Procurement and Tendering Flashcards

1
Q

What is procurement?

A
  • The overall act of obtaining goods and services for a construction project.
  • There are several routes by which the design and construction of a building can be procured. The selected procurement route should follow a strategy which fits the project criteria and objectives.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the main factors that typically govern procurement route selection?

A
  • The key is to identify the client’s objectives and key drivers in terms of time, cost and quality. Other factors such as risk allocation should also be considered.
  • It’s unusual to satisfy all these elements with one procurement route. Consideration must be given to the client’s list of priorities to identify the most appropriate procurement route.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which procurement options are you familiar with?

A
  • Traditional procurement
  • Design & Build
  • Management contracting
  • Construction management
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is traditional procurement?

A

The traditional procurement route involves separating design from construction. The employer first appoints consultants to design the project in detail, contractors are then invited to submit tenders based on a fully developed scheme.

Key points:
- the design is completed by the employer’s design team before competitive tenders are invited. The contractor is then appointed to build what the designers have specified.
- the contractors tender on a complete design produced by the employer’s consultants (with the exception of Contractor’s Design Portions).
- The employer retains the design consultants during construction. The consultants prepare any additional design information and review CDP designs prepared by the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the key advantages of traditional procurement?

A
  • The employer retains control of the design
  • The design is largely finalised before the contractor’s tender for the build, which means the employer knows exactly what they are getting.
  • All tenderers produce a submission based on the same information (tender returns are much easier to compare).
  • Assuming the design is robust, reasonable price certainty is achieved at contract award
  • Minimal built-in contractor risk premium (unlike design & build)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the key disadvantages of traditional procurement?

A
  • The overall project duration may be longer than design and build procurement (limited opportunity to overlap design and construction phase).
  • Zero or limited contractor buildability input
  • Design risk is retained by the employer, any changes post contract will be a variation or compensation event
  • Dual point of responsibility (employer for design and contractor for construction)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When might traditional procurement be appropriate?

A
  • The employer may have specific or detailed design requirements
  • Cost certainty is important (traditional procurement has significant advantages over construction management or management contracting procurement routes).
  • The shortest overall programme is not the employer’s main priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Design & Build?

A

The contractor is responsible for completing the design and executing the construction phase of the project. This is a completely different approach to delivering a project via traditional procurement, where the client appoints consultants to undertake the design and then a contractor is appointed to construct the works.

Key points:
- Under JCT contracts, the employer’s team produces a set of employer’s requirements (ERs), the contractor then responds to the ERs with their contractor’s proposals (CPs).
- The original employer’s design team may be novated to the contractor for continuity, or the contractor may appoint their own design team.
- The contractor is responsible for the design, planning, organisation, control and construction of the works.
- Design risk is transferred to the contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the key advantages of design & build?

A
  • Single point of responsibility for design and construction (contractor).
  • Earlier commencement on site is possible (if design and construction can be overlapped)
  • Benefit of the contractor’s experience harnessed during design (buildability input)
  • Design and construction risk rest with the contractor
  • Provides more cost certainty than traditional procurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the key disadvantages of design & build?

A
  • The design is only as good as the employer’s requirements (the employer may find it difficult to prepare a sufficiently comprehensive brief)
  • More complex to compare tender returns
  • Employer changes can be difficult to value and expensive
  • The employer may have less control over aesthetics and quality
  • The contractor will build risk premiums into their tender returns
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When might design & build be appropriate?

A
  • Where there is a need to make an early start on site (D&B has the potential to overlap design and construction).
  • Where the employer wishes to minimise their risk profile (design risk is passed onto the contractor)
  • For technically complex projects, the design will benefit from the contractor’s buildability input
  • Where retaining control of the design is not a priority
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What additional insurance might be required under a D&B contract?

A

The contractor and their design team will have design responsibility; therefore, it is likely that additional professional indemnity (PII) will be required.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are employer’s requirements (ERs)?

A

The expression employer’s requirements are used to describe the document(s) produced by the employer to set out its requirements in relation to the project (including performance specifications, drawings, initial designs, etc) and this is what the design and construction of the works will be based on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are contractor’s proposals (CPs)?

A
  • CPs are prepared by the contractor which respond to the employer’s requirements
  • In this document(s), the contractor will produce detailed design information (based on the employer’s requirements), which will require further development throughout the course of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which procurement route poses the least risk to the employer?

A

Design & build, this is because the design risk is transferred to the contractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Why does the employer usually pay a premium for design & build procurement at tender stage?

A

The contractor will usually factor in an allowance within their tender return in exchange for taking on the design risk.

17
Q

Under design and build, who executes the design for the contractor?

A

The contractor may use their own in-house designers, or they can appoint external consultants. The employer’s original design team can also be novated to the contractor.

18
Q

What is construction management?

A

The employer directly appoints multiple subcontractors (referred to as trade contractors) instead of employing a single main contractor. The single feature that makes construction management unique, particularly from management contracting, is that the employer places individual contracts with separate specialist trade contractors themselves.

Key points:
- the employer places a direct contract with each trade contractor and utilise the expertise of a construction manager to coordinate the works.
- The construction manager programmes and coordinates the works
- The construction manager has no contractual relationship with the trade contractors
- The construction manager has no vested interest in the financial outcomes of the project and, barring professional negligence, carries no risk

19
Q

What are the key advantages of construction management?

A
  • Speed (early start on site)
  • The overall project duration could be reduced by overlapping design and construction
  • the construction manager can contribute to the design and project planning processes
  • Changes in design can be accommodated without paying a premium
  • Prices may be lower due to direct contracts with trade contractors
  • The employer has means of redress with trade contractors through direct contractual links
20
Q

What are the key disadvantages of construction management?

A
  • Price certainty is not achieved until the last trade package is let
  • The procurement route requires an informed, experienced and proactive employer/client to function efficiently
  • the employer has a lot of consultants and contractors to manage
21
Q

When might construction management be appropriate?

A
  • The employer is experienced in construction and has suitable resources to manage the project.
  • The employer wants to achieve an early start on site
  • The employer wants the flexibility to make minor changes to the design / specification throughout the process with minimal impact on time or finances
  • The project is technically complex and requires detailed engagement of specialists consultants and trade contractors
22
Q

What is the riskiest procurement route for the employer?

A

Construction management. This is because the employer places individual contracts directly with each trade contractor and the construction manager carries no risk (barring professional negligence)

23
Q

What is management contracting?

A
  • The employer appoints a management contractor to manage the entire building process, who in turn appoints trade contractors to carry out the construction works
  • The management contractor is usually paid a fee percentage based on construction costs
  • The management contractor has a direct contractual link with the trade contractors and is responsible for the overall construction works.
24
Q

What are the key advantages of management contracting?

A
  • Overall project duration can be reduced by overlapping design and construction
  • The management contractor will provide buildability input
  • Single point of responsibility (management contractor)
  • Trade packages are let competitively and transparently
  • There can be considerable flexibility in the design, with changes being made throughout the construction process.
25
Q

What are the key disadvantages of management contracting?

A
  • Price certainty is not achieved until the last trade package is let.
  • Requires an informed and proactive employer to be successful
  • Depending on how the construction manager is renumerated, there may be a built-in disincentive for the construction manager to minimise costs
26
Q

When might management contracting be appropriate?

A
  • When an early start on site is a priority
  • Flexibility in design is required
  • Buildability input from the management contractor is required
  • Where cost certainty is not a priority for the employer
27
Q
A