and templates in doc sharing.
You need to select specific faults to use in the tree. General examples of faults are too broad for the fault tree to provide a comprehensive evaluation of the possible causes.
The graphics for the tree do not have to be artist professional quality but they do need to be student professional. A table is not sufficient. If you use screen shots be sure you crop them so that only the tree is included not all the computer menus and etc.
You should have at least two options under each gate. There is no reason for a gate if there is only one option.
When a template is provided or an example it is not meant to be copied. If you are not doing a construction project, your headings should not be “construction project” just because the example says that.
This is a risk management course. The engineering solutions to the problems on these projects are not the answer that you should be developing. The development is of the risk management system and process for your specific project.
Check this A+ tutorial guideline at
http://www.assignmentcloud.com/proj-595-devry/proj-595-week-6-course-project
For more classes visit
http://www.assignmentcloud.com