Programme and Planning Flashcards

1
Q

What are the names of each stage identified in the RIBA Plan of Work?

A

Stage 0 - Strategic Definition
Stage 1 - Preparation and Briefing
Stage 2 - Concept Design
Stage 3 - Spatial Coordination
Stage 4 - Technical Design
Stage 5 - Manufacturing and Construction
Stage 6 - Handover
Stage 7 - Use

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do we have the RIBA Plan of Work?

A
  • The RIBA Plan of Work organises the process of briefing, designing, constructing and operating building projects into eight stages.
  • The Plan of Work explains outcomes, core tasks and information exchanges required at each stage.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a programme, and why do we need one for a construction project?

A
  • The programme should reflect the scope of work, identify activities and sequence those activities efficiently; a well-executed construction programme outlines each step and provides dates for completion.
  • Maintaining an effective programme is key to identifying potential risks, minimising delays and ensuring the project is completed on time.
  • The programme is used to both plan work and monitor progress.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What information does a programme typically show?

A
  • Activities and their sequencing.
  • Activity duration including the start and finish dates.
  • Activity dependencies.
  • Milestones (key dates).
  • Float and lag.
  • Critical path.
  • Current and predicted progress.
  • The programme can also be used to predict cash flow and resource requirements (plant and labour).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is programme float?

A

Float is the amount of time an activity can be delayed without delaying the subsequent activity or critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is lag between activities?

A

When the first activity completes and there is a delay before the second activity starts, this is called lag.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Can you provide a working example of lag on a new build project?

A

Once a concrete foundation is laid, there will be lag prior to erecting steelwork (to allow the concrete to cure/harden)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the critical path on a programme?

A
  • The critical path is the longest sequence of activities that must be completed to successfully conclude
    a project.
  • Activities on the critical path are known as critical activities because if they’re delayed, the whole project will be delayed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can critical path activities have float?

A

Critical path activities have no float. If critical path activities are delayed, the overall completion of the project will be delayed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are milestones?

A

A project milestone is a task of zero duration that shows an important achievement in a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Please provide examples of typical programme milestones for a new build construction project?

A
  • Planning permission granted.
  • RIBA Stage 3 complete.
  • Contractor appointed.
  • Start on site.
  • Building watertight.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the difference between a jagged and a straight drop line on a programme?

A

Jagged drop line:
- Progress as a percentage is entered for each task. This shows activities which are on, behind or ahead on the reporting date

Straight drop line:
- After progress is entered, the programme is rescheduled so each task sits on the progress reporting date (this straightens the drop line).
- It is useful to determine the impact on the critical path.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How would you put together a programme for a new project?

A
  • I would first understand the purpose of the programme and the level of detail required.
  • Identify all activities to be completed, project deliverables, contractual requirements and key milestones (consulting with the project team and stakeholders where required).
  • Assign durations to each activity.
  • Summarise activities into RIBA Stages.
  • Identify relationships between activities and link them accordingly.
  • Identify float and the critical path in the programme.
  • Issue the programme to the team for comment, adjust as required.
  • Monitor and review.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a concurrent delay?

A

Two or more delays caused by different parties occur independently of each other, but during the same period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the benefit of assigning resources to specific programme activities?

A
  • Assigning resources such as plant and labour to each activity allows a resource profile to be built.
  • This ultimately identifies resource requirements for the project and/or pinch points.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is acceleration in programming terms?

A

Acceleration means completing the works in a shorter period or mitigating some form of delay (and completing on the original date).

17
Q

What options may be considered to facilitate acceleration?

A
  • Re-sequencing works (activities are reprogrammed and completed in parallel).
  • Working longer hours (evenings and weekends).
  • Increasing resources (more labour and/or equipment).
  • Adopting alternative construction methods, such as off-site manufacturing.
  • Changing the design or specification (improving lead time, etc.).
  • Reducing the scope of the works.
18
Q

What is a Gantt Chart?

A
  • A Gantt chart is a project management tool that illustrates work completed over a period of time in relation to the time planned for the work.
  • A Gantt chart can include the start and end dates of tasks, milestones, dependencies between tasks, assignees, and more.